Status:
C of o
Type:
COMMERCIAL NEW
Address:
9560 E 22ND ST
Apply Date:
01/05/2006
Applicant:
METRO PERMIT EXPRESS, INC *C
Description:
RESTAURANT
Architects:
  • DOERSCHLAG, CHRISTOPHEKURT
Contractors:
  • E G C SERVICES INC

Permit Reviews

Permit Number - T06CM00064
Permit Status: C of o
Permit Description: RESTAURANT
Start Date Submittal Complete Date Status  
01/05/2006 PLANS OK TO SUBMIT - 3RD PARTY 01/19/2006 COMPLETED Review Details
01/05/2006 SITE 05/15/2006 COMPLETED Review Details
01/19/2006 3RD PARTY REVIEW-COMMERCIAL 03/16/2006 COMPLETED Review Details
03/16/2006 POST 3RD PARTY REVIEW 05/19/2006 COMPLETED Review Details
05/19/2006 RESUBMITTAL - SITE 05/23/2006 COMPLETED Review Details
06/06/2006 RESUBMITTAL - SITE 06/19/2006 COMPLETED Review Details
10/31/2006 3RD PARTY REVIEW-REVISION/OTHER 10/31/2006 COMPLETED Review Details

Outstanding Activity Conditions

Permit Number - T06CM00064
Permit Status: C of o
Permit Description: RESTAURANT
Total Outstanding Activity Conditions - 1
Date Name
01/05/2006 PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION.

Completed Inspections

Permit Status: C of o
Permit Number: T06CM00064
Permit Description: RESTAURANT
Total Completed Inspections - 46
Date Description Inspector Results Comments
06/20/2006 ELECTRIC - UFER RSUBA Approved IVRS - Inspection :*
07/12/2006 ELECTRIC - UNDERGROUND RSUBA Approved IVRS - Inspection :*
07/19/2006 BUILDING PRE-SLAB GDABBS Approved IVRS - Inspection :*
OK TO POUR MAIN RESTAURANT AREA & COOLER AREA
08/09/2006 REINFORCED MASONRY PRE-GROUT GDABBS Approved IVRS - Inspection :*
STOREFRONT ENTRY JAMBS/CLEANOUT FOR FULL GROUT OK
08/17/2006 FIRE SPKLR - UG PIPING FLUSH LTHOMAS Approved
08/17/2006 FIRE SPKLR - UG, PIPING, HYDRO LTHOMAS Approved
08/28/2006 ROOF NAILING GDABBS Approved IVRS - Inspection :*
08/30/2006 PLUMBING - SEWER HCS CONNECT RRICH Approved IVRS - Inspection :*
WATER TEST FROM BUILDING 2-WAY TO EXISTING SEWER,
FROM GREASE INTERCEPTOR TO EXISTING SEWER OK
08/30/2006 TEP CLEARANCE - AM JWEATHER Approved TEC CLEARED PER R. HOLLANDER
09/19/2006 ELECTRIC - INTERMEDIATE RMAJUTA Approved IVRS - Inspection :*
REST OF INTERMEDIATE
09/19/2006 EXT METAL CLIPS/EXT SHEATHING GDABBS Approved IVRS - Inspection :*
09/21/2006 PLUMBING - INTERMEDIATE RRICH Approved IVRS - Inspection :*
WATER TEST WASTE & VENT THRU ROOF OK
WATER PIPING OK
ROOF DRAINS WATER TEST OK
1. INSULATION TO BE INSTALLED PER PLAN & MANUFACTURER REQUIREMENT.
09/21/2006 PLUMBING - ROOF DRAINS RRICH Approved IVRS - Inspection :*
09/25/2006 FRAMING GDABBS Approved IVRS - Inspection :*
09/26/2006 MECHANICAL - INTERMEDIATE JMILITEL Approved IVRS - Inspection :*
CHECKED CONDENSATE DRAIN LINES. OK TO COVER.
10/02/2006 SHEET ROCK NAILING GDABBS Approved IVRS - Inspection :*
10/05/2006 MECHANICAL - HOODS JMILITEL Approved IVRS - Inspection :*
ON FINAL EXTEND GREASE DUCT & CURB IF NEEDED TO CLEAR WALL ON ROOF.
CHECKED FIRE WRAP -- OK TO PROCEED.
10/06/2006 U VALUE FOR WINDOW GDABBS Approved IVRS - Inspection :*
10/11/2006 ELECTRIC - TEMPORARY SERVICE RSUBA Approved IVRS - Inspection :*
10/11/2006 ELECTRIC - CABLE DROP RSUBA Approved IVRS - Inspection :*
10/23/2006 MECHANICAL - ABOVE CEILING JMILITEL Approved IVRS - Inspection :*
10/26/2006 ELECTRIC - ABOVE CEILING DSANTACR Approved IVRS - Inspection :*
10/27/2006 BUILDING ABOVE CEILING GDABBS Approved IVRS - Inspection :*
10/27/2006 EXCAVATION/LAYOUT REBAR & ZON GDABBS Approved IVRS - Inspection :*
10/31/2006 PLUMBING - GAS PRESSURE TEST RLEDONNE Approved IVRS - Inspection :*
GAS CARD ON PIPE AT METER
PROVIDE SADDLES UNDER PIPING IN HANGERS WITH INSULATION.
11/01/2006 PLUMBING - ABOVE CEILING RRICH Approved IVRS - Inspection :*
CALL IN 03005, 03040, 03090
11/02/2006 MECHANICAL - FINAL JMILITEL Approved IVRS - Inspection :*
11/02/2006 ELECTRIC - FINAL RSUBA Approved IVRS - Inspection :*
11/02/2006 ELECTRIC - OUTDOOR LIGHTING RSUBA Approved IVRS - Inspection :*
11/06/2006 BUILDING - FINAL GDABBS Approved IVRS - Inspection :*
SUBJECT TO PASSING REST OF FINALS
PAVING BEHIND RESTAURANT NEEDS TO BE COMPLETED.
11/06/2006 FIRE - KITCHEN EXH HOOD FINAL LLAKEY Approved
11/06/2006 FIRE - HYDRANTS LTHOMAS Approved
11/06/2006 FIRE - FINAL LLAKEY Approved
11/06/2006 FIRE SPKLR - FINAL LTHOMAS Approved
11/06/2006 FIRE SPKLR - OH PIPING & HYDRO LTHOMAS Approved
11/06/2006 SIGN - FINAL JYBARRA Approved IVRS - Inspection :*
11/06/2006 PLUMBING - YARD WTR LINE/TEST RRICH Approved IVRS - Inspection :*
11/06/2006 PLUMBING - ROUGH, SOIL RRICH Approved IVRS - Inspection :*
11/07/2006 PLUMBING - FINAL RRICH Approved IVRS - Inspection :*
RECEIVED (11) IN HOUSE BACKFLOW CERTIFICATIONS.
11/14/2006 ENGINEERING - FINAL NKALAHAR Approved PAVING NOT COMPLETE SOUTH OF STORE
11/17/2006 NPPO - FINAL ACONNOR Approved
11/17/2006 LANDSCAPE - FINAL ACONNOR Approved
11/18/2006 RIGHT OF WAY - FINAL PWHIDDON Approved PER EMAIL
01/02/2007 STEM WALL/RETAINING WALL GDABBS Approved
01/02/2007 STUCCO MESH GDABBS Approved
01/08/2007 PERMIT FINALED BGRANT Approved

Documents

File Name Document Type  
None CERT OF OCC VIEW
None DOCUMENTS VIEW