Permit: T05CM02332
Permit Details
Apply Date:
05/23/2005
Applicant:
METRO PERMIT EXPRESS, INC *C
Description:
NEW RETAIL SHELL
Contractors:
- LLOYD CONSTRUCTION COMPANY INC ,
Permit Reviews
Permit Number - T05CM02332
Permit Status: Final
Permit Description: NEW RETAIL SHELL
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
05/23/2005 | PLANS OK TO SUBMIT - 3RD PARTY | 05/23/2005 | COMPLETED |
05/23/2005 | 3RD PARTY REVIEW-COMMERCIAL | 08/05/2005 | COMPLETED |
08/05/2005 | POST 3RD PARTY REVIEW | 09/20/2005 | COMPLETED |
09/06/2006 | 3RD PARTY REVIEW-REVISION/OTHER | 11/17/2006 | COMPLETED |
09/21/2005 | RESUBMITTAL | 09/28/2005 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T05CM02332
Permit Status: Final
Permit Description: NEW RETAIL SHELL
Total Outstanding Activity Conditions - 1
Date | Name |
---|---|
05/23/2005 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: Final
Permit Number: T05CM02332
Permit Description: NEW RETAIL SHELL
Total Completed Inspections - 38
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
10/19/2005 | ELECTRIC - TEMPORARY SERVICE | RSUBA | Approved | IVRS - Inspection :* |
10/20/2005 | TEP CLEARANCE - AM | JKOZUCH | Approved | ECO |
11/14/2005 | ELECTRIC - UFER | RHOLLAND | Approved | IVRS - Inspection :* 1) OK 3-3/0 TO 20' REBAR 2) ? NEED 2-3/4 X 10 GROUND RODS ? PLEASE CHECK WITH ENGINEER AND GET A LETTER |
11/30/2005 | EXCAVATION/LAYOUT REBAR & ZON | JCAGLE | Approved | IVRS - Inspection :*FOOTING @ LINES B/10 |
12/05/2005 | STEM WALL/RETAINING WALL | JCAGLE | Approved | IVRS - Inspection :*LINES B/1-9.9 D/7-10 ( STEM WALL) GET CLARIFICATION FROM ENGINEER AS TO MASON? @ LINES 10/B IS A COLUMN OR PIER. |
12/12/2005 | ELECTRIC - INTERMEDIATE | RSUBA | Approved | IVRS - Inspection :* FEEDERS & PARTIAL OK T.E.P |
12/12/2005 | PLUMBING - ROUGH, SOIL | TRINIVJR | Approved | IVRS - Inspection :*SOIL WATER TEST IS OK NOTE: BLDG DRAIN IS STUBBED OUT OF BLDG @ TWO WAY C.O ONLY OK TO BACKFILL TRENCH SHALL USE CLEAN FILL. |
12/30/2005 | REINFORCED MASONRY PRE-GROUT | JCAGLE | Approved | IVRS - Inspection : See detailed listing on site.| 999* 1) JOB SITE LOCKED-NO ACCESS |
12/30/2005 | BUILDING PRE-SLAB | IVR USER | Approved | IVRS - RI canceled |
03/29/2006 | PLUMBING - SEWER HCS CONNECT | RRICH | Approved | IVRS - Inspection :* (2) 4" SCH 40 PVC HCS FROM 2-WAY CLEANOUT TO EXISTING POINT OF CONNECTION. |
04/10/2006 | ROOF NAILING | JBURGE | Approved | IVRS - Inspection :* |
04/11/2006 | FIRE SPKLR - OH PIPING & HYDRO | LTHOMAS | Approved | overhead press test OK |
04/18/2006 | MECHANICAL - INTERMEDIATE | JMILITEL | Approved | IVRS - Inspection :* SUPPLY & EXHAUST IN RESTROOMS OK CONDENSATE DRAINS OK OK TO SHEETROCK |
04/21/2006 | SHEET ROCK NAILING | JBURGE | Approved | IVRS - Inspection :* |
04/26/2006 | EXT METAL CLIPS/EXT SHEATHING | JCAGLE | Approved | IVRS - Inspection :* |
05/19/2006 | STUCCO MESH | JBURGE | Approved | IVRS - Inspection :* |
05/31/2006 | PLUMBING - INTERMEDIATE | RRICH | Approved | IVRS - Inspection :* |
06/20/2006 | ELECTRIC - OUTDOOR LIGHTING | RSUBA | Approved | IVRS - Inspection :* 1) OK BATHROOMS, COMPLETE NOTE BATTERY BACK UP 2) OK HOUSE PANEL LIGHTING CONTRACTOR, ROOF, EXTERIOR LIGHTING AND FLOW SWITCH |
07/06/2006 | ELECTRIC - FINAL | RHOLLAND | Approved | IVRS - Inspection :* OK FINAL 1. RECEPTACLE COVER TO BE WEATHERPROOF WHETHER OR NOT PLUGGED IN 406.8 2. CHASE NIPPLE NOT APPROVED FOR GROUNDING, PLEASE RUN A GROUND WIRE. |
07/06/2006 | ELECTRIC - CABLE DROP | RHOLLAND | Approved | IVRS - Inspection :* |
07/11/2006 | FIRE - FINAL | LTHOMAS | Approved | |
07/11/2006 | FIRE SPKLR - FINAL | LTHOMAS | Approved | |
07/11/2006 | FIRE SPKLR - UG PIPING FLUSH | LTHOMAS | Approved | |
07/11/2006 | FIRE SPKLR - UG, PIPING, HYDRO | LTHOMAS | Approved | |
07/17/2006 | PLUMBING - FINAL | RRICH | Approved | IVRS - Inspection :* |
07/17/2006 | PLUMBING - ABOVE CEILING | RRICH | Approved | IVRS - Inspection :* |
07/17/2006 | PLUMBING - YARD WTR LINE/TEST | RRICH | Approved | IVRS - Inspection :* |
08/21/2006 | NPPO - FINAL | ACONNOR | Approved | |
08/21/2006 | LANDSCAPE - FINAL | ACONNOR | Approved | |
08/21/2006 | U VALUE FOR WINDOW | JBURGE | Approved | IVRS - Inspection :* |
08/21/2006 | BUILDING ABOVE CEILING | JBURGE | Approved | IVRS - Inspection :* |
08/21/2006 | FRAMING | JBURGE | Approved | IVRS - Inspection :* |
08/22/2006 | RIGHT OF WAY - FINAL | NBRIGGS | Approved | OK TO CLEAR |
08/23/2006 | SIGN - FINAL | JYBARRA | Approved | IVRS - Inspection :* |
10/13/2006 | MECHANICAL - FINAL | JMILITEL | Approved | IVRS - Inspection :* OK FOR FINAL A/C UNITS WILL BE CONNECTED & DUCTED DURING TENANT IMPROVEMENTS. |
10/26/2006 | BUILDING - FINAL | JBURGE | Approved | IVRS - Inspection :* WATER BASINS INSTALLED |
12/26/2006 | SITE - SEWER | RRICH | Approved | |
12/26/2006 | ENGINEERING - FINAL | JBRUCKME | Approved |