Permit: T04CM02898
Permit Details
Apply Date:
06/23/2004
Applicant:
N/A
Description:
NEW:WAREHOUSE
Architects:
- LEE, LYO TERRELL
Contractors:
- D R I PARTNERS INC
Permit Reviews
Permit Number - T04CM02898
Permit Status: C of o
Permit Description: NEW:WAREHOUSE
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
01/20/2005 | 3RD PARTY REVIEW-REVISION/OTHER | 01/24/2005 | COMPLETED |
06/23/2004 | PLANS OK TO SUBMIT - 3RD PARTY | 06/24/2004 | COMPLETED |
06/24/2004 | 3RD PARTY REVIEW-COMMERCIAL | 07/30/2004 | COMPLETED |
07/30/2004 | POST 3RD PARTY REVIEW | 08/31/2004 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T04CM02898
Permit Status: C of o
Permit Description: NEW:WAREHOUSE
Total Outstanding Activity Conditions - 1
Date | Name |
---|---|
06/23/2004 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T04CM02898
Permit Description: NEW:WAREHOUSE
Total Completed Inspections - 39
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
09/07/2004 | PLUMBING - ROUGH, SOIL | RRICH | Approved | IVRS - Inspection :*/1)WATER TEST FROM 5' OUT SIDE BUILDING THRU 2-WAY CLEANOUT 2)LOCATIONS INTO RESTROOMS UNDERGROUND ONLY OK |
10/04/2004 | STEM WALL/RETAINING WALL | LHANLY | Approved | IVRS - Inspection :*/ 1) JAMB BARS AS "BUNDLED" OK PER E.O.R. 9/30/04 |
10/13/2004 | ELECTRIC - UFER | JORTA | Approved | IVRS - Inspection :* |
10/19/2004 | EXCAVATION/LAYOUT REBAR & ZON | LHANLY | Approved | IVRS - Inspection :*/ 1) COLUMNS OK |
11/15/2004 | PLUMBING - GAS PRESSURE TEST | RRICH | Approved | IVRS - Inspection :*/15 PSI AIR TEST ON 1 1/4" SCOTCH COAT STUBBED UP IN BUILDING AND OUT OF BUILDING UP APP. 7' FROM BUILDING IN 3" SLEEVE (ABS). THIS IS UNDER BUILDING SLAB AND STRUCTURE AND REQUIRES REVISED CITY APPROVED PLAN WITH CORRECT VENT TERMINATION. COVER AT OWN RISK |
11/15/2004 | PLUMBING - YARD WTR LINE/TEST | RRICH | Approved | IVRS - Inspection :*/80 PSI AIR TEST ON 1 1/2 H2O STUB UP BUILDING AND 5' OUT OK. |
11/17/2004 | ELECTRIC - UNDERGROUND | RMAJUTA | Approved | PARTIAL OK TO COVER 3-2" PVC FEEDERS SOUTH WALL. |
11/19/2004 | ROOF NAILING | LHANLY | Approved | IVRS - Inspection :*/ 1) OK EXCEPT FOR DETAIL CLARIFICATION 2) OK TO DRY IN 3) PLEASE CLARIFY PURLIM BRACE DETAIL 1/S-6 ARE THEY REQUIRED OR IS IT UP TO ROOF SYSTEM ENGINEER |
11/26/2004 | BUILDING PRE-SLAB | LHANLY | Approved | IVRS - Inspection :CLOSURE POUR OK |
12/07/2004 | FIRE SPKLR - UG PIPING FLUSH | LTHOMAS | Approved | |
12/07/2004 | FIRE SPKLR - UG, PIPING, HYDRO | LTHOMAS | Approved | |
12/23/2004 | ELECTRIC - INTERMEDIATE | RSUBA | Approved | IVRS - Inspection :* 1) WALLS |
12/28/2004 | FRAMING | LHANLY | Approved | IVRS - Inspection :* |
12/30/2004 | PLUMBING - INTERMEDIATE | RRICH | Approved | IVRS - Inspection :*APPROVED. |
01/10/2005 | SHEET ROCK NAILING | LHANLY | Approved | IVRS - Inspection :* |
01/13/2005 | STUCCO MESH | LHANLY | Approved | IVRS - Inspection :* APPROVED |
01/13/2005 | U VALUE FOR WINDOW | LHANLY | Approved | IVRS - Inspection :* |
01/26/2005 | PLUMBING - SEWER HCS CONNECT | RRICH | Approved | IVRS - Inspection :* WEST 4" BUILDING DRAIN THRU 2 WAY CLEANOUT TO 4" BULDING SEWER TO HCS CONNECTION PER REVISED CITY APPROVED PLAN 6 PSI AIR TEST OK |
02/01/2005 | PLUMBING - ABOVE CEILING | RRICH | Approved | IVRS - Inspection :* APPROVED |
02/01/2005 | ELECTRIC - ABOVE CEILING | RSUBA | Approved | IVRS - Inspection :* APPROVED |
02/03/2005 | MECHANICAL - ABOVE CEILING | JMILITEL | Approved | IVRS - Inspection :* OK FOR CEILING TILES |
03/01/2005 | ELECTRIC - CABLE DROP | RSUBA | Approved | IVRS - Inspection :* 1) OK TO CLEAR |
03/02/2005 | ELECTRIC - TEMP POWER FOR TEST | RSUBA | Approved | IVRS - Inspection :* OK TO CLEAR M1 & M2 |
03/03/2005 | FIRE SPKLR - OH PIPING & HYDRO | LTHOMAS | Approved | |
03/03/2005 | TEP CLEARANCE - AM | RMAJUTA | Approved | OK TEST POWER FOR M1,M2 PER SUBA |
03/04/2005 | PLUMBING - GAS PRESS TEST FNL | RRICH | Approved | IVRS - Inspection :* APPROVED |
03/07/2005 | PLUMBING - FINAL | RRICH | Approved | IVRS - Inspection :* CORRECTIONS MADE. ( 2) BACKFLOW CERTIFICATIONS TURNED IN ( 1) INTERIOR (1) EXTERIOR |
03/10/2005 | OUTDOOR LIGHTING FINAL | RSUBA | Approved | |
03/10/2005 | ELECTRIC - FINAL | RSUBA | Approved | IVRS - Inspection :* APPROVED |
03/11/2005 | MECHANICAL - FINAL | JMILITEL | Approved | IVRS - Inspection :* ALL CORRECTONS HAVE BEEN MADE . OK FOR FINAL C OF O |
03/11/2005 | MECHANICAL - INTERMEDIATE | JMILITEL | Approved | |
03/11/2005 | FIRE - FINAL | CSCHULTZ | Approved | |
03/11/2005 | FIRE SPKLR - FINAL | CSCHULTZ | Approved | |
03/11/2005 | SIGN - FINAL | RDEAR | Approved | IVRS - Inspection :* |
03/11/2005 | RIGHT OF WAY - FINAL | DLEE | Approved | |
03/23/2005 | BUILDING - FINAL | LHANLY | Approved | IVRS - Inspection :* OK FOR C OF O |
03/23/2005 | BUILDING ABOVE CEILING | LHANLY | Approved | IVRS - Inspection :* |
03/29/2005 | ENGINEERING - FINAL | JSALINE | Approved | C OF O Approved |
03/30/2005 | PERMIT FINALED | TACHONG | Approved |