Inspection Status: Approved
Inspection History: ENGINEERING PRE-CONSTRUCTION
| Date |
Description |
Inspector |
Results |
Comments |
| 05/17/2006 |
ENGINEERING PRE-CONSTRUCTION |
|
Approved |
COMPLETED PRECONSTRUCTION MEETING WITH MIKE FROM CANYON. THE DIRT CONTRACTOR WILL BE EAGLE ROCK. SEDIMENT CONTROLS HAVE BEEN INSTALLED. |
| 05/12/2006 |
ENGINEERING PRE-CONSTRUCTION |
|
Partial Approval |
MET CONTRACTOR (CANYON/MIKE WILHEIGHT 331-6945) ON SITE DISCUSSED SWPPP AND GRADING PLAN. NEED CLARIFICATION ON SWPPP AND GRADING PLAN BY REVIEW ENGINEER (JOSE). NEED EXISTING TOPO AND/OR DRAINAGEFLOW LINES. |
| 05/11/2006 |
ENGINEERING PRE-CONSTRUCTION |
|
Not ready for Inspection |
NO ACTIVITY, SITE HAS BEEN CLEARED. |