Permit: T05CM00027
Permit Details
Apply Date:
01/04/2005
Applicant:
N/A
Description:
SITE/NEW CHURCH BUILDING
Contractors:
- A P N BUILDERS INC ,
Permit Reviews
Permit Number - T05CM00027
Permit Status: C of o
Permit Description: SITE/NEW CHURCH BUILDING
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
01/04/2005 | PLANS OK TO SUBMIT - SITE | 01/05/2005 | COMPLETED |
01/05/2005 | SITE | 03/01/2005 | COMPLETED |
03/23/2006 | PLANS OK TO SUBMIT - 3RD PARTY | 03/29/2006 | COMPLETED |
03/29/2006 | 3RD PARTY REVIEW-COMMERCIAL | 06/27/2006 | COMPLETED |
04/20/2005 | RESUBMITTAL - SITE | 06/10/2005 | COMPLETED |
06/10/2005 | RESUBMITTAL - SITE | 06/28/2005 | COMPLETED |
06/27/2006 | POST 3RD PARTY REVIEW | 06/28/2006 | COMPLETED |
07/11/2005 | RESUBMITTAL - SITE | 11/17/2005 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T05CM00027
Permit Status: C of o
Permit Description: SITE/NEW CHURCH BUILDING
Total Outstanding Activity Conditions - 1
Date | Name |
---|---|
01/04/2005 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T05CM00027
Permit Description: SITE/NEW CHURCH BUILDING
Total Completed Inspections - 44
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
07/21/2006 | PLUMBING - ROUGH, SOIL | RLEDONNE | Approved | IVRS - Inspection :* PLUMBING ROUGH SOIL, OK INSIDE SLAB |
08/11/2006 | ELECTRIC - UFER | DSANTACR | Approved | IVRS - Inspection :* |
08/17/2006 | BUILDING PRE-SLAB | LHANLY | Approved | IVRS - Inspection :* |
09/05/2006 | EXCAVATION/LAYOUT REBAR & ZON | AALEGRIA | Approved | IVRS - Inspection :* IN COMPLIANCE WITH APPROVED PLANS SHEET S1 DETAIL FOR F4 3 #5 E. WAY 2'-6" SQ. X 1'0" |
09/13/2006 | REINFORCED MASONRY PRE-GROUT | AALEGRIA | Approved | IVRS - Inspection :* FRONT MASONRY WALL AND COLUMNS |
10/31/2006 | ELECTRIC - CONSTRUCTION POWER | DSANTACR | Approved | IVRS - Inspection :* 1) OK OUTSIDE TEMP POLE ONLY |
10/31/2006 | PLUMBING - YARD WTR LINE/TEST | RLEDONNE | Approved | IVRS - Inspection :* |
11/01/2006 | TEP CLEARANCE - AM | JWEATHER | Approved | TEC CLEARED PER D. SANTACRUZ |
11/21/2006 | MECHANICAL - INTERMEDIATE | JMILITEL | Approved | IVRS - Inspection :* SUSPENDED ROUGH DUCT OK TO PROCEED |
11/21/2006 | FRAMING | AALEGRIA | Approved | IVRS - Inspection :* EXCEPT KITCHEN (SHEET A-16) |
11/21/2006 | ELECTRIC - INTERMEDIATE | DSANTACR | Approved | IVRS - Inspection :* OK WALLS EXCEPT SOUND ROOM |
11/28/2006 | PLUMBING - INTERMEDIATE | RLEDONNE | Approved | IVRS - Inspection :* CALL BACK FOR OVERHEAD DO NOT COVER OVERHEAD |
12/04/2006 | ELECTRIC - UNDERGROUND | DSANTACR | Approved | IVRS - Inspection :* OK U.G CONDUIT & POLE BASES FOR PARKING |
