Permit: T05CM04625
Permit Details
Apply Date:
09/07/2005
Applicant:
JOHN FENECK
Description:
ADDITION:OFFICE
Contractors:
- LUNDGREN HOMES INC
Permit Reviews
Permit Number - T05CM04625
Permit Status: Final
Permit Description: ADDITION:OFFICE
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 09/07/2005 | PLANS OK TO SUBMIT - 3RD PARTY | 09/13/2005 | COMPLETED |
| 09/09/2005 | SITE | 10/07/2005 | COMPLETED |
| 09/13/2005 | 3RD PARTY REVIEW-COMMERCIAL | 10/04/2005 | COMPLETED |
| 10/04/2005 | POST 3RD PARTY REVIEW | 10/21/2005 | COMPLETED |
| 10/07/2005 | SITE | 10/21/2005 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T05CM04625
Permit Status: Final
Permit Description: ADDITION:OFFICE
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 09/07/2005 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: Final
Permit Number: T05CM04625
Permit Description: ADDITION:OFFICE
Total Completed Inspections - 21
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 10/26/2005 | BUILDING PRE-SLAB | LHANLY | Approved | IVRS - Inspection :* |
| 10/26/2005 | EXCAVATION/LAYOUT REBAR & ZON | LHANLY | Approved | IVRS - Inspection :* |
| 11/07/2005 | ELECTRIC - INTERMEDIATE | RSUBA | Approved | IVRS - Inspection :* |
| 11/07/2005 | ROOF NAILING | LHANLY | Approved | IVRS - Inspection :* |
| 11/10/2005 | MECHANICAL - INTERMEDIATE | CWILLIAM | Approved | IVRS - Inspection :*HAVE YOUR A/C CONTRACTOR INSULATE THE SHEET METAL SUPPLY/RETURN FLORED REGISTER |
| 11/15/2005 | FRAMING | LHANLY | Approved | IVRS - Inspection :*APPROVED |
| 11/15/2005 | EXT METAL CLIPS/EXT SHEATHING | LHANLY | Approved | IVRS - Inspection :* |
| 11/21/2005 | BUILDING ABOVE CEILING | LHANLY | Approved | IVRS - Inspection :* |
| 11/21/2005 | U VALUE FOR WINDOW | LHANLY | Approved | IVRS - Inspection :* |
| 11/21/2005 | STUCCO MESH | LHANLY | Approved | IVRS - Inspection :* |
| 11/21/2005 | SHEET ROCK NAILING | LHANLY | Approved | IVRS - Inspection :* |
| 01/10/2006 | FIRE - FINAL | LTHOMAS | Approved | |
| 06/20/2006 | ENGINEERING - FINAL | NKALAHAR | Approved | TALKED TO CHRIS LUNDGREN NO SITE WORK WALKED SITE-TI ONLY |
| 06/20/2006 | SIGN - FINAL | JYBARRA | Approved | IVRS - Inspection :* |
| 06/20/2006 | ELECTRIC - FINAL | RSUBA | Approved | IVRS - Inspection :* |
| 06/20/2006 | RIGHT OF WAY - FINAL | NBRIGGS | Approved | PER EMAIL |
| 10/24/2006 | MECHANICAL - FINAL | CWILLIAM | Approved | IVRS - Inspection :* HEAT STRIP REMOVED -- UNIT FUNCTION STRAIGHT HEAT PUMP -- CORRECTLY FUSED & ID'D |
| 10/31/2006 | BUILDING - FINAL | GDABBS | Approved | IVRS - Inspection :* |
| 11/01/2006 | PERMIT FINALED | BFLORES | Approved | |
| 11/01/2006 | MECHANICAL - ABOVE CEILING | CWILLIAM | Approved | |
| 11/01/2006 | ELECTRIC - ABOVE CEILING | RSUBA | Approved |