Permit Details

Status:
C of o
Type:
COMMERCIAL NEW
Address NEW:
334 W LOS REALES RD
Apply Date:
04/27/2004
Applicant:
N/A
Description:
NEW CHURCH
Contractors:
  • SILVER WEST INC ,

Permit Reviews

Permit Number - T04CM01885
Permit Status: C of o
Permit Description: NEW CHURCH
Start Date Submittal Complete Date Status  
01/13/2005 RESUBMITTAL 02/04/2005 COMPLETED Review Details
04/27/2004 PLANS OK TO SUBMIT - 3RD PARTY 05/04/2004 COMPLETED Review Details
05/04/2004 3RD PARTY REVIEW-COMMERCIAL 10/13/2004 COMPLETED Review Details
10/13/2004 COMMERCIAL NEW 11/29/2004 COMPLETED Review Details
12/03/2004 RESUBMITTAL 12/27/2004 COMPLETED Review Details
12/29/2004 RESUBMITTAL 01/12/2005 COMPLETED Review Details

Outstanding Activity Conditions

Permit Number - T04CM01885
Permit Status: C of o
Permit Description: NEW CHURCH
Total Outstanding Activity Conditions - 1
Date Name
04/27/2004 PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION.

Completed Inspections

Permit Status: C of o
Permit Number: T04CM01885
Permit Description: NEW CHURCH
Total Completed Inspections - 45
Date Description Inspector Results Comments
02/24/2005 PLUMBING - ROUGH, SOIL TRINIVJR Approved IVRS - Inspection :* 1) AIR PRESSURE TEST IS OK. 2) THIS INSPECTION IS FOR UNDERGROUND WASTE AND IS OK UP TO WATER CLOSETS IN MAIN RESTROOM @ EAST END OF BUILDING. 3) OK TO BACKFILL TRENCH.
02/24/2005 PLUMBING - ROUGH, SOIL TRINIVJR Approved IVRS - Inspection :* 1) AIR PRESSURE TEST IS OK. 2) ALL CORRECTIONS HAVE BEEN MADE. 3) OK TO BACKFILL TRENCH.
03/04/2005 PLUMBING - SEWER HCS CONNECT TRINIVJR Approved IVRS - Inspection :*
03/07/2005 ELECTRIC - UFER DSANTACR Approved IVRS - Inspection :*
03/29/2005 BUILDING PRE-SLAB AMATHIES Approved IVRS - Inspection :*
03/29/2005 EXCAVATION/LAYOUT REBAR & ZON AMATHIES Approved IVRS - Inspection :*
07/18/2005 ELECTRIC - UNDERGROUND DSANTACR Approved IVRS - Inspection :*
1) OK SECONDARY CONDUITS FROM X-FORMER TO SES AT BLDG
09/02/2005 PLUMBING - YARD WTR LINE/TEST TRINIVJR Approved IVRS - Inspection :*
09/16/2005 ELECTRIC - INTERMEDIATE RMAJUTA Approved IVRS - Inspection :*
ASSEMBLY AREA OK TO COVER WALLS
09/30/2005 SHEET ROCK NAILING AMATHIES Approved IVRS - Inspection :*
09/30/2005 ROOF NAILING AMATHIES Approved IVRS - Inspection :*
09/30/2005 EXT METAL CLIPS/EXT SHEATHING AMATHIES Approved IVRS - Inspection :*
12/09/2005 MECHANICAL - ABOVE CEILING JMILITEL Approved IVRS - Inspection :*
1) OK FOR CEILING TILES ALL AREAS EAST OF SANCTUARY
2) PLANS REQUIRE COPPER ON ALL CONDENSATE PIPING
3) FAN COILS WILL NEED SECONDARY DRAINS
12/09/2005 MECHANICAL - INTERMEDIATE JMILITEL Approved IVRS - Inspection :*
12/09/2005 PLUMBING - INTERMEDIATE BBENEDON Approved IVRS - Inspection :*
PROVIDE HANGERS AT CHANGE OF DIRECTION
12/09/2005 BUILDING ABOVE CEILING AMATHIES Approved IVRS - Inspection :*
12/09/2005 PLUMBING - BACK WATER VALVE BBENEDON Approved IVRS - Inspection :*
12/14/2005 PLUMBING - ABOVE CEILING BBENEDON Approved IVRS - Inspection :*
1) GAS LINE
2) 14.6 PSI
3) GAS LINE PIPING WITHIN BLDG OK TO COVER
4) PRESSURE TEST APPEARS TO BE HOLDING
5) RAISE DRIP LEGS ABOVE ROOF
6) RE-PRESSURE TEST
7) SUPPORT PIPING
8) SEAL PENETRATION
9) CHECK BTU RATING ON FLEX CONNECTORS TO ROOF TOP FURNACES
12/14/2005 ELECTRIC - ABOVE CEILING DSANTACR Approved IVRS - Inspection :*
OK EAST OF SANCTUARY
12/14/2005 SITE - SEWER BBENEDON Approved IVRS - Inspection :*
12/14/2005 FRAMING AMATHIES Approved IVRS - Inspection :*
12/22/2005 U VALUE FOR WINDOW AMATHIES Approved IVRS - Inspection :*
03/01/2006 PLUMBING - GAS PRESSURE TEST BBENEDON Approved IVRS - Inspection :*
14.7 PSI 1055
BOND REQUIRED FOR UTILITY CLEARANCE
CLOSET FLANGES OK
03/01/2006 STUCCO MESH LHANLY Approved IVRS - Inspection :*
03/14/2006 ELECTRIC - TEMP POWER FOR TEST DSANTACR Approved IVRS - Inspection :*
03/14/2006 ELECTRIC - CABLE DROP DSANTACR Approved IVRS - Inspection :*
03/15/2006 TEP CLEARANCE - AM JWEATHER Approved TEC CLEARED PER D. SANTACRUZ
03/24/2006 ELECTRIC - OUTDOOR LIGHTING DSANTACR Approved IVRS - Inspection :*
03/24/2006 PLUMBING - FINAL BBENEDON Approved IVRS - Inspection :*
03/24/2006 FIRE SPKLR - OH PIPING & HYDRO LTHOMAS Approved
03/24/2006 FIRE SPKLR - UG PIPING FLUSH LTHOMAS Approved
03/24/2006 FIRE SPKLR - UG, PIPING, HYDRO LTHOMAS Approved
03/27/2006 SIGN - FINAL RDEAR Approved
03/27/2006 ELECTRIC - FINAL DSANTACR Approved IVRS - Inspection :*
03/27/2006 FIRE SPKLR - FINAL LTHOMAS Approved
03/27/2006 FIRE - FINAL LTHOMAS Approved
03/28/2006 MECHANICAL - PROGRESS CWILLIAM Approved IVRS - Inspection :*
03/29/2006 RIGHT OF WAY - FINAL LLOPEZ Approved PER EMAIL
03/30/2006 MECHANICAL - FINAL CWILLIAM Approved IVRS - Inspection :*
03/30/2006 NPPO - FINAL ACONNOR Approved
03/30/2006 LANDSCAPE - FINAL ACONNOR Approved
04/06/2006 BUILDING - FINAL LHANLY Approved IVRS - Inspection :*
06/20/2006 ENGINEERING - FINAL MAVERY Approved Contractor completed punch list.
06/21/2006 STEM WALL/RETAINING WALL LHANLY Approved
06/21/2006 PERMIT FINALED DROBEY Approved