Permit Reviews
Permit Number - T06CM01754
Permit Status: Si_xpire
Permit Description: TI:RETAIL (METER 1 & 2 )
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
03/29/2006 | COMMERCIAL TI | 03/30/2006 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T06CM01754
Permit Status: Si_xpire
Permit Description: TI:RETAIL (METER 1 & 2 )
Total Outstanding Activity Conditions - 4
Date | Name |
---|---|
03/29/2006 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
03/29/2006 | SPECIAL INSPECTION FOR STRUCTURAL MASONRY IS REQUIRED. |
03/29/2006 | SPECIAL INSPECTION FOR EPOXY ANCHORS IS REQUIRED. |
03/29/2006 | SPECIAL INSPECTION FOR EXPANSION ANCHORS IS REQUIRED. |
Outstanding Inspections
Permit Status: Si_xpire
Permit Number: T06CM01754
Permite Description: TI:RETAIL (METER 1 & 2 )
Total Outstanding Inspections - 1
Last Inspection Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
PERMIT FINALED | N/A | Not Inspected |
Completed Inspections
Permit Status: Si_xpire
Permit Number: T06CM01754
Permit Description: TI:RETAIL (METER 1 & 2 )
Total Completed Inspections - 19
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
04/25/2006 | EXCAVATION/LAYOUT REBAR & ZON | JBURGE | Approved | IVRS - Inspection :* CHANGE APPROVED BY ENGINEER |
04/25/2006 | REINFORCED MASONRY PRE-GROUT | JBURGE | Approved | IVRS - Inspection :* |
04/27/2006 | PLUMBING - INTERMEDIATE | BBENEDON | Approved | IVRS - Inspection :* ADDRESS NOT POSTED |
04/27/2006 | PLUMBING - ROUGH, SOIL | BBENEDON | Approved | IVRS - Inspection :* |
05/05/2006 | FRAMING | JBURGE | Approved | IVRS - Inspection :* |
05/05/2006 | SHEET ROCK NAILING | JBURGE | Approved | IVRS - Inspection :* |
05/09/2006 | MECHANICAL - FINAL | CWILLIAM | Approved | IVRS - Inspection :* MECHANICAL WORK - RELOCATED SUPPLY REGISTERS. |
05/09/2006 | MECHANICAL - ABOVE CEILING | CWILLIAM | Approved | IVRS - Inspection :* |
05/11/2006 | ELECTRIC - ABOVE CEILING | RHOLLAND | Approved | IVRS - Inspection :* OK TO TILE |
05/17/2006 | SIGN - FINAL | JYBARRA | Approved | IVRS - Inspection :* |
05/17/2006 | ELECTRIC - FINAL | RSUBA | Approved | IVRS - Inspection :* |
05/17/2006 | ELECTRIC - INTERMEDIATE | RSUBA | Approved | IVRS - Inspection :* |
05/24/2006 | ENGINEERING - FINAL | JBRUCKME | Approved | |
05/24/2006 | PLUMBING - FINAL | BBENEDON | Approved | IVRS - Inspection :* |
05/24/2006 | PLUMBING - PROGRESS | BBENEDON | Approved | IVRS - Inspection :* |
05/25/2006 | FIRE - FINAL | LTHOMAS | Approved | |
05/25/2006 | FIRE SPKLR - FINAL | LTHOMAS | Approved | |
05/26/2006 | BUILDING - FINAL | JBURGE | Approved | |
05/31/2006 | RIGHT OF WAY - FINAL | PWHIDDON | Approved | PER EMAIL |