Permit Reviews
Permit Number - T06CM04085
Permit Status: C of o
Permit Description: TI:CLASSROOM
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
01/23/2007 | 3RD PARTY REVIEW-REVISION/OTHER | 01/23/2007 | COMPLETED |
07/13/2006 | PLANS OK TO SUBMIT - 3RD PARTY | 07/26/2006 | COMPLETED |
07/26/2006 | 3RD PARTY REVIEW-COMMERCIAL TI | 08/31/2006 | COMPLETED |
08/31/2006 | POST 3RD PARTY REVIEW | 12/04/2006 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T06CM04085
Permit Status: C of o
Permit Description: TI:CLASSROOM
Total Outstanding Activity Conditions - 1
Date | Name |
---|---|
07/12/2006 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T06CM04085
Permit Description: TI:CLASSROOM
Total Completed Inspections - 34
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
09/29/2006 | PLUMBING - PRE SLAB | RMYERS | Approved | IVRS - Inspection :* |
09/29/2006 | PLUMBING - ROUGH, SOIL | RMYERS | Approved | IVRS - Inspection :* |
10/18/2006 | FRAMING | AQUIROZ | Approved | IVRS - Inspection :* EXCLUDES RESTROOM, DOES NOT MEET ACCESSIBLE REQUIREMENTS. |
10/19/2006 | PLUMBING - INTERMEDIATE | RMYERS | Approved | IVRS - Inspection :* OK TO COVER ALL AREAS |
10/19/2006 | PLUMBING - GAS PRESSURE TEST | RMYERS | Approved | IVRS - Inspection :* |
10/19/2006 | PLUMBING - YARD WTR LINE/TEST | RMYERS | Approved | IVRS - Inspection :* |
10/24/2006 | SHEET ROCK NAILING | AQUIROZ | Approved | IVRS - Inspection :* EXCLUDES RESTROOM |
11/06/2006 | ELECTRIC - SERVICE RELOCATION | CCLEMENS | Approved | IVRS - Inspection : The service is not per code.| 210* 1. INSTALL ADDRESS ON SERVICE. 2. PROVIDE FLASHING FOR MAST @ ROOF PENETRATION 3. TIGHTEN ALL RACEWAY FITTINGS. 4. BOND GAS PIPING FOR UNIT (NOT GAS MAIN) 5. BOND UNIT'S WATER PIPE 6. SECURE GROUNDING ELECTRODE CONDUCTOR TO STRUCTURE OR BURY MINIMUM 12" 7. NEED MINIMUM 3 0 COPPER FOR SERVICE CONDUCTORS (HOT'S) 8. IDENTIFY ALL NEUTRALS AT TERMINATIONS AND CLOSE TO WEATHERHEAD. 9. IDENTIFY SERVICE DISCONNECT. 10. WALL AT SUB-PANEL COVERED WITHOUT INSPECTION. 11. TIGHTEN ALL BUSHINGS AND SET SCREWS. |
11/06/2006 | ELECTRIC - CABLE DROP | CCLEMENS | Approved | IVRS - Inspection : The service is not per code.| 210* |
11/29/2006 | MECHANICAL - INTERMEDIATE | AQUIROZ | Approved | IVRS - Inspection :* |
11/29/2006 | BUILDING - PROGRESS | AQUIROZ | Approved | IVRS - Inspection :* |
12/05/2006 | ELECTRIC - INTERMEDIATE | CCLEMENS | Approved | IVRS - Inspection :* 1) OK CEILING COVER-BOND SPRINKLER PIPE |
12/06/2006 | TEP CLEARANCE - AM | JWEATHER | Approved | INCR CLEARED PER C. CLEMENS |
01/16/2007 | RIGHT OF WAY - FINAL | MOTERO | Approved | PER EMAIL |
01/16/2007 | NPPO - FINAL | JLINVILL | Approved | N/A |
01/16/2007 | LANDSCAPE - FINAL | JLINVILL | Approved | N/A |
01/16/2007 | SIGN - FINAL | JYBARRA | Approved | IVRS - Inspection :* |
01/17/2007 | ENGINEERING - FINAL | JBRUCKME | Approved | |
01/23/2007 | MECHANICAL - FINAL | JMILITEL | Approved | IVRS - Inspection :* OK FOR FINAL |
01/24/2007 | MECHANICAL - PROGRESS | JMILITEL | Approved | |
01/24/2007 | PLUMBING - SEWER HCS CONNECT | RMYERS | Approved | IVRS - Inspection :* |
01/26/2007 | PLUMBING - FINAL | RMYERS | Approved | IVRS - Inspection :* 1. CORRECTIONS MADE OK AND TO REVISED PLAN 2. PLUMBING FINAL OK OK FOR C OF O S.T.O.I |
01/26/2007 | PLUMBING - GAS PRESS TEST FNL | RMYERS | Approved | IVRS - Inspection :* |
01/31/2007 | ELECTRIC - UFER | CCLEMENS | Approved | |
01/31/2007 | BUILDING - FINAL | AQUIROZ | Approved | IVRS - Inspection :* OK C OF O |
01/31/2007 | BUILDING PRE-SLAB | AQUIROZ | Approved | IVRS - Inspection :* |
01/31/2007 | ELECTRIC - FINAL | CCLEMENS | Approved | IVRS - Inspection :* |
01/31/2007 | ELECTRIC - SERVICE UPGRADE | CCLEMENS | Approved | IVRS - Inspection :* |
01/31/2007 | ELECTRIC - TEMP POWER FOR TEST | CCLEMENS | Approved | IVRS - Inspection :* |
01/31/2007 | ELECTRIC - CONSTRUCTION POWER | CCLEMENS | Approved | IVRS - Inspection :* |
01/31/2007 | ELECTRIC - UFER | CCLEMENS | Approved | IVRS - Inspection :* |
02/01/2007 | FIRE - ALARM FINAL | LTHOMAS | Approved | |
02/01/2007 | FIRE SPKLR - FINAL | LTHOMAS | Approved | |
02/01/2007 | FIRE - FINAL | LTHOMAS | Approved |