Permit: T05CM05855
Permit Details
Apply Date:
11/22/2005
Applicant:
LLOYD CONSTRUCTION COMPANY INC ,
Description:
NEW OFFICE
Contractors:
- LLOYD CONSTRUCTION COMPANY INC ,
Permit Reviews
Permit Number - T05CM05855
Permit Status: Final
Permit Description: NEW OFFICE
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 01/16/2006 | POST 3RD PARTY REVIEW | 01/26/2006 | COMPLETED |
| 01/25/2006 | SITE | 01/31/2006 | COMPLETED |
| 01/26/2006 | RESUBMITTAL | 01/31/2006 | COMPLETED |
| 03/09/2006 | 3RD PARTY REVIEW-REVISION/OTHER | 03/10/2006 | COMPLETED |
| 05/02/2007 | 3RD PARTY REVIEW-REVISION/OTHER | 05/16/2007 | COMPLETED |
| 11/22/2005 | PLANS OK TO SUBMIT - SITE | 01/31/2006 | COMPLETED |
| 11/22/2005 | PLANS OK TO SUBMIT - 3RD PARTY | 11/22/2005 | COMPLETED |
| 11/22/2005 | 3RD PARTY REVIEW-COMMERCIAL TI | 01/16/2006 | COMPLETED |
| 12/21/2006 | 3RD PARTY REVIEW-REVISION/OTHER | 12/28/2006 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T05CM05855
Permit Status: Final
Permit Description: NEW OFFICE
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 11/22/2005 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: Final
Permit Number: T05CM05855
Permit Description: NEW OFFICE
Total Completed Inspections - 43
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 02/23/2006 | ELECTRIC - UFER | RSUBA | Approved | IVRS - Inspection :* OK 2 GROUND RODS 20' IN FOOTING & ATTACHED TO 20' #4 REBAR #4 CU |
| 03/14/2006 | STEM WALL/RETAINING WALL | JCAGLE | Approved | IVRS - Inspection :* 1 STORY BUILDING, ENTIRE PERIMETER STEM WALL |
| 03/16/2006 | PLUMBING - ROUGH, SOIL | RRICH | Approved | IVRS - Inspection :* WATER TEST THRU BUILDING TO 2-WAY CLEANOUT OK |
| 04/10/2006 | PLUMBING - SEWER HCS CONNECT | RRICH | Approved | IVRS - Inspection :* HCS TIE IN AT BUILDING OK SEE PAST NOTES. |
| 05/09/2006 | EXCAVATION/LAYOUT REBAR & ZON | JBURGE | Approved | SITE LOCKED 1605 HRS |
| 05/25/2006 | PLUMBING - YARD WTR LINE/TEST | RRICH | Approved | IVRS - Inspection :* 3" HDPE PER PLAN FROM METER AREA TO SERVICE AREA 50 PSI TEST OK. 1. NEED TO SEE CONTINUATION AT BOTH ENDS WITH RPBA INSTALL & TESTING. |
| 06/12/2006 | ELECTRIC - UNDERGROUND | RHOLLAND | Approved | IVRS - Inspection :* OK 1" X 3/4" PVC BUILDING TO PULL BOX. |
| 09/12/2006 | ELECTRIC - OUTDOOR LIGHTING | RHOLLAND | Approved | OK PVC BLDG. TO POLE TO POLE FRONT |
| 09/27/2006 | ELECTRIC - ABOVE CEILING | RHOLLAND | Approved | IVRS - Inspection :* BUILDING IS NOT BUILT AT THIS TIME. |
| 10/30/2006 | BUILDING PRE-SLAB | JBURGE | Approved | IVRS - Inspection :* OK TO POUR |
