Permit: T06CM02119
Permit Details
Status:
Si_xpire
Type:
COMMERCIAL NEW
Address:
10701 E MARY ANN CLEVELAND WY 06
Address NEW:
10701 E MARY ANN CLEVELAND WY 06
Apply Date:
04/13/2006
Applicant:
LLOYD CONSTRUCTION COMPANY INC ,
Description:
NEW RESTROOM BUILDING
Architects:
- SWAIM, PHILLIP ELLIOTT
Contractors:
- LLOYD CONSTRUCTION COMPANY INC ,
Permit Reviews
Permit Number - T06CM02119
Permit Status: Si_xpire
Permit Description: NEW RESTROOM BUILDING
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 04/13/2006 | PLANS OK TO SUBMIT - 3RD PARTY | 04/13/2006 | COMPLETED |
| 04/13/2006 | PLANS OK TO SUBMIT - SITE | 04/13/2006 | COMPLETED |
| 04/13/2006 | 3RD PARTY REVIEW-COMMERCIAL | 06/20/2006 | COMPLETED |
| 06/20/2006 | POST 3RD PARTY REVIEW | 06/26/2006 | COMPLETED |
| 06/20/2006 | SITE | 06/26/2006 | COMPLETED |
| 09/20/2006 | 3RD PARTY REVIEW-REVISION/OTHER | 09/25/2006 | COMPLETED |
| 10/05/2006 | 3RD PARTY REVIEW-REVISION/OTHER | 10/08/2006 | ACTIVE |
Outstanding Activity Conditions
Permit Number - T06CM02119
Permit Status: Si_xpire
Permit Description: NEW RESTROOM BUILDING
Total Outstanding Activity Conditions - 2
| Date | Name |
|---|---|
| 04/13/2006 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
| 06/20/2006 | SPECIAL INSPECTION FOR STRUCTURAL MASONRY IS REQUIRED. |
Completed Inspections
Permit Status: Si_xpire
Permit Number: T06CM02119
Permit Description: NEW RESTROOM BUILDING
Total Completed Inspections - 33
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 07/20/2006 | PLUMBING - YARD WTR LINE/TEST | RRICH | Approved | IVRS - Inspection :* 2 1/2 FROM TIE IN AT EXISTING 4" TO STUB UP AT BUILDING CORNER PER REDLINE WATER TEST OK REVISED CITY APPROVED PLAN TO FOLLOW. |
| 08/04/2006 | ELECTRIC - UFER | RSUBA | Approved | IVRS - Inspection :* |
| 08/15/2006 | EXCAVATION/LAYOUT REBAR & ZON | GDABBS | Approved | IVRS - Inspection :* |
| 08/23/2006 | PLUMBING - ROUGH, SOIL | RRICH | Approved | IVRS - Inspection :* WATER TEST UNDERGROUND THRU BUILDING + 2 WAY CLEANOUT OT 5' EXTERIOR OF BUILDING OK 1. NEED TO SEE CONNECTION TO SITE SEWER. |
| 09/12/2006 | BUILDING PRE-SLAB | GDABBS | Approved | RESTROOM SLAB OK TO POUR |
| 09/12/2006 | PLUMBING - PRE SLAB | RLEDONNE | Approved | |
| 09/19/2006 | REINFORCED MASONRY PRE-GROUT | GDABBS | Approved | IVRS - Inspection :* NEW RESTROOMS -- MASONRY TOP OUT -- OK TO GROUT |
| 09/21/2006 | PLUMBING - SEWER HCS CONNECT | RRICH | Approved | IVRS - Inspection :* |
| 10/06/2006 | ELECTRIC - INTERMEDIATE | RSUBA | Approved | IVRS - Inspection :* BATHROOM CAN LIGHTS (EXTERIOR) HAND DRYERS |
