Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Permit: T06BU00192
Permit Details
Apply Date:
01/25/2006
Applicant:
RICK ENGINEERING
Description:
GRADING CUT 6300 FILL 6000
Contractors:
- DIVERSIFED DESIGN AND CONSTRUCTION RESIDENTIAL I
Permit Reviews
Permit Number - T06BU00192
Permit Status: Closed
Permit Description: GRADING CUT 6300 FILL 6000
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 01/25/2006 | PLANS OK TO SUBMIT - GRADING | 01/25/2006 | COMPLETED |
| 01/25/2006 | GRADING | 03/20/2006 | COMPLETED |
| 02/28/2007 | GRADING | 03/16/2007 | COMPLETED |
| 05/26/2009 | REVISION - GRADING | 06/09/2009 | COMPLETED |
| 09/25/2008 | REVISION - GRADING | 10/13/2008 | COMPLETED |
| 10/03/2007 | REVISION - GRADING | 10/16/2007 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T06BU00192
Permit Status: Closed
Permit Description: GRADING CUT 6300 FILL 6000
Total Outstanding Activity Conditions - 2
| Date | Name |
|---|---|
| 01/25/2006 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
| 03/01/2007 | LANDSCAPE INSPECTION REQUIRED. |
Completed Inspections
Permit Status: Closed
Permit Number: T06BU00192
Permit Description: GRADING CUT 6300 FILL 6000
Total Completed Inspections - 8
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 07/19/2007 | STORMWATER INSTALL OF CONTROLS | MRUSSO | Approved | 1) RE-INSTALL SILT FENCE ALONG NE CORNER OF SITE/OR ADD ROCK TO AREA AND USE AS ENTRANCE. - AREA BEING USED FOR CONSTRUCTION ENTRANCE. 2) SWEEP UP TRACKED MATERIAL OFF OF BALBOA. 3) ENSURE A DESIGNATED CONCRETE WASH OUT IS INSTALLED AS SOON AS PRACTICABLE. 4) ENSURE ROUTINE STORM WATER MAINT. SELF INSPECTIONS ARE PERFORMED AND DOCUMENTED. 5) POST A SIGNED COPY OF YOUR NOI ON SITE. 6) CONTINUE TO MAINTAIN SEDIMENT CONTROLS AS NEEDED UNTIL THE SITE IS 100% STABILIZED. |
| 07/19/2007 | ENGINEERING PRE-CONSTRUCTION | MRUSSO | Approved | 1) RE-INSTALL SILT FENCE ALONG NE CORNER OF SITE/OR ADD ROCK TO AREA AND USE AS ENTRANCE. - AREA BEING USED FOR CONSTRUCTION ENTRANCE. 2) SWEEP UP TRACKED MATERIAL OFF OF BALBOA. 3) ENSURE A DESIGNATED CONCRETE WASH OUT IS INSTALLED AS SOON AS PRACTICABLE. 4) ENSURE ROUTINE STORM WATER MAINT. SELF INSPECTIONS ARE PERFORMED AND DOCUMENTED. 5) POST A SIGNED COPY OF YOUR NOI ON SITE. 6) CONTINUE TO MAINTAIN SEDIMENT CONTROLS AS NEEDED UNTIL THE SITE IS 100% STABILIZED. |
| 11/01/2007 | GRADING - INTERMEDIATE | MRUSSO | Approved | ANY SIGNIFICANT CHANGES MADE TO THE APPROVED GRADING PLAN MUST BE SUBMITTED BY THE ENGINEER OF RECORD AND APPROVED BY THE CITY OF TUCSON. PROVIDE A DRAINAGE CERTIFICATION STATEMNET FRON THE ENGINEER OF RECORD PRIOR TO FINAL GARDING APPROVAL APPROVAL FOR A C OF O FOR ENGINEERING WILL NOT BE GIVEN UNTIL THE FINAL GRADING INSPECTION IS APPROVED. |
| 11/20/2007 | STORMWATER FOLLOW-UP INSP | MRUSSO | Approved | |
| 11/20/2007 | STORMWATER FOLLOW-UP INSP | MRUSSO | Approved | ALL ITEMS HAVE BEEN ADDRESSED, NO ADDITIONAL STORM WATER CONCERNS AT THIS TIME |
| 07/17/2008 | GRADING - FINAL | MRUSSO | Approved | 1) CLEAN OUT BUBBLER CATCH BASIN (SEE NOTE #18 - DETAIL 0/5) SHOWN ON APPROVED GRADING PLAN. 2) INSTALL ROCK RIP RAP PAD AT OUTLET OF BUBBLER, NW CORNER. 3) COMPLETE INSTALLATION OF RAILING ALONG RET/DET BASIN AT NE CORNER. 4) PATCH ASPHALT AT CURBING ALONG PUBLIC ROADWAYS ON NE CORNER. 5) CLEAN OUT - 8" OUTLET PIPE OF RET/DET BASIN. 6) REPAIR EROSION DAMAGE FROM ROOF DRAINS LOCATED ON EAST SIDE OF LOADING DOCK AREA - INSTALL SPLASH PADS 7) PROVIDE AN APPROVED DRAWING SHAOWING CHANGES MADE TO VAN DROP OFF AREA SEE NOTES #6 AND #7 ON APPROVED GRADING PLAN 8) ENSURE BOTTOM WIDTH OF RET/DET BASIN NORTH OF CULVERT CROSSING IS 11' ACCROSS. .........TO BE CONTINUED |
| 02/23/2009 | STORMWATER FINAL INSPECTION | MRUSSO | Approved | |
| 03/24/2011 | LANDSCAPE INSPECTION | ACONNOR | Approved |