| 12/05/2006 | REINFORCED MASONRY PRE-GROUT | JBURGE | Approved | IVRS - Inspection :* ALL WALLS TOPPED OUT - GROUTED |
| 12/20/2006 | EXT METAL CLIPS/EXT SHEATHING | JBURGE | Approved | IVRS - Inspection :* EXTERIOR SOFFITS OK TO COVER |
| 12/29/2006 | ROOF NAILING | JBURGE | Approved | IVRS - Inspection :* 1) OK TO DRY IN |
| 02/15/2007 | ELECTRIC - INTERMEDIATE | RHOLLAND | Approved | IVRS - Inspection :* OK ROUGH ELECTRIC |
| 02/22/2007 | MECHANICAL - INTERMEDIATE | JMILITEL | Approved | IVRS - Inspection :* PROVIDE R5 DUCT LINER IN DROPS |
| 02/22/2007 | RIGHT OF WAY - FINAL | PWHIDDON | Approved | |
| 02/22/2007 | PLUMBING - PROGRESS | BBENEDON | Approved | IVRS - Inspection :* WATER LINE IN BUILDING OK |
| 02/22/2007 | SIGN - FINAL | JYBARRA | Approved | IVRS - Inspection :* |
| 02/23/2007 | MECHANICAL - FINAL | JMILITEL | Approved | IVRS - Inspection :* OK FOR FINAL |
| 02/23/2007 | PLUMBING - FINAL | BBENEDON | Approved | IVRS - Inspection :* FOR FUTURE PROJECTS 1. ALL INSP. MUST BE APPROVED PRIOR TO FINAL 2. DO NOT COVER CONNECTIONS W/OUT INSP. 3. REDLINED DRAWINGS (IF INSPECTED FROM) SHALL BE SAVED TO COMPARE W/REVISED DRAWINGS. |
| 02/23/2007 | PLUMBING - GAS PRESS TEST FNL | BBENEDON | Approved | IVRS - Inspection :* |
| 02/23/2007 | PLUMBING - GAS PRESSURE TEST | BBENEDON | Approved | IVRS - Inspection :* |
| 02/23/2007 | PLUMBING - INTERMEDIATE | BBENEDON | Approved | IVRS - Inspection :* |
| 02/26/2007 | OUTDOOR LIGHTING FINAL | RHOLLAND | Approved | IVRS - Inspection :* |
| 02/26/2007 | ELECTRIC - FINAL | RHOLLAND | Approved | IVRS - Inspection :* |
| 02/26/2007 | SITE - SEWER | BBENEDON | Approved | |
| 02/27/2007 | FIRE SPKLR - UG PIPING FLUSH | LTHOMAS | Approved | |
| 02/27/2007 | FIRE SPKLR - OH PIPING & HYDRO | LTHOMAS | Approved | |
| 02/27/2007 | FIRE SPKLR - FINAL | LTHOMAS | Approved | |
| 02/27/2007 | FIRE - FINAL | LTHOMAS | Approved | |
| 02/27/2007 | FIRE SPKLR - UG, PIPING, HYDRO | LTHOMAS | Approved | |
| 02/28/2007 | PERMIT FINALED | JBURGE | Approved | |
| 02/28/2007 | BUILDING - FINAL | JBURGE | Approved | IVRS - Inspection :* |
| 03/01/2007 | MECHANICAL - ABOVE CEILING | JMILITEL | Approved | |
| 03/01/2007 | FRAMING | JBURGE | Approved | |
| 03/01/2007 | BUILDING ABOVE CEILING | JBURGE | Approved | |
| 03/01/2007 | STUCCO MESH | JBURGE | Approved | |
| 03/01/2007 | U VALUE FOR WINDOW | JBURGE | Approved | |
| 03/01/2007 | SHEET ROCK NAILING | JBURGE | Approved | |
| 03/01/2007 | BUILDING - PROGRESS | JBURGE | Approved | |
| 05/29/2007 | NPPO - FINAL | ACONNOR | Approved | |
| 05/29/2007 | LANDSCAPE - FINAL | ACONNOR | Approved | |
| 06/05/2007 | ENGINEERING - FINAL | JBRUCKME | Approved |