Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Inspection History Details
Inspection Status: Approved
Inspection History: STORMWATER FOLLOW-UP INSP
Permit Number - T06BU00192
Inspection Description - STORMWATER FOLLOW-UP INSP
Inspection Status - Approved
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 02/23/2009 | STORMWATER FOLLOW-UP INSP | Approved | ||
| 01/20/2009 | STORMWATER FOLLOW-UP INSP | Correction Required | SITE WORK FOR PHASE II NOT COMPLETED. NO SIGNIFICANT STORM WATER CONCERNS AT THIS TIME. | |
| 10/27/2008 | STORMWATER FOLLOW-UP INSP | Partial Approval | NO SIGNIFICANT STORM WATER CONCERNS. HALF OF BLDG OCCUPIED. INTERIOR WORK LEFT TO BE DONE AND SOME MINOR SITE WORK. | |
| 05/15/2008 | STORMWATER FOLLOW-UP INSP | Partial Approval | NO STORM WATER CONCERNS AT THIS TIME - PERIMETER CURBING IN PLACE. | |
| 04/15/2008 | STORMWATER FOLLOW-UP INSP | Partial Approval | NO SIGNIFICANT STORM WATER CONCERNS AT THIS TIME. | |
| 02/21/2008 | STORMWATER FOLLOW-UP INSP | Correction Required | 1) SWEEP UP TRACKED MATERIAL OFF OF PUBLIC ROADWAYS, MORE OFTEN DURING HAULING OPERATIONS. 2) RE-INSTALL CONCRETE/MATERIALS WASH-OUT PER YOUR PLAN. 3) CONTINUE TO MAINTAIN CONTROLS AND PERFORM SELF INSPECTIONS AS REQUIRED. 4) MAY NEED TO ADD SUPLEMENTAL SW CONTROLS AT THE NW CORNER OF SITE, CORNER IS A POINT OF DISCHARGE FOR STORM WATER. |
|
| 02/05/2008 | STORMWATER FOLLOW-UP INSP | Correction Required | RAINING, NO ACTIVITY. SW CONTROLS IN PLACE |
|
| 02/05/2008 | STORMWATER FOLLOW-UP INSP | Correction Required | RAINING TODAY, LITTLE ACTIVITY SOME SW MAINT REQUIRED. |
|
| 01/16/2008 | STORMWATER FOLLOW-UP INSP | Correction Required | 1) SWEEP UP TRACKING OFF OF LAGUNA 2) REMOVE CONSTRUCTION MATERIAL/DEBRI OFF OF SILT FENCE. 3) RE-ESTABLISH SILT FENCE WHERE FALLING DOWN/WORN. 4) BRING SOIL BACK ON SITE ON SE SIDE OF SITE. 5) CONTINUE TO PERFORM AND DOCUMENT STORM WATER SELF INSPECTIONS. |
|
| 11/20/2007 | STORMWATER FOLLOW-UP INSP | Partial Approval | ALL ITEMS HAVE BEEN ADDRESSED, NO ADDITIONAL STORM WATER CONCERNS AT THIS TIME | |
| 11/20/2007 | STORMWATER FOLLOW-UP INSP | Partial Approval | ||
| 11/01/2007 | STORMWATER FOLLOW-UP INSP | Correction Required | 1) REPAR AND/OR REPLACE SILT FENCE IN AREAS WHERE IT IS FALLING DOWN OR HAS BEEN DAMAGED. 2) REMOVE CONSTRUCTION EQUIPENT AND MATERIALS OFF OF SILT FENCE. 3) CLEAN UP AREA ALONG THE FAR SOUTH EAST CORNER OF THE SITE. BRING SOIL FROM WALL CONSTRUCTION BACK ONTO SITE OR ADD SEDIEMNT CONTROLS AROUND IT. 4) CONTINUE TO SWEEP UP TRACKED MATERIAL OFF OF PUBLIC ROADWAYS. 5) DISPOSE OF CONCRETE/MORTOR WASTE PROPERLY - DON'T BURY ON SITE. 6) CONTINUE TO PERFORM AND DOCUMENT STOEM WATER SELF INSPECTIONS PER YOUR SWPPP. |
|
| 09/20/2007 | STORMWATER FOLLOW-UP INSP | Correction Required | RE-ESTABLISH STABILIZED CONSTRUCTION ENTRANCE SWEEP UP TRACKING OFF OF PUBLIC ROADWAY |
|
| 08/27/2007 | STORMWATER FOLLOW-UP INSP | Correction Required | NO NEW STORM WATER CONCERNS AT THIS TIME. NOTE: PER CITY OF TUCSON DEV. STD. AND NPDES, STOCKPILED MATERIAL NOT WORKED FOR > 14 DAYS REQUIRES STABILIZATION. |
|
| 07/31/2007 | STORMWATER FOLLOW-UP INSP | Correction Required | SEDIMENT CONTROLS IN PLACE, NO VISUAL EVIDENCE OF SOIL BEING DISCHARGE OFF SITE. 1) ENSURE STORM WATER SELF INSPECTION ARE PERFORMED AND DOCUMENTED. 2) CONTINUE TO MAINTAIN CONTROLS AS NEEDED. 3) CONTINUE TO SWEEP UP TRACKED MATERIAL OFF OF PUBLIC ROADWAYS. 4) PROVIDE A CONCRETE/MATERIALS WASH OUT WHEN APPLICABLE. |