Permit: T05CM05802
Permit Details
Apply Date:
11/21/2005
Applicant:
CAPPS, ANTHONY G
Description:
AUTO SERVICE BUILDING:NEW
Contractors:
- DAMITIO CONSTRUCTION INC ,
Permit Reviews
Permit Number - T05CM05802
Permit Status: C of o
Permit Description: AUTO SERVICE BUILDING:NEW
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
02/13/2006 | RESUBMITTAL - SITE ALL | 03/10/2006 | COMPLETED |
02/13/2006 | POST 3RD PARTY REVIEW | 03/10/2006 | COMPLETED |
03/24/2006 | RESUBMITTAL | 05/12/2006 | COMPLETED |
11/21/2005 | PLANS OK TO SUBMIT - 3RD PARTY | 11/23/2005 | COMPLETED |
11/21/2005 | SITE | 02/13/2006 | COMPLETED |
11/23/2005 | 3RD PARTY REVIEW-COMMERCIAL | 02/13/2006 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T05CM05802
Permit Status: C of o
Permit Description: AUTO SERVICE BUILDING:NEW
Total Outstanding Activity Conditions - 1
Date | Name |
---|---|
11/21/2005 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T05CM05802
Permit Description: AUTO SERVICE BUILDING:NEW
Total Completed Inspections - 38
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
05/17/2006 | EXCAVATION/LAYOUT REBAR & ZON | LHANLY | Approved | IVRS - Inspection :* |
05/18/2006 | ELECTRIC - UFER | RSUBA | Approved | IVRS - Inspection :* |
05/18/2006 | ELECTRIC - UFER | RSUBA | Approved | CONTRACTOR WASN'T READY LEE RAY WAS TO COMPLETE THIS INSP. PER OUR CONVERSATION & ENTER RESULTS. |
05/22/2006 | STEM WALL/RETAINING WALL | LHANLY | Approved | IVRS - Inspection :* |
06/06/2006 | PLUMBING - ROUGH, SOIL | RRICH | Approved | IVRS - Inspection :* 1 1/4 WATER STUB T/L LOOPED UP AT NORTHEAST CORNER OK PIPE WRAPS OK |
06/07/2006 | BUILDING PRE-SLAB | LHANLY | Approved | IVRS - Inspection :* |
07/19/2006 | ROOF NAILING | GDABBS | Approved | IVRS - Inspection :* |
07/21/2006 | FRAMING | GDABBS | Approved | IVRS - Inspection :* FRAMING & SHEETING AT EXTERIOR POP OUTS OK |
07/28/2006 | MECHANICAL - INTERMEDIATE | JMILITEL | Approved | IVRS - Inspection :* SUPPLY & EXHAUST IN RESTROOMS OK FOR SHEETROCK CONDENSATE LINE IN WALL OK TO COVER SUSPENDED ROUGH DUCT OK TO PROCEED. |
07/28/2006 | PLUMBING - YARD WTR LINE/TEST | RRICH | Approved | IVRS - Inspection :* FROM METER THRU RPB INTO BUILDING APPROVED SHALL INSPECT CLOSET FLANGES PRIOR TO INSTALL OF STOCKS. FLANGES TO BE INSTALLED CORRECTLY & SECURED TO FLOORING. |
07/28/2006 | PLUMBING - INTERMEDIATE | RRICH | Approved | IVRS - Inspection :* WATER TEST THRU ROOF WASTE & VENT WATER PIPING OK |
08/11/2006 | STUCCO MESH | GDABBS | Approved | IVRS - Inspection :* |
09/25/2006 | U VALUE FOR WINDOW | GDABBS | Approved | IVRS - Inspection :* |
09/25/2006 | BUILDING ABOVE CEILING | GDABBS | Approved | IVRS - Inspection :* |
09/25/2006 | FIRE - FINAL | LTHOMAS | Approved | |
09/25/2006 | ELECTRIC - OUTDOOR LIGHTING | RSUBA | Approved | IVRS - Inspection :* |
09/25/2006 | ELECTRIC - INTERMEDIATE | RSUBA | Approved | IVRS - Inspection :* |
10/11/2006 | MECHANICAL - ABOVE CEILING | JMILITEL | Approved | IVRS - Inspection :* OK FOR CEILING TILES IDENTIFY HEAT STRIP ON DATA PLATE. |
10/11/2006 | ELECTRIC - CABLE DROP | RSUBA | Approved | IVRS - Inspection :* |
10/18/2006 | ELECTRIC - TEMP POWER FOR TEST | RSUBA | Approved | IVRS - Inspection :* |
10/19/2006 | TEP CLEARANCE - AM | JWEATHER | Approved | TEC CLEARED PER R. SUBA |
10/25/2006 | SIGN - FINAL | JYBARRA | Approved | IVRS - Inspection :* |
10/26/2006 | MECHANICAL - FINAL | JMILITEL | Approved | IVRS - Inspection :* |
10/26/2006 | OUTDOOR LIGHTING FINAL | DSANTACR | Approved | IVRS - Inspection :* |
10/26/2006 | BUILDING - FINAL | GDABBS | Approved | IVRS - Inspection :* |
10/26/2006 | PLUMBING - SEWER HCS CONNECT | RRICH | Approved | IVRS - Inspection :* |
10/26/2006 | SITE - SEWER | RRICH | Approved | IVRS - Inspection :* |
10/27/2006 | NPPO - FINAL | JLINVILL | Approved | OK FOR TCO FOR 30 DAYS |
10/27/2006 | LANDSCAPE - FINAL | JLINVILL | Approved | OK FOR TCO FOR 30 DAYS |
10/27/2006 | ELECTRIC - UNDERGROUND | RHOLLAND | Approved | |
10/27/2006 | ELECTRIC - FINAL | RHOLLAND | Approved | PER SHEET |
10/27/2006 | EXT METAL CLIPS/EXT SHEATHING | GDABBS | Approved | PER BUILDING FINAL |
10/27/2006 | SHEET ROCK NAILING | GDABBS | Approved | PER BUILDING FINAL INSPECTION |
10/27/2006 | REINFORCED MASONRY PRE-GROUT | GDABBS | Approved | PER FINAL INSPECTION |
10/27/2006 | RIGHT OF WAY - FINAL | PWHIDDON | Approved | |
10/27/2006 | PLUMBING - FINAL | RLEDONNE | Approved | IVRS - Inspection :* |
10/31/2006 | ENGINEERING - FINAL | NKALAHAR | Approved | follow up inspection |
04/11/2007 | PERMIT FINALED | ACONNOR | Approved |