Permit Details

Status:
Final
Type:
COMMERCIAL NEW
Address NEW:
3675 E BRITANNIA DR
Apply Date:
04/21/2004
Applicant:
N/A
Description:
WAREHOUSE:NEW SHELL 225'4" x 361'4" CONCRETE TILT-UP BUILDING W/ INTERIOR STEEL STRUCTURE, STEEL ROOF JOISTS AND STEEL ROOF DECKING, ONE-HOUR FIRE-RATED WALL SEPARATING SES ROOM AND WAREHOUSE REVISION FOR SHOP DRAWINGS : SHOP DRAWINGS APPROVED FOR:1. TILT-UP WALLS,2. STRUCTURAL STEEL,3. METAL ROOF DECKING,4. METAL ROOF JOISTS ,5. STEEL LADDER ,6. ROOF LATCH. REVISION FOR LOADING DOCK AND CANOPY : (10/26/04) PROVIDE SHOP DRAWINGS FOR CANOPY STEEL , METAL DECKING , HANDRAILS AND GUARDRAILS SHOP DRAWINGS SUBMITTED FOR LOADING DOCK GUARDRAIL, DOCK HANDRAIL, GUARDRAIL, CANOPY FRAMING, COLUMNS, CANOPY BEAMS, (12/9/04) (12/30/04) LOADING DOCK SHOP DRAWINGS FOR : 1. CANOPY METAL DECKING, 2. CANOPY STEEL FRAMING, 3.GUARDS ,4. HANDRAILS.
Contractors:
  • OPUS SOUTHWEST CONSTRUCTION CORP

Permit Reviews

Permit Number - T04CM01811
Permit Status: Final
Permit Description: WAREHOUSE:NEW SHELL 225'4" x 361'4" CONCRETE TILT-UP BUILDING W/ INTERIOR STEEL STRUCTURE, STEEL ROOF JOISTS AND STEEL ROOF DECKING, ONE-HOUR FIRE-RATED WALL SEPARATING SES ROOM AND WAREHOUSE REVISION FOR SHOP DRAWINGS : SHOP DRAWINGS APPROVED FOR:1. TILT-UP WALLS,2. STRUCTURAL STEEL,3. METAL ROOF DECKING,4. METAL ROOF JOISTS ,5. STEEL LADDER ,6. ROOF LATCH. REVISION FOR LOADING DOCK AND CANOPY : (10/26/04) PROVIDE SHOP DRAWINGS FOR CANOPY STEEL , METAL DECKING , HANDRAILS AND GUARDRAILS SHOP DRAWINGS SUBMITTED FOR LOADING DOCK GUARDRAIL, DOCK HANDRAIL, GUARDRAIL, CANOPY FRAMING, COLUMNS, CANOPY BEAMS, (12/9/04) (12/30/04) LOADING DOCK SHOP DRAWINGS FOR : 1. CANOPY METAL DECKING, 2. CANOPY STEEL FRAMING, 3.GUARDS ,4. HANDRAILS.
Start Date Submittal Complete Date Status  
04/21/2004 PLANS OK TO SUBMIT - COMM 04/23/2004 COMPLETED Review Details
04/21/2004 PLANS OK TO SUBMIT - SITE 04/21/2004 COMPLETED Review Details
04/21/2004 SITE 05/26/2004 COMPLETED Review Details
04/23/2004 COMMERCIAL NEW 05/26/2004 COMPLETED Review Details
06/15/2004 RESUBMITTAL 06/24/2004 COMPLETED Review Details
06/15/2004 RESUBMITTAL - SITE ALL 07/09/2004 COMPLETED Review Details
06/24/2004 RESUBMITTAL 07/09/2004 COMPLETED Review Details
07/15/2004 RESUBMITTAL 07/23/2004 COMPLETED Review Details
08/13/2004 REVISION 09/10/2004 COMPLETED Review Details
09/10/2004 REVISION - 2ND 10/15/2004 COMPLETED Review Details
10/22/2004 RESUBMITTAL 11/03/2004 COMPLETED Review Details
11/10/2004 RESUBMITTAL - SITE 12/30/2004 COMPLETED Review Details
11/10/2004 RESUBMITTAL 12/30/2004 COMPLETED Review Details
12/09/2004 REVISION 12/13/2004 COMPLETED Review Details
12/30/2004 REVISION 01/04/2005 COMPLETED Review Details

Outstanding Activity Conditions

Permit Number - T04CM01811
Permit Status: Final
Permit Description: WAREHOUSE:NEW SHELL 225'4" x 361'4" CONCRETE TILT-UP BUILDING W/ INTERIOR STEEL STRUCTURE, STEEL ROOF JOISTS AND STEEL ROOF DECKING, ONE-HOUR FIRE-RATED WALL SEPARATING SES ROOM AND WAREHOUSE REVISION FOR SHOP DRAWINGS : SHOP DRAWINGS APPROVED FOR:1. TILT-UP WALLS,2. STRUCTURAL STEEL,3. METAL ROOF DECKING,4. METAL ROOF JOISTS ,5. STEEL LADDER ,6. ROOF LATCH. REVISION FOR LOADING DOCK AND CANOPY : (10/26/04) PROVIDE SHOP DRAWINGS FOR CANOPY STEEL , METAL DECKING , HANDRAILS AND GUARDRAILS SHOP DRAWINGS SUBMITTED FOR LOADING DOCK GUARDRAIL, DOCK HANDRAIL, GUARDRAIL, CANOPY FRAMING, COLUMNS, CANOPY BEAMS, (12/9/04) (12/30/04) LOADING DOCK SHOP DRAWINGS FOR : 1. CANOPY METAL DECKING, 2. CANOPY STEEL FRAMING, 3.GUARDS ,4. HANDRAILS.
Total Outstanding Activity Conditions - 1
Date Name
04/21/2004 PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION.

