Permit: T06BU02867
Permit Details
Status:
Final
Type:
COMMERCIAL OTHER
Address:
10265 E IRVINGTON RD
Address NEW:
10265 E IRVINGTON RD
Apply Date:
12/06/2006
Applicant:
N/A
Description:
GRADING QUIKMART AT HOUGHTON AND IRVINGTON CUT 700CY FILL 100CY
Contractors:
- COBRE BUILDING SYSTEMS INC ,
Permit Reviews
Permit Number - T06BU02867
Permit Status: Final
Permit Description: GRADING QUIKMART AT HOUGHTON AND IRVINGTON
CUT 700CY FILL 100CY
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 04/18/2007 | RESUBMITTAL - GRADING ALL | 05/23/2007 | COMPLETED |
| 05/23/2007 | RESUBMITTAL - GRADING ALL | 05/30/2007 | COMPLETED |
| 07/23/2007 | REVISION - GRADING | 07/26/2007 | COMPLETED |
| 12/06/2006 | PLANS OK TO SUBMIT - GRADING | 12/06/2006 | COMPLETED |
| 12/06/2006 | GRADING | 03/05/2007 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T06BU02867
Permit Status: Final
Permit Description: GRADING QUIKMART AT HOUGHTON AND IRVINGTON
CUT 700CY FILL 100CY
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 12/06/2006 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: Final
Permit Number: T06BU02867
Permit Description: GRADING QUIKMART AT HOUGHTON AND IRVINGTON
CUT 700CY FILL 100CY
Total Completed Inspections - 7
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 07/16/2007 | ENGINEERING PRE-CONSTRUCTION | MAVERY | Approved | Completed pre-con, contractor did not have the approved set of drawings. The site plan and the grading plan on the set he did have did not match. I told contractor he needs to get the approved set on site before construction starts. |
| 07/24/2007 | STORMWATER INSTALL OF CONTROLS | NKALAHAR | Approved | CONTROLS IN AND APPEAR TO BE WORKING DROPPED OFF RAIN GAUGE. |
| 10/18/2007 | GRADING - INTERMEDIATE | NKALAHAR | Approved | MET ON SITE WITH BILL KOCH AND WARREN REGARDING WEST SIDE OF BUILDING WHERE ELECTRIC PANELS WILL ENCROACH ON ADA SIDEWALK AREA CONTACTED GLENN DABBS FOR INPUT-HE WILL CHECK SITE TODAY DURING RETAINING WALL INSPECTION |
| 11/13/2007 | STORMWATER FOLLOW-UP INSP | NKALAHAR | Approved | WALKED SITE WITH WARREN OFF SITE IMPROVEMENTS BEING DONE BY ASHTON-ROAD PROJECT GRANITE HAS A MATERIALS STORAGE YARD AND IS CAUSING MUCH TRACK OUT WEST OF SITE ON IRVINGTON |
| 03/28/2008 | LANDSCAPE INSPECTION | ACONNOR | Approved | |
| 04/08/2008 | GRADING - FINAL | NKALAHAR | Approved | APPROVED |
| 04/09/2008 | PERMIT FINALED | KMEDINA | Approved |