Permit: T06CM01495
Permit Details
Status:
C of o
Type:
COMMERCIAL NEW
Address:
870 W MIRACLE MILE 03
Address NEW:
870 W MIRACLE MILE 03
Apply Date:
03/17/2006
Applicant:
POSTER FROST ASSOC/DOUG HAWKINS
Description:
NEW: FOSTER CARE RESOURCE CNTR REV: PLUMBING
Contractors:
- LANG WYATT CONSTRUCTION ,
Permit Reviews
Permit Number - T06CM01495
Permit Status: C of o
Permit Description: NEW: FOSTER CARE RESOURCE CNTR
REV: PLUMBING
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 03/17/2006 | PLANS OK TO SUBMIT - 3RD PARTY | 03/21/2006 | COMPLETED |
| 03/21/2006 | 3RD PARTY REVIEW-COMMERCIAL | 07/24/2006 | COMPLETED |
| 05/02/2007 | 3RD PARTY REVIEW-REVISION/OTHER | 05/03/2007 | COMPLETED |
| 07/24/2006 | POST 3RD PARTY REVIEW | 08/03/2006 | COMPLETED |
| 08/01/2006 | OTHER | 08/01/2006 | COMPLETED |
| 08/03/2006 | OTHER | 08/21/2006 | COMPLETED |
| 08/09/2007 | 3RD PARTY REVIEW-REVISION/OTHER | 08/10/2007 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T06CM01495
Permit Status: C of o
Permit Description: NEW: FOSTER CARE RESOURCE CNTR
REV: PLUMBING
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 03/17/2006 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T06CM01495
Permit Description: NEW: FOSTER CARE RESOURCE CNTR
REV: PLUMBING
Total Completed Inspections - 44
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 09/15/2006 | EXCAVATION/LAYOUT REBAR & ZON | LHANLY | Approved | IVRS - Inspection :* |
| 09/25/2006 | STEM WALL/RETAINING WALL | LHANLY | Approved | IVRS - Inspection :* |
| 12/12/2006 | ELECTRIC - UNDERGROUND | CCLEMENS | Approved | IVRS - Inspection :* OK FLOOR BOXES UNDERSLAB IN TRAINING ROOM BUILDING |
| 12/18/2006 | PLUMBING - ROUGH, SOIL | RMYERS | Approved | IVRS - Inspection :* 1. 2" ABS WASTE STUBBED UP AND OUT ONLY 3/4" COPPER STUBBED INTO BLDG. ONLY |
| 12/18/2006 | PLUMBING - PRE SLAB | RMYERS | Approved | IVRS - Inspection :* |
| 12/19/2006 | BUILDING PRE-SLAB | AQUIROZ | Approved | IVRS - Inspection :* TRAINING BUILDING OK |
| 02/26/2007 | ROOF NAILING | AQUIROZ | Approved | IVRS - Inspection :* |
| 03/05/2007 | EXT METAL CLIPS/EXT SHEATHING | AQUIROZ | Approved | IVRS - Inspection :* |
| 03/28/2007 | PLUMBING - YARD WTR LINE/TEST | RMYERS | Approved | IVRS - Inspection :* |
| 04/04/2007 | FRAMING | JBURGE | Approved | IVRS - Inspection :* DO NOT COVER UNTIL INTERMEDIATE TRADES INSPECTIONS. |
| 04/06/2007 | PLUMBING - INTERMEDIATE | RMYERS | Approved | IVRS - Inspection :* OK TO COVER ALL AREAS |
| 06/21/2007 | SHEET ROCK NAILING | AQUIROZ | Approved | IVRS - Inspection :* |
| 10/24/2007 | BUILDING ABOVE CEILING | AQUIROZ | Approved | IVRS - Inspection :* |
| 10/24/2007 | ELECTRIC - TEMP POWER FOR TEST | CCLEMENS | Approved | IVRS - Inspection :* |
| 10/25/2007 | TEP CLEARANCE - AM | BFLORES | Approved | TEC PER C.CLEMENS |
| 11/15/2007 | FIRE - FINAL | LTHOMAS | Approved | |
| 11/15/2007 | FIRE SPKLR - FINAL | LTHOMAS | Approved | |
| 11/15/2007 | FIRE SPKLR - OH PIPING & HYDRO | LTHOMAS | Approved | |
| 11/21/2007 | NPPO - FINAL | ACONNOR | Approved | |
| 11/21/2007 | LANDSCAPE - FINAL | ACONNOR | Approved | |
| 11/23/2007 | PLUMBING - FINAL | BBENEDON | Approved | IVRS - Inspection :* |
| 11/23/2007 | SITE - SEWER | BBENEDON | Approved | IVRS - Inspection :* |
| 11/23/2007 | PLUMBING - SEWER HCS CONNECT | BBENEDON | Approved | IVRS - Inspection :* |
| 11/27/2007 | RIGHT OF WAY - FINAL | MOTERO | Approved | |
| 11/27/2007 | ELECTRIC - FINAL | CCLEMENS | Approved | IVRS - Inspection :* 1) NOTE: CONTRACTOR TO CLEAR SHORT IN FLOOR RECEPTACLE CIRCUIT |
| 11/27/2007 | BUILDING - PROGRESS | AQUIROZ | Approved | IVRS - Inspection :* |
| 11/27/2007 | U VALUE FOR WINDOW | AQUIROZ | Approved | IVRS - Inspection :* |
| 11/27/2007 | STUCCO MESH | AQUIROZ | Approved | IVRS - Inspection :* |
| 11/27/2007 | ELECTRIC - OUTDOOR LIGHTING | CCLEMENS | Approved | IVRS - Inspection :* |
| 11/27/2007 | OUTDOOR LIGHTING FINAL | CCLEMENS | Approved | IVRS - Inspection :* |
| 11/27/2007 | ELECTRIC - PROGRESS | CCLEMENS | Approved | IVRS - Inspection :* |
| 11/27/2007 | ELECTRIC - CONSTRUCTION POWER | CCLEMENS | Approved | IVRS - Inspection :* |
| 11/27/2007 | ELECTRIC - TEMPORARY SERVICE | CCLEMENS | Approved | IVRS - Inspection :* |
| 11/27/2007 | ELECTRIC - CABLE DROP | CCLEMENS | Approved | IVRS - Inspection :* |
| 11/27/2007 | ELECTRIC - ABOVE CEILING | CCLEMENS | Approved | IVRS - Inspection :* |
| 11/27/2007 | ELECTRIC - INTERMEDIATE | CCLEMENS | Approved | IVRS - Inspection :* |
| 11/27/2007 | ELECTRIC - UFER | CCLEMENS | Approved | IVRS - Inspection :* |
| 11/28/2007 | MECHANICAL - INTERMEDIATE | MRAMBER | Approved | IVRS - Inspection :* |
| 11/30/2007 | MECHANICAL - UNDERGROUND | MRAMBER | Approved | |
| 11/30/2007 | MECHANICAL - FINAL | MRAMBER | Approved | IVRS - Inspection :* |
| 12/04/2007 | BUILDING - FINAL | AQUIROZ | Approved | OK C OF O |
| 12/05/2007 | SIGN - FINAL | JYBARRA | Approved | |
| 12/07/2007 | REINFORCED MASONRY PRE-GROUT | ENEWCOMB | Approved | |
| 12/10/2007 | ENGINEERING - FINAL | MRUSSO | Approved |