Permit: T05CM01656
Permit Details
Apply Date:
04/14/2005
Applicant:
STEVE HAMMOND
Description:
DUPLEX:NEW rev1: change supply to sub-panels to aluminum
Contractors:
- PREMIER CONSTRUCTION CORPORATION
Permit Reviews
Permit Number - T05CM01656
Permit Status: C of o
Permit Description: DUPLEX:NEW
rev1: change supply to sub-panels to aluminum
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 01/25/2006 | REVISION - - 1ST | 01/25/2006 | COMPLETED |
| 04/14/2005 | PLANS OK TO SUBMIT - RES | 07/13/2005 | COMPLETED |
| 07/13/2005 | RESIDENTIAL BLDG/WWM | 08/10/2005 | COMPLETED |
| 08/29/2005 | RESUBMITTAL | 09/12/2005 | COMPLETED |
| 09/14/2006 | REVISION - - 2ND | 09/14/2006 | ACTIVE |
Outstanding Activity Conditions
Permit Number - T05CM01656
Permit Status: C of o
Permit Description: DUPLEX:NEW
rev1: change supply to sub-panels to aluminum
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 04/14/2005 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T05CM01656
Permit Description: DUPLEX:NEW
rev1: change supply to sub-panels to aluminum
Total Completed Inspections - 23
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 04/12/2006 | PLUMBING - ROUGH, SOIL | BBENEDON | Approved | IVRS - Inspection :* |
| 04/19/2006 | PLUMBING - SEWER HCS CONNECT | BBENEDON | Approved | IVRS - Inspection :* |
| 04/20/2006 | ELECTRIC - UFER | LHANLY | Approved | IVRS - Inspection :* |
| 04/20/2006 | BUILDING PRE-SLAB | LHANLY | Approved | IVRS - Inspection :* |
| 04/20/2006 | EXCAVATION/LAYOUT REBAR & ZON | LHANLY | Approved | IVRS - Inspection :* |
| 05/31/2006 | ROOF NAILING | AALEGRIA | Approved | IVRS - Inspection :* |
| 06/05/2006 | FRAMING | AALEGRIA | Approved | IVRS - Inspection :* |
| 06/05/2006 | BUILDING - FINAL | AALEGRIA | Approved | IVRS - Inspection :* |
| 06/15/2006 | PLUMBING - YARD WTR LINE/TEST | RLEDONNE | Approved | IVRS - Inspection :* |
| 06/15/2006 | PLUMBING - INTERMEDIATE | RLEDONNE | Approved | IVRS - Inspection :* |
| 06/21/2006 | ELECTRIC - INTERMEDIATE | DSANTACR | Approved | IVRS - Inspection :* |
| 07/12/2006 | U VALUE FOR WINDOW | AALEGRIA | Approved | IVRS - Inspection :* |
| 07/12/2006 | STUCCO MESH | AALEGRIA | Approved | IVRS - Inspection :* |
| 09/18/2006 | ELECTRIC - TEMPORARY SERVICE | DSANTACR | Approved | IVRS - Inspection :* |
| 09/18/2006 | ELECTRIC - CABLE DROP | DSANTACR | Approved | IVRS - Inspection :* |
| 09/19/2006 | TEP CLEARANCE - AM | JWEATHER | Approved | TEC CLEARED FOR UNITS #1 & #2 PER D. SANTACRUZ |
| 11/15/2006 | REINFORCED MASONRY PRE-GROUT | LHANLY | Approved | |
| 11/15/2006 | SHEET ROCK NAILING | LHANLY | Approved | |
| 11/16/2006 | PLUMBING - FINAL | RLEDONNE | Approved | IVRS - Inspection :* |
| 11/16/2006 | ELECTRIC - FINAL | DSANTACR | Approved | IVRS - Inspection :* |
| 11/17/2006 | PERMIT FINALED | BFLORES | Approved | |
| 11/17/2006 | MECHANICAL - INTERMEDIATE | CWILLIAM | Approved | |
| 11/17/2006 | MECHANICAL - FINAL | CWILLIAM | Approved | IVRS - Inspection :* |