Permit: T06CM04619
Permit Details
Status:
Final
Type:
SINGLE FAMILY ADDITION
Address:
2809 E ALTA VISTA ST
Address NEW:
2809 E ALTA VISTA ST
Apply Date:
08/16/2006
Applicant:
PAULA HOLMES
Description:
ADDITION: MASTER BEDROOM, BATH & CARPORT R1 Revise kitchen plan R2 Replace all electrical
Contractors:
- HOYER KIMURA INC
Permit Reviews
Permit Number - T06CM04619
Permit Status: Final
Permit Description: ADDITION: MASTER BEDROOM, BATH & CARPORT
R1 Revise kitchen plan
R2 Replace all electrical
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 03/29/2007 | REVISION - - 1ST | 03/29/2007 | COMPLETED |
| 05/02/2007 | REVISION - - 2ND | 05/02/2007 | COMPLETED |
| 08/16/2006 | PLANS OK TO SUBMIT - RES | 09/07/2006 | COMPLETED |
| 09/07/2006 | RESIDENTIAL BLDG/WWM | 10/13/2006 | COMPLETED |
| 10/24/2006 | RESUBMITTAL | 11/22/2006 | COMPLETED |
| 11/27/2006 | RESUBMITTAL | 01/02/2007 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T06CM04619
Permit Status: Final
Permit Description: ADDITION: MASTER BEDROOM, BATH & CARPORT
R1 Revise kitchen plan
R2 Replace all electrical
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 08/16/2006 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: Final
Permit Number: T06CM04619
Permit Description: ADDITION: MASTER BEDROOM, BATH & CARPORT
R1 Revise kitchen plan
R2 Replace all electrical
Total Completed Inspections - 24
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 12/19/2006 | PLUMBING - SEWER HCS CONNECT | RCAMACHO | Approved | IVRS - Inspection :* |
| 12/19/2006 | PLUMBING - ROUGH, SOIL | RCAMACHO | Approved | IVRS - Inspection :* |
| 12/28/2006 | BUILDING PRE-SLAB | CRUIZ | Approved | IVRS - Inspection :* |
| 12/28/2006 | EXCAVATION/LAYOUT REBAR & ZON | CRUIZ | Approved | IVRS - Inspection :* |
| 02/23/2007 | ROOF NAILING | CTREVILL | Approved | IVRS - Inspection :* |
| 03/23/2007 | U VALUE FOR WINDOW | RCAMACHO | Approved | IVRS - Inspection :* |
| 04/03/2007 | EXT METAL CLIPS/EXT SHEATHING | RCAMACHO | Approved | IVRS - Inspection :* |
| 04/12/2007 | MECHANICAL - INTERMEDIATE | RCAMACHO | Approved | IVRS - Inspection :* |
| 04/12/2007 | STUCCO MESH | RCAMACHO | Approved | IVRS - Inspection :* |
| 04/24/2007 | ELECTRIC - SERVICE UPGRADE | ROHAVER | Approved | IVRS - Inspection :* |
| 04/25/2007 | TEP CLEARANCE - AM | JWEATHER | Approved | INCR CLEARED PER R. O'HAVER |
| 05/04/2007 | PLUMBING - GAS PRESSURE TEST | RCAMACHO | Approved | IVRS - Inspection :* |
| 05/04/2007 | PLUMBING - INTERMEDIATE | RCAMACHO | Approved | IVRS - Inspection :* |
| 05/04/2007 | ELECTRIC - INTERMEDIATE | RCAMACHO | Approved | IVRS - Inspection :* |
| 05/04/2007 | FRAMING | RCAMACHO | Approved | IVRS - Inspection :* |
| 05/15/2007 | SHEET ROCK NAILING | RCAMACHO | Approved | IVRS - Inspection :* |
| 07/18/2007 | MECHANICAL - FINAL | RCAMACHO | Approved | IVRS - Inspection :* |
| 07/18/2007 | PLUMBING - YARD WTR LINE/TEST | RCAMACHO | Approved | IVRS - Inspection :* |
| 07/18/2007 | PLUMBING - YARD WTR LINE/TEST | IVR USER | Approved | IVRS - RI canceled |
| 07/25/2007 | OUTDOOR LIGHTING FINAL | DQUINN | Approved | IVRS - Inspection :* |
| 10/22/2007 | PLUMBING - FINAL | DWALKER | Approved | IVRS - Inspection :* |
| 10/22/2007 | ELECTRIC - FINAL | DWALKER | Approved | IVRS - Inspection :* |
| 10/22/2007 | BUILDING - FINAL | DWALKER | Approved | IVRS - Inspection :* |
| 10/23/2007 | PERMIT FINALED | JWEATHER | Approved |