Permit: T05BU02499
Permit Details
Apply Date:
10/12/2005
Applicant:
JON MORTO POSTER FROST ASSCT
Description:
CUT 3580CY & FILL 2610CY
Contractors:
- T A-WALLICK LLC C*
Permit Reviews
Permit Number - T05BU02499
Permit Status: Final
Permit Description: CUT 3580CY & FILL 2610CY
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
01/17/2006 | RESUBMITTAL - GRADING ALL | 03/08/2006 | COMPLETED |
03/08/2006 | RESUBMITTAL - GRADING | 01/30/2008 | COMPLETED |
10/12/2005 | PLANS OK TO SUBMIT - GRADING | 10/12/2005 | COMPLETED |
10/12/2005 | GRADING | 12/23/2005 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T05BU02499
Permit Status: Final
Permit Description: CUT 3580CY & FILL 2610CY
Total Outstanding Activity Conditions - 1
Date | Name |
---|---|
10/12/2005 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: Final
Permit Number: T05BU02499
Permit Description: CUT 3580CY & FILL 2610CY
Total Completed Inspections - 6
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
09/14/2007 | NPPO PRE PERMIT INSPECTION | ACONNOR | Approved | |
09/14/2007 | ENGINEERING PRE-CONSTRUCTION | MAVERY | Approved | Completed pre-con with site super Chris Cobos. |
09/27/2007 | STORMWATER INSTALL OF CONTROLS | MAVERY | Approved | Contractor needs to install SWPPP controls per and approved detail. Spoke to Chris site super in regards to. |
12/10/2007 | GRADING - FINAL | MAVERY | Approved | Contractor installed bleeder pipe on south side between basins. Contractor needs to provide eleavations for inlet and discharge. |
12/18/2007 | STORMWATER FOLLOW-UP INSP | MAVERY | Approved | Contractor needs to: 1- Clean 34th. and 35th. streets. 2- Repair wattle around site. 3- Limit construction access. Install construction entrance as needed per approved SWPPP. 4- Limit vehicle access in basins. Spoke to site super in regards to. |
07/09/2008 | LANDSCAPE INSPECTION | ACONNOR | Approved |