Inspection History Details
Inspection Status: Approved
Inspection History: STORMWATER FOLLOW-UP INSP
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 04/11/2008 | STORMWATER FOLLOW-UP INSP | Approved | ||
| 02/04/2008 | STORMWATER FOLLOW-UP INSP | Partial Approval | SITE WORK CONTINUING NO CONCERNS DRAINAGEWAY WORK APPEARS TO BE COMPLETE FROM ROAD WORK PROJECT |
|
| 11/13/2007 | STORMWATER FOLLOW-UP INSP | Partial Approval | WALKED SITE WITH WARREN OFF SITE IMPROVEMENTS BEING DONE BY ASHTON-ROAD PROJECT GRANITE HAS A MATERIALS STORAGE YARD AND IS CAUSING MUCH TRACK OUT WEST OF SITE ON IRVINGTON |
|
| 10/24/2007 | STORMWATER FOLLOW-UP INSP | Partial Approval | CONTROLS HAVE BEEN PLACED AT TOP OF SLOPE AND AT TOP OF CONCRETE DRAINAGEWAY AT NEW SEWER CONNECTION EXCAVATION | |
| 10/18/2007 | STORMWATER FOLLOW-UP INSP | Correction Required | WALKED SITE WITH BILL KOCH AND WARREN CONTROLS TO BE PLACED AT TOP OF CONCRETE DRAINAGEWAY ONCE CONCRETE POURED HYDROSEED TO BE SPRAYED DRAINAGEWAY TO BE CLEANED OUT |
|
| 09/14/2007 | STORMWATER FOLLOW-UP INSP | Partial Approval | NO STORMWATER CONCERNS LOADER STUCK RETAINING WALL IN PLACE |