| 10/06/2006 | FRAMING | GDABBS | Approved | IVRS - Inspection :* |
| 10/09/2006 | PLUMBING - INTERMEDIATE | RRICH | Approved | IVRS - Inspection :* |
| 10/11/2006 | ROOF NAILING | GDABBS | Approved | IVRS - Inspection :* |
| 10/11/2006 | EXT METAL CLIPS/EXT SHEATHING | GDABBS | Approved | IVRS - Inspection :* |
| 10/13/2006 | ELECTRIC - OUTDOOR LIGHTING | RSUBA | Approved | IVRS - Inspection :* OK 1 1/2" PVC FROM FENCE TO BUILDING. |
| 10/13/2006 | PLUMBING - ABOVE CEILING | RLEDONNE | Approved | IVRS - Inspection :* 1. FRAMED OUT TEMPORARY VALVE 2. INSULATION ON HOT WATER PIPING OK |
| 10/17/2006 | SHEET ROCK NAILING | GDABBS | Approved | IVRS - Inspection :* |
| 10/26/2006 | MECHANICAL - INTERMEDIATE | JMILITEL | Approved | IVRS - Inspection :* |
| 11/16/2006 | MECHANICAL - FINAL | JMILITEL | Approved | IVRS - Inspection :* |
| 11/17/2006 | BUILDING - FINAL | GDABBS | Approved | IVRS - Inspection : See detailed listing on site.| 999* FOUR NON ADA TOILET STALL DOORS NEED TO BE LOCATED SO AS NOT TO PASS OVER THE TOILET. WHEN OPENED IN THE WOMEN'S RESTROOM. |
| 11/17/2006 | ELECTRIC - FINAL | RMAJUTA | Approved | IVRS - Inspection :* NEED REJECT PINS IN DISCONNECT AFTER TRANSFORMER. |
| 11/17/2006 | ELECTRIC - FINAL | RMAJUTA | Approved | IVRS - Inspection : See detailed listing on site.| 999* 1. RESTROOM STRUCTURE - OK NEED TO LOOK AT 480V TRANSFORMER CONNECTIONS AND TRANSFORMER TIE INTO GEAR. WILL NEED WITH RMS ON REST OF UNDERGROUND WILL NEED REJECT PINS AT DISCONNECT |
| 11/17/2006 | OUTDOOR LIGHTING FINAL | RMAJUTA | Approved | IVRS - Inspection :* |
| 11/21/2006 | PLUMBING - FINAL | RRICH | Approved | IVRS - Inspection :* 03005 -- APPROVED 03040 -- PROVIDE APPROVED PLAN AS REQUESTED ON 7/20/06 03090 -- 1. SEE NOTES FROM 11/16/06 & COMPLY 2. MANHOLE BASE AT BUILDING SEWER TERMINATION TO BE BUILT UP CORRECTLY TO PROVIDE CORRECT TROUGH. |
| 01/18/2007 | NPPO - FINAL | JLINVILL | Approved | n/a |
| 01/18/2007 | LANDSCAPE - FINAL | JLINVILL | Approved | n/a |
| 01/18/2007 | RIGHT OF WAY - FINAL | SDAMRON | Approved | PER EMAIL |
| 01/18/2007 | ENGINEERING - FINAL | NKALAHAR | Approved | APPROVED HELD T06CM01755/T06CM02125 FOR SITE STABILIZATION |
| 01/18/2007 | SIGN - FINAL | JYBARRA | Approved | IVRS - Inspection :* |
| 01/19/2007 | ELECTRIC - CABLE DROP | RMAJUTA | Approved | |
| 01/19/2007 | ELECTRIC - TEMPORARY SERVICE | RMAJUTA | Approved | |
| 01/19/2007 | ELECTRIC - CONSTRUCTION POWER | RMAJUTA | Approved | |
| 01/19/2007 | U VALUE FOR WINDOW | GDABBS | Approved | |
| 02/05/2007 | FIRE - FINAL | LTHOMAS | Approved |