Date Description Inspector Results Comments
01/19/2006 ENGINEERING - FINAL Approved STRIPING COMPLETE
HANDRAIL IN PLACE IN R.O.W.
01/12/2006 ENGINEERING - FINAL Partial Approval NO CHANGE IN SITE
NO HANDRAIL IN ROW
NO STRIPING WORK YET
01/09/2006 ENGINEERING - FINAL Partial Approval Yes, he will need to provide hand railing on both sides of the sidewalk per COT Development Standards. It is considered a ramp.

Richard Leigh
Engineering Associate
DOT, Engineering, Permits & Code Unit
201 N. Stone Ave, 4th Floor
Tucson AZ, 85701
520-791-5100
Richard.Leigh@tucsonaz.gov


>>> Nichole Kalahar 01/05/06 7:54 AM >>>
Hello there Mr. Richard,

This property is a unique site. It is a retro-fit of an old K-mart store. In order to comply with new development standards, a new P.A.A.L. was put in and striped going from the store front to Golf Links Rd. There is a tie in from the parking lot to the sidewalk along Golf Links Rd. That side walk is 5' wide and has about an 11% slope to it (14" of drop in 10' approx.). The site super is wondering if he should put hand railing in due to it's steepness. I am deferring his questions to you since it is in the R.O.W.

Thanks,

Nichole
240-0153
01/04/2006 ENGINEERING - FINAL Partial Approval SIDEWALK LEADING FROM PAAL TO SIDEWALK ALONG NORTH SIDE OF PROJECT ALONG GOLF LINKS RD HAS 11% SLOPE (14" OF DROP IN 10' APROX) MADE RIGHT OF WAY AWARE VIA EMAIL 1/5/06
11/28/2005 ENGINEERING - FINAL Partial Approval 1. P.A.A.L. STRIPING (NORTH TO GOLF LINKS) NOT COMPLETE
2. PARKING LOT STRIPING (WEST SIDE OF BUILDING) NOT COMPLETE
3. CONCRETE NOT REPLACED AT DOWNSPOUT (SOUTH SIDE OF BUILDING)
4. RAILING NOT IN AT WEST ENTRANCE (MORE THAN 6" REVEAL ON CURB)
5. HANDICAPPED PARKING/ACCESS ISSUE STILL NEEDS TO BE RESOLVED (WEST SIDE OF BUILDING)
6. CURBING FOR P.A.A.L. SIDEWALK NOT COMPLETE (NORTH OF BUILDING TO GOLF LINKS)
7. GENERAL CLEAN UP OF CONSTRUCTION DEBRIS

SPOKE TO SITE SUPER (ED WITH TL ROOF) HE EXPECTS TO CALL FOR FINAL LATER THIS WEEK
11/15/2005 ENGINEERING - FINAL Correction Required INSPECTED TRUNCATED DOMES-SET BACK IS 6"-8" AS DETAIL SHOWS
11/14/2005 ENGINEERING - FINAL Correction Required TALKED TO ED ABOUT TRUNCATED DOMES. WILL PROVIDE DETAIL 11/15. HANDICAPPED ACCESS ISSUE ON WEST SIDE STILL EXISTS. GRADE CHANGE TO FLATTEN HANDICAPPED ACCESS HAS BEEN PROPOSED.
STRIPING FOR PARKING AND P.A.A.L. HAS BEEN DONE ON NORTH SIDE OF BUILDING EXCEPT FROM MEDIAN STRUCTURE TO GOLF LINKS
CONCRETE STILL NEEDS TO BE POURED AT THE REAR OF BUILDING AND SPLASH BLOCKS NEED TO BE PLACED.
STILL GENERAL CLEAN UP OF CONST DEBRIS.
11/04/2005 ENGINEERING - FINAL Partial Approval OK FOR TEMP C OF O PER CRAIG GROSS
11/04/2005 ENGINEERING - FINAL Correction Required 1. P.A.A.L. STRIPING (NORTH TO GOLF LINKS) NOT COMPLETE
2. PARKING LOT STRIPING (WEST AND NORTH SIDE OF BUILDING) NOT COMPLETE
3. CONCRETE NOT REPLACED AT DOWNSPOUT (SOUTH SIDE OF BUILDING)
4. RAILING NOT IN AT WEST ENTRANCE (MORE THAN 6" REVEAL ON CURB)
5. HANDICAPPED PARKING/ACCESS ISSUE STILL NEEDS TO BE RESOLVED (WEST SIDE OF BUILDING)
6. CURBING FOR P.A.A.L. SIDEWALK NOT COMPLETE (NORTH OF BUILDING TO GOLF LINKS)
7. GENERAL CLEAN UP OF CONSTRUCTION DEBRIS
8. SILT NEEDS TO BE REMOVED FROM DRAINAGE AT WEST SIDE OF PROJECT NORTH OF DRIVEWAY
9. SIDEWALK STRIPING HAS BEEN SEAL COATED ON NORTH SIDE OF BUILDING
11/03/2005 ENGINEERING - FINAL Correction Required ALL RAILINGS TO BE INSTALLED ON SIDEWALKS WITH GREATER THAN A 6" REVEAL CURB ON WEST SIDE OF BUILDING

HANDICAPPED PARKING ISSUE (WEST SIDE OF BUILDING) NEEDS TO BE ADDRESSED AND REVIEWED BY COT STAFF

ALL P.A.A.L. STRIPING TO BE COMPLETE AND SIDEWALKS IN PLACE TO GOLF LINKS RD (CURB CREW ON SITE TODAY)

PREVIOUS ITEMS FROM INSP 10/28 STILL NOT COMPLETE

SILT TO BE REMOVED FROM DRAINAGE AT WEST SIDE OF PROJECT NORTH OF DRIVEWAY

LOADING ZONE AT REAR OF ADDITION TO BE STRIPED

GENERAL CLEAN UP OF ALL CONSTRUCTION DEBRIS
10/28/2005 ENGINEERING - FINAL Partial Approval BEFORE PERMANENT C OF O

SILT TO BE REMOVED FROM DRAINAGE AT WEST SIDE OF PROJECT NORTH OF DRIVEWAY

ALL P.A.A.L. STRIPING TO BE COMPLETE AND SIDEWALKS IN PLACE TO GOLF LINKS RD

LOADING ZONE AT REAR OF ADDITION TO BE STRIPED

ALL RAILINGS TO BE INSTALLED ON SIDEWALKS WITH GREATER THAN A 6" REVEAL CURB

GENERAL CLEAN UP OF ALL CONSTRUCTION DEBRIS
10/20/2005 ENGINEERING - FINAL Partial Approval SITE WORK IS COMPLETE ENOUGH FOR STOCKING PURPOSES ONLY.