Permit: T06CM04893
Permit Details
Apply Date:
09/01/2006
Applicant:
BARRY COLEMAN
Description:
SFR:NEW
Contractors:
- COLEMAN CONSTRUCTION AND DESIGN L L C
Permit Reviews
Permit Number - T06CM04893
Permit Status: Final
Permit Description: SFR:NEW
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
01/12/2007 | RESUBMITTAL | 02/12/2007 | COMPLETED |
02/12/2007 | RESUBMITTAL | 02/13/2007 | COMPLETED |
02/13/2007 | RESUBMITTAL | 04/11/2007 | COMPLETED |
06/15/2007 | REVISION - - 1ST | 06/15/2007 | COMPLETED |
06/15/2007 | REVISION - - 1ST | 06/29/2007 | COMPLETED |
09/01/2006 | PLANS OK TO SUBMIT - RES | 09/11/2006 | COMPLETED |
09/11/2006 | RESIDENTIAL BLDG/ZONING/ENGINE/WWM | 10/16/2006 | COMPLETED |
10/15/2007 | REVISION - - 2ND | 10/15/2007 | ACTIVE |
12/07/2006 | RESUBMITTAL | 01/02/2007 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T06CM04893
Permit Status: Final
Permit Description: SFR:NEW
Total Outstanding Activity Conditions - 1
Date | Name |
---|---|
09/01/2006 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: Final
Permit Number: T06CM04893
Permit Description: SFR:NEW
Total Completed Inspections - 26
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
05/14/2007 | PLUMBING - SEWER HCS CONNECT | CRUIZ | Approved | IVRS - Inspection :* |
05/24/2007 | ELECTRIC - UFER | CRUIZ | Approved | |
05/24/2007 | EXCAVATION/LAYOUT REBAR & ZON | CRUIZ | Approved | IVRS - Inspection :* |
08/08/2007 | REINFORCED MASONRY PRE-GROUT | CRUIZ | Approved | IVRS - Inspection :* |
08/16/2007 | ELECTRIC - UNDERGROUND | CRUIZ | Approved | IVRS - Inspection :* |
08/22/2007 | PLUMBING - YARD WTR LINE/TEST | CRUIZ | Approved | IVRS - Inspection :* |
08/29/2007 | ROOF NAILING | DWALKER | Approved | IVRS - Inspection :* |
09/05/2007 | PLUMBING - ROUGH, SOIL | CRUIZ | Approved | |
09/12/2007 | ELECTRIC - TEMPORARY SERVICE | CRUIZ | Approved | IVRS - Inspection :* |
09/12/2007 | ELECTRIC - CABLE DROP | CRUIZ | Approved | IVRS - Inspection :* |
09/13/2007 | TEP CLEARANCE - AM | JWEATHER | Approved | ECO CLEARED PER C. RUIZ |
10/31/2007 | BUILDING PRE-SLAB | CRUIZ | Approved | IVRS - Inspection :* 1) OK TO POUR BACK TWO STEEL COLUMN FOOTINGS, WAITING ON REVISION FOR BOLTS FOR THE FRONT TWO COLUMN FOOTERS |
12/14/2007 | PLUMBING - GAS PRESSURE TEST | CRUIZ | Approved | IVRS - Inspection : See detailed listing on site.| 999* |
12/14/2007 | MECHANICAL - INTERMEDIATE | CRUIZ | Approved | IVRS - Inspection : See detailed listing on site.| 999* |
12/14/2007 | PLUMBING - INTERMEDIATE | CRUIZ | Approved | IVRS - Inspection : See detailed listing on site.| 999* |
12/14/2007 | ELECTRIC - INTERMEDIATE | CRUIZ | Approved | IVRS - Inspection : See detailed listing on site.| 999* |
12/21/2007 | FRAMING | CRUIZ | Approved | IVRS - Inspection :* INSPECTED GUEST HOUSE ONLY OK TO INSULATE AND SHEETROCK |
12/31/2007 | SHEET ROCK NAILING | RFREIDIN | Approved | IVRS - Inspection :* 1) GARAGE (GUEST HOUSE) 2) GARAGE DRYWALL ONLY. 5/8" X ON LID (GUEST HOUSE) |
01/02/2008 | ASSURANCE | MCARREON | Approved | DRAINAGE TO BE INSPECTED FOR ENTIRE SITE AT TIME OF FINAL GRADING. |
09/19/2008 | MECHANICAL - FINAL | CRUIZ | Approved | IVRS - Inspection :* |
09/24/2008 | BUILDING - FINAL | CRUIZ | Approved | IVRS - Inspection :* 1) INSULATION CERT NOT NEEDED ICF SYSTEM |
09/24/2008 | STEM WALL/RETAINING WALL | CRUIZ | Approved | |
09/24/2008 | PLUMBING - FINAL | CRUIZ | Approved | |
09/24/2008 | ELECTRIC - FINAL | CRUIZ | Approved | |
09/24/2008 | U VALUE FOR WINDOW | CRUIZ | Approved | |
09/26/2008 | PERMIT FINALED | JWEATHER | Approved |