Completed Inspections

Permit Status: Final
Permit Number: T04CM01811
Permit Description: WAREHOUSE:NEW SHELL 225'4" x 361'4" CONCRETE TILT-UP BUILDING W/ INTERIOR STEEL STRUCTURE, STEEL ROOF JOISTS AND STEEL ROOF DECKING, ONE-HOUR FIRE-RATED WALL SEPARATING SES ROOM AND WAREHOUSE REVISION FOR SHOP DRAWINGS : SHOP DRAWINGS APPROVED FOR:1. TILT-UP WALLS,2. STRUCTURAL STEEL,3. METAL ROOF DECKING,4. METAL ROOF JOISTS ,5. STEEL LADDER ,6. ROOF LATCH. REVISION FOR LOADING DOCK AND CANOPY : (10/26/04) PROVIDE SHOP DRAWINGS FOR CANOPY STEEL , METAL DECKING , HANDRAILS AND GUARDRAILS SHOP DRAWINGS SUBMITTED FOR LOADING DOCK GUARDRAIL, DOCK HANDRAIL, GUARDRAIL, CANOPY FRAMING, COLUMNS, CANOPY BEAMS, (12/9/04) (12/30/04) LOADING DOCK SHOP DRAWINGS FOR : 1. CANOPY METAL DECKING, 2. CANOPY STEEL FRAMING, 3.GUARDS ,4. HANDRAILS.
Total Completed Inspections - 29
Date Description Inspector Results Comments
07/29/2004 ELECTRIC - UFER DSANTACR Approved IVRS - Inspection :*
08/18/2004 PLUMBING - ROUGH, SOIL TRINIVJR Approved IVRS - Inspection :*/APPROVED
1)SOIL WATER TEST IS OK
2)OK TO BACKFILL TRENCH
08/24/2004 FIRE SPKLR - UG, PIPING, HYDRO LTHOMAS Approved
08/30/2004 ELECTRIC - TEMPORARY POLE RMAJUTA Approved APPROVED OK TO CLEAR
08/31/2004 TEP CLEARANCE - AM JKOZUCH Approved TEMP POWER POLE FOR CONSTRUCTION ONLY
09/20/2004 BUILDING PRE-SLAB AMATHIES Approved IVRS - Inspection :*
10/18/2004 ROOF NAILING AMATHIES Approved IVRS - Inspection :*
10/20/2004 STEM WALL/RETAINING WALL AMATHIES Approved IVRS - Inspection :*
10/22/2004 FRAMING AMATHIES Approved IVRS - Inspection :*
11/16/2004 PLUMBING - FINAL TRINIVJR Approved IVRS - Inspection :*/1)PIT FOR BACK WATER VALVE IS OK 2)YARD WATER LINE OK BACKFLOW PREVENTER OK
11/16/2004 PLUMBING - PROGRESS TRINIVJR Approved IVRS - Inspection :*
11/16/2004 PLUMBING - SEWER HCS CONNECT TRINIVJR Approved IVRS - Inspection :*
11/16/2004 PLUMBING - YARD WTR LINE/TEST TRINIVJR Approved IVRS - Inspection :*
11/24/2004 SHEET ROCK NAILING AMATHIES Approved IVRS - Inspection :*
11/24/2004 EXT METAL CLIPS/EXT SHEATHING AMATHIES Approved IVRS - Inspection :*
11/24/2004 EXCAVATION/LAYOUT REBAR & ZON AMATHIES Approved IVRS - Inspection :*
12/01/2004 FIRE SPKLR - OH PIPING & HYDRO LTHOMAS Approved
12/07/2004 ELECTRIC - TEMP POWER FOR TEST DSANTACR Approved
12/21/2004 BUILDING - FINAL AMATHIES Approved IVRS - Inspection :*
1) OK TEMP C OF O
12/22/2004 ELECTRIC - FINAL DSANTACR Approved IVRS - Inspection :*
12/22/2004 ELECTRIC - INTERMEDIATE DSANTACR Approved IVRS - Inspection :*
12/22/2004 ELECTRIC - UNDERGROUND DSANTACR Approved IVRS - Inspection :*
12/23/2004 FIRE SPKLR - UG PIPING FLUSH LTHOMAS Approved
12/27/2004 FIRE SPKLR - FINAL LTHOMAS Approved Approval for shell building only.
12/30/2004 FIRE - FINAL LTHOMAS Approved OKAY TEMP C OF O
01/07/2005 STUCCO MESH AMATHIES Approved IVRS - Inspection :*
01/10/2005 NPPO - FINAL ACONNOR Approved
01/10/2005 LANDSCAPE - FINAL ACONNOR Approved
01/27/2005 PERMIT FINALED TACHONG Approved

Documents

File Name Document Type  
None DOCUMENTS VIEW