Permit: T05CM05802

Parcel: 14117007F


Addresses:

7525 S HOUGHTON RD

Inspection Status: Approved

Inspection History: ENGINEERING - FINAL

Date Description Inspector Results Comments
10/31/2006 ENGINEERING - FINAL Approved follow up inspection
10/27/2006 ENGINEERING - FINAL Approved PER INSPECTION SHEET

INSPECTOR COMMENTS:
BICYCLE PARKING INSTALLED
PAAL STRIPING IN
10/26/2006 ENGINEERING - FINAL Denied MET ON SITE WITH LOU BOCK AND RANDY (DAMITIO)

- BICYCLE PARKING SPACES REQ'D- 1 CLASS 1 AND 2 CLASS II NOT INSTALLED
-STRIPING NOT DONE TO PLAN (PER LOU WILL BE CP 10/27)

-ALL DISTURBED AREAS NEED TO BE STABILIZED-HELD TO GRADING PERMIT T04BU02370
09/26/2006 ENGINEERING - FINAL Not ready for Inspection SITE NOT READY, PRELIMINARY INSPECTION ONLY.
SUBMIT PAPER WORK (APPLICATION) FOR TEMP C OF O.