Permit Details

Status:
C of o
Type:
COMMERCIAL ADDITION
Apply Date:
04/13/2005
Applicant:
JOEL KRAMER
Description:
ADDITION: FLOORROOM SPACE
Contractors:
  • TUTTLE CO , THE J R

Permit Reviews

Permit Number - T05CM01626
Permit Status: C of o
Permit Description: ADDITION: FLOORROOM SPACE
Start Date Submittal Complete Date Status  
04/13/2005 PLANS OK TO SUBMIT - 3RD PARTY 05/10/2005 COMPLETED Review Details
04/13/2005 PLANS OK TO SUBMIT - SITE 04/15/2005 COMPLETED Review Details
04/15/2005 SITE 05/24/2005 COMPLETED Review Details
05/10/2005 3RD PARTY REVIEW-COMMERCIAL TI 07/15/2005 COMPLETED Review Details
06/03/2005 RESUBMITTAL - SITE ALL 06/29/2005 COMPLETED Review Details
07/06/2005 RESUBMITTAL - SITE 07/15/2005 COMPLETED Review Details
07/15/2005 POST 3RD PARTY REVIEW 07/15/2005 COMPLETED Review Details

Outstanding Activity Conditions

Permit Number - T05CM01626
Permit Status: C of o
Permit Description: ADDITION: FLOORROOM SPACE
Total Outstanding Activity Conditions - 1
Date Name
04/13/2005 PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION.

Completed Inspections

Permit Status: C of o
Permit Number: T05CM01626
Permit Description: ADDITION: FLOORROOM SPACE
Total Completed Inspections - 30
Date Description Inspector Results Comments
08/03/2005 EXCAVATION/LAYOUT REBAR & ZON LHANLY Approved IVRS - Inspection :*
APPROVED N FOOTER
08/03/2005 STEM WALL/RETAINING WALL LHANLY Approved IVRS - Inspection :*
08/11/2005 BUILDING PRE-SLAB LHANLY Approved IVRS - Inspection :*
09/08/2005 REINFORCED MASONRY PRE-GROUT LHANLY Approved IVRS - Inspection :*
09/23/2005 ELECTRIC - INTERMEDIATE RSUBA Approved IVRS - Inspection :*
09/23/2005 ROOF NAILING LHANLY Approved IVRS - Inspection :*
09/28/2005 MECHANICAL - ABOVE CEILING JMILITEL Approved IVRS - Inspection :*RETURN & SUPPLY DROPS THRU ROOF. ON FINAL WILL CHECK CONDENSATE DRAINS, DUCT SMOKE DETECTORS.
09/28/2005 MECHANICAL - INTERMEDIATE JMILITEL Approved IVRS - Inspection :*
09/28/2005 FIRE SPKLR - OH PIPING & HYDRO LTHOMAS Approved
10/03/2005 PLUMBING - ROOF DRAINS RRICH Approved WATER TEST 4 SOTS 4" RAIN DRAIN & OVERFLOW RAIN DRAINS ON WEST END OK
PROVIDE HANGERS ON OVERFLOW DRAIN AT 90 DEGREE TO DRAIN BODY IVRS - Inspection :*
10/05/2005 EXT METAL CLIPS/EXT SHEATHING RRICH Approved NO PROGRESS SINCE LAST INSPECTION IVRS - Inspection :*
10/05/2005 PLUMBING - FINAL RRICH Approved IVRS - Inspection :*
10/10/2005 FRAMING LHANLY Approved IVRS - Inspection :*
10/18/2005 U VALUE FOR WINDOW LHANLY Approved IVRS - Inspection :*
10/18/2005 STUCCO MESH LHANLY Approved IVRS - Inspection :*
10/18/2005 BUILDING ABOVE CEILING LHANLY Approved IVRS - Inspection :*
10/19/2005 ELECTRIC - OUTDOOR LIGHTING RSUBA Approved IVRS - Inspection :*
10/19/2005 ELECTRIC - ABOVE CEILING RSUBA Approved IVRS - Inspection :*
10/20/2005 OUTDOOR LIGHTING FINAL RSUBA Approved IVRS - Inspection :*
10/20/2005 ELECTRIC - FINAL RSUBA Approved IVRS - Inspection :*
10/20/2005 SIGN - FINAL JYBARRA Approved IVRS - Inspection :*
10/20/2005 FIRE - FINAL LTHOMAS Approved
10/20/2005 FIRE - HYDRANTS LTHOMAS Approved
10/20/2005 FIRE SPKLR - FINAL LTHOMAS Approved
10/21/2005 RIGHT OF WAY - FINAL LLOPEZ Approved OK TO RELEASE
11/03/2005 MECHANICAL - FINAL CWILLIAM Approved IVRS - Inspection :*
11/03/2005 LANDSCAPE - FINAL ACONNOR Approved OK for Temp. C of O
11/04/2005 BUILDING - FINAL CGROSS Approved OK FOR TEMP C OF O PER CRAIG GROSS
11/28/2005 ENGINEERING - FINAL NKALAHAR Approved 1. P.A.A.L. STRIPING (NORTH TO GOLF LINKS) NOT COMPLETE
2. PARKING LOT STRIPING (WEST SIDE OF BUILDING) NOT COMPLETE
3. CONCRETE NOT REPLACED AT DOWNSPOUT (SOUTH SIDE OF BUILDING)
4. RAILING NOT IN AT WEST ENTRANCE (MORE THAN 6" REVEAL ON CURB)
5. HANDICAPPED PARKING/ACCESS ISSUE STILL NEEDS TO BE RESOLVED (WEST SIDE OF BUILDING)
6. CURBING FOR P.A.A.L. SIDEWALK NOT COMPLETE (NORTH OF BUILDING TO GOLF LINKS)
7. GENERAL CLEAN UP OF CONSTRUCTION DEBRIS

SPOKE TO SITE SUPER (ED WITH TL ROOF) HE EXPECTS TO CALL FOR FINAL LATER THIS WEEK
04/05/2006 PERMIT FINALED LJACKSON Approved

Documents

File Name Document Type  
COFO_03-08-2006.TIF CERT OF OCC VIEW
TEMPORARY COFO_11-04-2005.TIF CERT OF OCC VIEW
None DOCUMENTS VIEW