Permit Details

Status:
Closed
Type:
COMMERCIAL OTHER
Apply Date:
07/28/2005
Applicant:
EDUARDO GONZALEZ
Description:
CUT 100CY FILL 100CY UNIVERSITY OF PHOENIX
Contractors:
  • TRIUMPH BUILDERS SOUTHWEST LLC *C*

Permit Reviews

Permit Number - T05BU01913
Permit Status: Closed
Permit Description: CUT 100CY FILL 100CY UNIVERSITY OF PHOENIX
Start Date Submittal Complete Date Status  
06/29/2006 REVISION - GRADING 06/29/2006 COMPLETED Review Details
07/28/2005 PLANS OK TO SUBMIT - GRADING 07/28/2005 COMPLETED Review Details
07/28/2005 GRADING 08/31/2005 COMPLETED Review Details
08/31/2005 RESUBMITTAL - GRADING 09/06/2005 COMPLETED Review Details

Outstanding Activity Conditions

Permit Number - T05BU01913
Permit Status: Closed
Permit Description: CUT 100CY FILL 100CY UNIVERSITY OF PHOENIX
Total Outstanding Activity Conditions - 1
Date Name
07/28/2005 PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION.

Outstanding Inspections

Permit Status: Closed
Permit Number: T05BU01913
Permite Description: CUT 100CY FILL 100CY UNIVERSITY OF PHOENIX
Total Outstanding Inspections - 3
Last Inspection Date Description Inspector Results Comments
STORMWATER FINAL INSPECTION N/A Not Inspected
06/28/2006 GRADING - INTERMEDIATE N/A Correction Required MET WITH GARY ON SITE
PROVIDED COPIES OF AP/PA INSPECTIONS FOR T05CM03547 AND T05CM03578
09/14/2005 STORMWATER INSTALL OF CONTROLS N/A Correction Required MET WITH THE DEVELOPER ON-SITE AND LOOKED AT THE CONTROLS THAT HE HAS INSTALLED AT THIS TIME. THERE ARE A FEW LOCATIONS THAT ARE MISSING SOME CONTROLS, THESE WILL BE INSTALLED LATER ON THIS AFTERNOON. MODIFICATIONS HAVE BEEN MADE TO THIS SITE IN REGARDS TO THE ACCESS POINTS FOR CONSTRUCTION VEHICLES, AND DELETION OF SOME OF THE REQUIRED SILT FENCE. I HAVE ADVISED THE DEVELOPER THAT THESE ITEMS NEEDED TO BE NOTED ON HIS SITE SWPPP PLANS AND THEY NEED TO BE DATED AND SIGNED BY THE SIGNING AUTHORITY. I WILL RECHECK THE SITE NEXT WEEK TO VERIFY THAT EVERYTHING IS COMPLETE.

Completed Inspections

Permit Status: Closed
Permit Number: T05BU01913
Permit Description: CUT 100CY FILL 100CY UNIVERSITY OF PHOENIX
Total Completed Inspections - 3
Date Description Inspector Results Comments
06/01/2006 STORMWATER FOLLOW-UP INSP NKALAHAR Approved CONSTRUCTION FENCING IS DOWN
SITE NEEDS TO BE SWEPT
MAINTENANCE STILL NEEDS TO BE DONE ON SEDIMENT CONTROLS
07/12/2006 LANDSCAPE INSPECTION ACONNOR Approved
07/28/2006 GRADING - FINAL NKALAHAR Approved ALL PUNCHLIST ITEMS HAVE BEEN ADDRESSED

Documents

File Name Document Type  
None DOCUMENTS VIEW
EROSIONCONTROLPLAN.TIF GRADING PLANS VIEW