Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you cannot find what you are looking for please submit a records request.

Permit: T05CM05855

Parcel: 13323102D


Addresses:

7340 E SPEEDWAY BL

Inspection Status: Approved

Inspection History: EXCAVATION/LAYOUT REBAR & ZON

Date Description Inspector Results Comments
03/01/2007 EXCAVATION/LAYOUT REBAR & ZON Approved
05/09/2006 EXCAVATION/LAYOUT REBAR & ZON Not ready for Inspection SITE LOCKED 1605 HRS
03/30/2006 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
2 @ CCI COLUMNS ONLY - S.E. PORTION
03/17/2006 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
2 COLUMNS @ S.E. SIDE OF 1-STORY BUILDING.
02/27/2006 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
1) FOOTINGS FOR UTILITY ROOM #101 ( 1-STORY BLDG)
02/24/2006 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
1 STORY BUILDING
FOOTINGS, LINES E-1/1.5-2, 3/E-E.1, 2-A/D-E; COLUMN FOOTINGS @ LINES 2/A-2/D.1, 3/D.1, 2.A/E.1
02/23/2006 EXCAVATION/LAYOUT REBAR & ZON Not ready for Inspection IVRS - Inspection :*
02/22/2006 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
FOOTINGS @ NORTHSIDE OF 1-STORY BLDG; LINES 1/.5A-E
02/17/2006 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
EXTERIOR FOOTINGS @ SW CORNER OF 1-STORY BUILDING