Permit: T06BU00245
Permit Details
Apply Date:
02/01/2006
Applicant:
N/A
Description:
Rillito Crossing Marketplace CUT 12249CY FILL 13934CY
Contractors:
- CANYON BUILDING AND DESIGN L L C
Permit Reviews
Permit Number - T06BU00245
Permit Status: Final
Permit Description: Rillito Crossing Marketplace
CUT 12249CY FILL 13934CY
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
02/01/2006 | PLANS OK TO SUBMIT - GRADING | 02/01/2006 | COMPLETED |
02/01/2006 | GRADING | 03/15/2006 | COMPLETED |
03/15/2006 | RESUBMITTAL - GRADING | 04/18/2006 | COMPLETED |
04/26/2006 | RESUBMITTAL - GRADING ALL | 05/04/2006 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T06BU00245
Permit Status: Final
Permit Description: Rillito Crossing Marketplace
CUT 12249CY FILL 13934CY
Total Outstanding Activity Conditions - 1
Date | Name |
---|---|
02/01/2006 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: Final
Permit Number: T06BU00245
Permit Description: Rillito Crossing Marketplace
CUT 12249CY FILL 13934CY
Total Completed Inspections - 7
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
05/17/2006 | NPPO PRE PERMIT INSPECTION | ACONNOR | Approved | |
05/17/2006 | ENGINEERING PRE-CONSTRUCTION | MRUSSO | Approved | COMPLETED PRECONSTRUCTION MEETING WITH MIKE FROM CANYON. THE DIRT CONTRACTOR WILL BE EAGLE ROCK. SEDIMENT CONTROLS HAVE BEEN INSTALLED. |
06/14/2006 | STORMWATER INSTALL OF CONTROLS | MRUSSO | Approved | 1) EXTEND WADDLE ALONG 1ST AVE PAST CATCH BASIN. 2) ADD STRAW BAILS AT ENTRANCE TO CATCH BASIN. 3) TALKED WITH SUPERINTENDENT/ TOLD INSPECTION RESULTS. 4) CONTINUALLY SWEEP TRACKING. |
12/07/2006 | GRADING - FINAL | MRUSSO | Approved | INSPECTION WAS CALLED IN TO DISCUSS AND CLARIFY GRADING PLAN - CATCH BASIN DETAILS THAT WERE APPROVED. |
12/28/2006 | STORMWATER FOLLOW-UP INSP | MRUSSO | Approved | NO ADDITIONAL STORM WATER CONCERNS AT THIS TIME - ENSURE SWPPP IS FOLLOWED |
04/23/2007 | STORMWATER FINAL INSPECTION | MRUSSO | Approved | STOCKPILED MATERIAL IS BEING REMOVED AND WADDLE HAS BEEN PLACED AROUND THE REMAINING SOIL. |
07/06/2007 | LANDSCAPE INSPECTION | ACONNOR | Approved |