Inspection Status: Approved
Inspection History: ENGINEERING - FINAL
Permit Number - T05CM01626
Inspection Description - ENGINEERING - FINAL
Inspection Status - Approved
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
01/19/2006 | ENGINEERING - FINAL | Approved | STRIPING COMPLETE HANDRAIL IN PLACE IN R.O.W. |
|
01/12/2006 | ENGINEERING - FINAL | Partial Approval | NO CHANGE IN SITE NO HANDRAIL IN ROW NO STRIPING WORK YET |
|
01/09/2006 | ENGINEERING - FINAL | Partial Approval | Yes, he will need to provide hand railing on both sides of the sidewalk per COT Development Standards. It is considered a ramp. Richard Leigh Engineering Associate DOT, Engineering, Permits & Code Unit 201 N. Stone Ave, 4th Floor Tucson AZ, 85701 520-791-5100 Richard.Leigh@tucsonaz.gov >>> Nichole Kalahar 01/05/06 7:54 AM >>> Hello there Mr. Richard, This property is a unique site. It is a retro-fit of an old K-mart store. In order to comply with new development standards, a new P.A.A.L. was put in and striped going from the store front to Golf Links Rd. There is a tie in from the parking lot to the sidewalk along Golf Links Rd. That side walk is 5' wide and has about an 11% slope to it (14" of drop in 10' approx.). The site super is wondering if he should put hand railing in due to it's steepness. I am deferring his questions to you since it is in the R.O.W. Thanks, Nichole 240-0153 |
|
01/04/2006 | ENGINEERING - FINAL | Partial Approval | SIDEWALK LEADING FROM PAAL TO SIDEWALK ALONG NORTH SIDE OF PROJECT ALONG GOLF LINKS RD HAS 11% SLOPE (14" OF DROP IN 10' APROX) MADE RIGHT OF WAY AWARE VIA EMAIL 1/5/06 | |
11/28/2005 | ENGINEERING - FINAL | Partial Approval | 1. P.A.A.L. STRIPING (NORTH TO GOLF LINKS) NOT COMPLETE 2. PARKING LOT STRIPING (WEST SIDE OF BUILDING) NOT COMPLETE 3. CONCRETE NOT REPLACED AT DOWNSPOUT (SOUTH SIDE OF BUILDING) 4. RAILING NOT IN AT WEST ENTRANCE (MORE THAN 6" REVEAL ON CURB) 5. HANDICAPPED PARKING/ACCESS ISSUE STILL NEEDS TO BE RESOLVED (WEST SIDE OF BUILDING) 6. CURBING FOR P.A.A.L. SIDEWALK NOT COMPLETE (NORTH OF BUILDING TO GOLF LINKS) 7. GENERAL CLEAN UP OF CONSTRUCTION DEBRIS SPOKE TO SITE SUPER (ED WITH TL ROOF) HE EXPECTS TO CALL FOR FINAL LATER THIS WEEK |
|
11/15/2005 | ENGINEERING - FINAL | Correction Required | INSPECTED TRUNCATED DOMES-SET BACK IS 6"-8" AS DETAIL SHOWS | |
11/14/2005 | ENGINEERING - FINAL | Correction Required | TALKED TO ED ABOUT TRUNCATED DOMES. WILL PROVIDE DETAIL 11/15. HANDICAPPED ACCESS ISSUE ON WEST SIDE STILL EXISTS. GRADE CHANGE TO FLATTEN HANDICAPPED ACCESS HAS BEEN PROPOSED. STRIPING FOR PARKING AND P.A.A.L. HAS BEEN DONE ON NORTH SIDE OF BUILDING EXCEPT FROM MEDIAN STRUCTURE TO GOLF LINKS CONCRETE STILL NEEDS TO BE POURED AT THE REAR OF BUILDING AND SPLASH BLOCKS NEED TO BE PLACED. STILL GENERAL CLEAN UP OF CONST DEBRIS. |
|
11/04/2005 | ENGINEERING - FINAL | Partial Approval | OK FOR TEMP C OF O PER CRAIG GROSS | |
11/04/2005 | ENGINEERING - FINAL | Correction Required | 1. P.A.A.L. STRIPING (NORTH TO GOLF LINKS) NOT COMPLETE 2. PARKING LOT STRIPING (WEST AND NORTH SIDE OF BUILDING) NOT COMPLETE 3. CONCRETE NOT REPLACED AT DOWNSPOUT (SOUTH SIDE OF BUILDING) 4. RAILING NOT IN AT WEST ENTRANCE (MORE THAN 6" REVEAL ON CURB) 5. HANDICAPPED PARKING/ACCESS ISSUE STILL NEEDS TO BE RESOLVED (WEST SIDE OF BUILDING) 6. CURBING FOR P.A.A.L. SIDEWALK NOT COMPLETE (NORTH OF BUILDING TO GOLF LINKS) 7. GENERAL CLEAN UP OF CONSTRUCTION DEBRIS 8. SILT NEEDS TO BE REMOVED FROM DRAINAGE AT WEST SIDE OF PROJECT NORTH OF DRIVEWAY 9. SIDEWALK STRIPING HAS BEEN SEAL COATED ON NORTH SIDE OF BUILDING |
|
11/03/2005 | ENGINEERING - FINAL | Correction Required | ALL RAILINGS TO BE INSTALLED ON SIDEWALKS WITH GREATER THAN A 6" REVEAL CURB ON WEST SIDE OF BUILDING HANDICAPPED PARKING ISSUE (WEST SIDE OF BUILDING) NEEDS TO BE ADDRESSED AND REVIEWED BY COT STAFF ALL P.A.A.L. STRIPING TO BE COMPLETE AND SIDEWALKS IN PLACE TO GOLF LINKS RD (CURB CREW ON SITE TODAY) PREVIOUS ITEMS FROM INSP 10/28 STILL NOT COMPLETE SILT TO BE REMOVED FROM DRAINAGE AT WEST SIDE OF PROJECT NORTH OF DRIVEWAY LOADING ZONE AT REAR OF ADDITION TO BE STRIPED GENERAL CLEAN UP OF ALL CONSTRUCTION DEBRIS |
|
10/28/2005 | ENGINEERING - FINAL | Partial Approval | BEFORE PERMANENT C OF O SILT TO BE REMOVED FROM DRAINAGE AT WEST SIDE OF PROJECT NORTH OF DRIVEWAY ALL P.A.A.L. STRIPING TO BE COMPLETE AND SIDEWALKS IN PLACE TO GOLF LINKS RD LOADING ZONE AT REAR OF ADDITION TO BE STRIPED ALL RAILINGS TO BE INSTALLED ON SIDEWALKS WITH GREATER THAN A 6" REVEAL CURB GENERAL CLEAN UP OF ALL CONSTRUCTION DEBRIS |
|
10/20/2005 | ENGINEERING - FINAL | Partial Approval | SITE WORK IS COMPLETE ENOUGH FOR STOCKING PURPOSES ONLY. |