Permit: T06CM03000
Permit Details
Status:
C of o
Type:
MULTI FAMILY NEW
Address:
2921 N GERONIMO AV #07
Address NEW:
2921 N GERONIMO AV #07
Apply Date:
05/19/2006
Applicant:
N/A
Description:
NEW: APARTMENT BUILDING
Architects:
- LANNING, ROBERT SCOTT
Contractors:
- ODEN CONSTRUCTION INC
Permit Reviews
Permit Number - T06CM03000
Permit Status: C of o
Permit Description: NEW: APARTMENT BUILDING
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 05/19/2006 | PLANS OK TO SUBMIT - COMM | 06/16/2006 | COMPLETED |
| 06/16/2006 | 3RD PARTY REVIEW-COMMERCIAL | 08/08/2006 | COMPLETED |
| 08/08/2006 | POST 3RD PARTY REVIEW | 08/25/2006 | COMPLETED |
| 08/29/2006 | RESUBMITTAL | 01/02/2007 | COMPLETED |
| 11/07/2007 | REVISION - - 1ST | 11/07/2007 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T06CM03000
Permit Status: C of o
Permit Description: NEW: APARTMENT BUILDING
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 05/19/2006 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T06CM03000
Permit Description: NEW: APARTMENT BUILDING
Total Completed Inspections - 37
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 02/21/2007 | PLUMBING - ROUGH, SOIL | BBENEDON | Approved | IVRS - Inspection :* 1. ROUGH SOIL, PVC W/TEST OK WRAPS IN PLACE 2. PLAN SPECS ABS PROVIDE A LETTER FROM LANNING ARCHITECTURE ALLOWING USE OF PVC. |
| 02/28/2007 | EXCAVATION/LAYOUT REBAR & ZON | AQUIROZ | Approved | |
| 03/07/2007 | BUILDING PRE-SLAB | AQUIROZ | Approved | IVRS - Inspection :* |
| 06/11/2007 | ROOF NAILING | AQUIROZ | Approved | IVRS - Inspection :* |
| 06/11/2007 | EXT METAL CLIPS/EXT SHEATHING | AQUIROZ | Approved | IVRS - Inspection :* |
| 06/19/2007 | MECHANICAL - INTERMEDIATE | JMILITEL | Approved | IVRS - Inspection :* OK FOR SHEETROCK |
| 06/19/2007 | U VALUE FOR WINDOW | AQUIROZ | Approved | IVRS - Inspection :* |
| 06/20/2007 | FRAMING | AQUIROZ | Approved | IVRS - Inspection :* MISSING AC SUPPORT BLOCKING |
| 06/20/2007 | ELECTRIC - INTERMEDIATE | CCLEMENS | Approved | IVRS - Inspection :* |
| 06/20/2007 | PLUMBING - GAS PRESSURE TEST | RMYERS | Approved | IVRS - Inspection :* |
| 06/28/2007 | PLUMBING - INTERMEDIATE | RMYERS | Approved | IVRS - Inspection :* 1. ARCHITECT APPROVES CSST 2. PLAN REVIEWER NEEDS TO LOOK AT REDLINED PLAN FOR CODE ACCEPTANCE FOR SIZE AND LENGTH 3. OK TO COVER SUBJECT TO APPROVED PLAN |
| 07/16/2007 | SHEET ROCK NAILING | AQUIROZ | Approved | IVRS - Inspection :* EXCLUDE #3 |
| 11/07/2007 | PLUMBING - YARD WTR LINE/TEST | RMYERS | Approved | IVRS - Inspection :* |
| 11/14/2007 | SITE - SEWER | BBENEDON | Approved | IVRS - Inspection : See detailed listing on site.| 999* DOES PLAN SPECIFY SLOPE? SEE PREVIOUS NOTES HAS PIPING BEEN INSTALLED? |
| 01/10/2008 | PLUMBING - SEWER HCS CONNECT | RMYERS | Approved | IVRS - Inspection :* OK TO COVER SEWER/HCS CALL O3057 AFTER PROPERTY LINE CLEANOUT IS SET |
| 01/15/2008 | ELECTRIC - TEMPORARY SERVICE | CCLEMENS | Approved | IVRS - Inspection :* |
| 01/15/2008 | ELECTRIC - UNDERGROUND | CCLEMENS | Approved | IVRS - Inspection :* |
| 01/17/2008 | PLUMBING - PRE SLAB | RMYERS | Approved | IVRS - Inspection :* |
| 01/22/2008 | ELECTRIC - CABLE DROP | RJIROUDE | Approved | IVRS - Inspection :* |
| 01/23/2008 | TEP CLEARANCE - AM | JWEATHER | Approved | TEC CLEARED FOR 7, 8 & 9 PER R. JIROUDEK |
| 03/13/2008 | OUTDOOR LIGHTING FINAL | CCLEMENS | Approved | IVRS - Inspection :* |
| 03/14/2008 | PLUMBING - GAS PRESS TEST FNL | RMYERS | Approved | IVRS - Inspection :* |
| 03/17/2008 | FIRE SPKLR - FINAL | LTHOMAS | Approved | |
| 03/17/2008 | FIRE - FINAL | LTHOMAS | Approved | |
| 05/27/2008 | MECHANICAL - FINAL | JMILITEL | Approved | IVRS - Inspection :* |
| 05/29/2008 | PLUMBING - FINAL | RMYERS | Approved | |
| 05/29/2008 | ELECTRIC - UFER | CCLEMENS | Approved | |
| 05/29/2008 | ELECTRIC - FINAL | CCLEMENS | Approved | IVRS - Inspection :* |
| 05/29/2008 | ELECTRIC - OUTDOOR LIGHTING | CCLEMENS | Approved | IVRS - Inspection :* |
| 05/30/2008 | BUILDING - FINAL | AQUIROZ | Approved | |
| 05/30/2008 | REINFORCED MASONRY PRE-GROUT | AQUIROZ | Approved | |
| 05/30/2008 | STEM WALL/RETAINING WALL | AQUIROZ | Approved | |
| 06/02/2008 | SIGN - FINAL | JSONKIN | Approved | IVRS - Inspection :* |
| 06/03/2008 | RIGHT OF WAY - FINAL | MOTERO | Approved | PER EMAIL |
| 06/03/2008 | ENGINEERING - FINAL | MRUSSO | Approved | |
| 06/03/2008 | NPPO - FINAL | ACONNOR | Approved | |
| 06/09/2008 | LANDSCAPE - FINAL | ACONNOR | Approved | IVRS - Inspection :* |