12/05/2006 | STEM WALL/RETAINING WALL | AALEGRIA | Approved | IVRS - Inspection :* LIGHT POLE IN COMPLIANCE WITH APPROVED PLANS AND SPEC. DETAIL ON SHEET E4 |
12/22/2006 | SHEET ROCK NAILING | AALEGRIA | Approved | IVRS - Inspection :* |
12/22/2006 | EXT METAL CLIPS/EXT SHEATHING | AALEGRIA | Approved | IVRS - Inspection :* |
12/28/2006 | PLUMBING - SEWER HCS CONNECT | RRICH | Approved | IVRS - Inspection :* |
01/29/2007 | MECHANICAL - HOODS | JMILITEL | Approved | IVRS - Inspection :* PLANS MAY HAVE BEEN APPROVED IN ERROR MIN. R5 INSULATION IS REQUIRED ON DUCT INSIDE THE BLDG. R4.2 WAS INSTALLED FIRE WRAP IS OK ON GREASE DUCT |
02/05/2007 | PLUMBING - PRE SLAB | RLEDONNE | Approved | IVRS - Inspection :* |
02/16/2007 | MECHANICAL - ABOVE CEILING | JMILITEL | Approved | IVRS - Inspection :* ON FINAL I.D FAN COILS, MARK DATA PLATES, LEAVE OUT TILE UNDER UNITS DO NOT RUN WIRES THROUGH A SERVICE PANEL OK FOR CEILING TILES |
02/16/2007 | BUILDING ABOVE CEILING | AALEGRIA | Approved | IVRS - Inspection :* |
02/16/2007 | PLUMBING - ABOVE CEILING | RLEDONNE | Approved | IVRS - Inspection :* |
03/09/2007 | TEP CLEARANCE - PM | JWEATHER | Approved | TEC CLEARANCE SENT PER B. GRANT |
03/22/2007 | LANDSCAPE - FINAL | ACONNOR | Approved | |
03/22/2007 | NPPO - FINAL | ACONNOR | Approved | |
03/22/2007 | SIGN - FINAL | JYBARRA | Approved | IVRS - Inspection :* |
03/22/2007 | ELECTRIC - OUTDOOR LIGHTING | DSANTACR | Approved | IVRS - Inspection :* |
03/22/2007 | ELECTRIC - CABLE DROP | DSANTACR | Approved | IVRS - Inspection :* |
03/22/2007 | ELECTRIC - ABOVE CEILING | DSANTACR | Approved | IVRS - Inspection :* |
03/22/2007 | OUTDOOR LIGHTING FINAL | DSANTACR | Approved | IVRS - Inspection :* |
03/22/2007 | ELECTRIC - FINAL | DSANTACR | Approved | IVRS - Inspection :* |
03/23/2007 | RIGHT OF WAY - FINAL | LLOPEZ | Approved | PER EMAIL |
03/23/2007 | BUILDING - FINAL | AALEGRIA | Approved | IVRS - Inspection :* |
03/23/2007 | ELECTRIC - TEMP POWER FOR TEST | DSANTACR | Approved | |
03/26/2007 | ROOF NAILING | AALEGRIA | Approved | |
03/26/2007 | U VALUE FOR WINDOW | AALEGRIA | Approved | |
04/13/2007 | ENGINEERING - FINAL | MAVERY | Approved | Contractor completed punch list. |
04/25/2007 | MECHANICAL - FINAL | JMILITEL | Approved | IVRS - Inspection :* CORRECTIONS HAVE BEEN MADE AIR BALANCE OK |
04/26/2007 | FIRE SPKLR - UG PIPING FLUSH | LLAKEY | Approved | |
04/26/2007 | FIRE SPKLR - UG, PIPING, HYDRO | LLAKEY | Approved | |
04/26/2007 | FIRE - KITCHEN EXH HOOD FINAL | LLAKEY | Approved | |
04/26/2007 | FIRE - FINAL | LLAKEY | Approved | |
04/26/2007 | PLUMBING - FINAL | RLEDONNE | Approved | IVRS - Inspection :* |
04/30/2007 | PERMIT FINALED | BFLORES | Approved |