Permit: T06CM03227
Permit Details
Apply Date:
05/30/2006
Applicant:
C N C DESIGN & CONSTRUCTION
Description:
ADDITION:MECH STORAGE & TI:DENTAL OFFICE & CHANGE OF USE
Contractors:
- C N C DESIGN & CONSTRUCTION
Permit Reviews
Permit Number - T06CM03227
Permit Status: C of o
Permit Description: ADDITION:MECH STORAGE & TI:DENTAL OFFICE & CHANGE OF USE
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 05/30/2006 | PLANS OK TO SUBMIT - COMM | 07/20/2006 | COMPLETED |
| 05/30/2006 | PLANS OK TO SUBMIT - SITE | 08/23/2006 | COMPLETED |
| 07/21/2006 | 3RD PARTY REVIEW-COMMERCIAL TI | 09/22/2006 | COMPLETED |
| 08/22/2006 | POST 3RD PARTY REVIEW | 09/22/2006 | COMPLETED |
| 09/22/2006 | 3RD PARTY REVIEW-REVISION/OTHER | 09/22/2006 | COMPLETED |
| 12/15/2006 | 3RD PARTY REVIEW-REVISION/OTHER | 12/19/2006 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T06CM03227
Permit Status: C of o
Permit Description: ADDITION:MECH STORAGE & TI:DENTAL OFFICE & CHANGE OF USE
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 05/30/2006 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T06CM03227
Permit Description: ADDITION:MECH STORAGE & TI:DENTAL OFFICE & CHANGE OF USE
Total Completed Inspections - 36
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 08/31/2006 | PLUMBING - YARD WTR LINE/TEST | RLEDONNE | Approved | IVRS - Inspection :* 1. PROVIDE VACUUM BREAKER AT HOSE BIBB 2. PLUMBING ROUGH & SOIL OK PER REDLINE HAVE APPROVED DRAWING ON SITE FROM CITY. AND WATER DRAWING NEED RED LINES. |
| 09/12/2006 | ELECTRIC - CABLE DROP | DSANTACR | Approved | 1. OK BELOW SLAB INSIDE BLD. 2. OK SECONDARYS FROM CT TO PULL BOX. |
| 09/13/2006 | BUILDING PRE-SLAB | AALEGRIA | Approved | IVRS - Inspection :* IN COMPLIANCE WITH APPROVED PLANS SHEET S/O DETAILS 12, 13 |
| 09/13/2006 | PLUMBING - PRE SLAB | RLEDONNE | Approved | IVRS - Inspection :* |
| 09/29/2006 | ELECTRIC - UFER | DSANTACR | Approved | IVRS - Inspection :* |
| 10/03/2006 | EXCAVATION/LAYOUT REBAR & ZON | AALEGRIA | Approved | IVRS - Inspection :* IN COMPLIANCE WITH APP. PLANS |
| 10/09/2006 | REINFORCED MASONRY PRE-GROUT | AALEGRIA | Approved | IVRS - Inspection :* IN COMPLIANCE WITH APPROVED PLANS REAR WALL DETAIL 4 ON SHEET S2 |
| 11/09/2006 | PLUMBING - ROUGH, SOIL | RLEDONNE | Approved | IVRS - Inspection :* 1. HCS TIE IN PROVIDE DRAWING AND ACTIVITY NUMBER ON ACTIVITY CARD. 2. TEST ON HCS HOLDING TO TWO WAY CLEANOUT'S AT BUILDING. |
| 11/09/2006 | ROOF NAILING | AALEGRIA | Approved | IVRS - Inspection :* |
| 11/15/2006 | PLUMBING - GAS PRESSURE TEST | RLEDONNE | Approved | IVRS - Inspection :* |
| 11/20/2006 | ELECTRIC - ABOVE CEILING | DSANTACR | Approved | IVRS - Inspection :* |
| 11/21/2006 | ELECTRIC - INTERMEDIATE | DSANTACR | Approved | IVRS - Inspection :* |
| 11/22/2006 | BUILDING ABOVE CEILING | AALEGRIA | Approved | IVRS - Inspection :* |
| 11/22/2006 | STUCCO MESH | AALEGRIA | Approved | IVRS - Inspection :* |
| 11/22/2006 | FRAMING | AALEGRIA | Approved | IVRS - Inspection :* |
| 11/24/2006 | PLUMBING - INTERMEDIATE | RLEDONNE | Approved | IVRS - Inspection :* PROVIDE REVISED DRAWINGS THAT ARE APPROVED |
| 11/24/2006 | PLUMBING - ABOVE CEILING | RLEDONNE | Approved | IVRS - Inspection :* |
| 11/28/2006 | MECHANICAL - ABOVE CEILING | AALEGRIA | Approved | IVRS - Inspection :* |
| 11/28/2006 | MECHANICAL - INTERMEDIATE | AALEGRIA | Approved | IVRS - Inspection :* |
| 12/05/2006 | SHEET ROCK NAILING | AALEGRIA | Approved | IVRS - Inspection :* |
| 12/18/2006 | ELECTRIC - OUTDOOR LIGHTING | DSANTACR | Approved | IVRS - Inspection :* 1) NO BOND REQUIRED-EXISTING BLDG WITH SERVICE INCREASE ONLY |
| 12/19/2006 | TEP CLEARANCE - AM | JWEATHER | Approved | INCR FOR MAIN SERVICE TO BLDG PER D. SANTACRUZ |
| 02/01/2007 | PLUMBING - FINAL | RLEDONNE | Approved | IVRS - Inspection :* |
| 02/01/2007 | PLUMBING - GAS PRESS TEST FNL | RLEDONNE | Approved | IVRS - Inspection :* |
| 02/05/2007 | ELECTRIC - FINAL | DSANTACR | Approved | |
| 02/20/2007 | BUILDING - FINAL | AALEGRIA | Approved | IVRS - Inspection :* |
| 02/21/2007 | MECHANICAL - FINAL | JMILITEL | Approved | IVRS - Inspection :* |
| 02/21/2007 | ENGINEERING - FINAL | MAVERY | Approved | Contractor needs to black out front parking striping. |
| 02/21/2007 | RIGHT OF WAY - FINAL | LLOPEZ | Approved | PER EMAIL |
| 02/21/2007 | OUTDOOR LIGHTING FINAL | DSANTACR | Approved | |
| 02/21/2007 | STEM WALL/RETAINING WALL | AALEGRIA | Approved | |
| 02/21/2007 | NPPO - FINAL | ACONNOR | Approved | |
| 02/21/2007 | LANDSCAPE - FINAL | ACONNOR | Approved | |
| 02/21/2007 | SIGN - FINAL | JYBARRA | Approved | IVRS - Inspection :* |
| 02/21/2007 | FIRE - FINAL | CSCHULTZ | Approved | |
| 02/22/2007 | PERMIT FINALED | BFLORES | Approved |