Permit Details

Status:
C of o
Type:
COMMERCIAL NEW
Address:
4380 N ORACLE RD
Apply Date:
01/27/2004
Applicant:
N/A
Description:
NEW RETAIL BUILDING
Architects:
  • SCOTT, DALE HARVEY
Contractors:
  • TRIUMPH BUILDERS SOUTHWEST LLC *C*

Permit Reviews

Permit Number - T04CM00341
Permit Status: C of o
Permit Description: NEW RETAIL BUILDING
Start Date Submittal Complete Date Status  
01/27/2004 PLANS OK TO SUBMIT - 3RD PARTY 01/28/2004 COMPLETED Review Details
01/28/2004 3RD PARTY REVIEW-COMMERCIAL 09/16/2004 COMPLETED Review Details
03/04/2005 3RD PARTY REVIEW-COMMERCIAL 03/04/2005 COMPLETED Review Details
03/04/2005 POST 3RD PARTY REVIEW 03/11/2005 COMPLETED Review Details
03/11/2005 RESUBMITTAL 04/11/2005 COMPLETED Review Details
05/03/2005 3RD PARTY REVIEW-REVISION/OTHER 05/06/2005 COMPLETED Review Details
06/27/2005 REVISION 09/23/2005 COMPLETED Review Details
08/02/2005 REVISION - 2ND 08/04/2005 COMPLETED Review Details
08/04/2005 REVISION - 2ND 09/26/2005 COMPLETED Review Details
09/01/2004 SITE 03/07/2005 COMPLETED Review Details
09/16/2004 POST 3RD PARTY REVIEW 03/04/2005 COMPLETED Review Details
09/23/2005 3RD PARTY REVIEW-REVISION/OTHER 09/26/2005 COMPLETED Review Details
09/26/2005 POST 3RD PARTY REVIEW 10/07/2005 COMPLETED Review Details

Outstanding Activity Conditions

Permit Number - T04CM00341
Permit Status: C of o
Permit Description: NEW RETAIL BUILDING
Total Outstanding Activity Conditions - 1
Date Name
01/27/2004 PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION.

Completed Inspections

Permit Status: C of o
Permit Number: T04CM00341
Permit Description: NEW RETAIL BUILDING
Total Completed Inspections - 41
Date Description Inspector Results Comments
04/27/2005 PLUMBING - ROUGH, SOIL RMYERS Approved IVRS - Inspection :* 1) CORRECTION MADE OK OK FOR CONCRETE
06/22/2005 ROOF NAILING AMATHIES Approved IVRS - Inspection :*
07/19/2005 ELECTRIC - PROGRESS RSUBA Approved IVRS - Inspection :*
1) 2035-PARTIAL (BATHROOMS)
2) 2036-PARTIAL (MAIN FLOOR) BATHROOMS
07/20/2005 BUILDING - PROGRESS AQUIROZ Approved IVRS - Inspection :*
07/21/2005 PLUMBING - INTERMEDIATE RRICH Approved IVRS - Inspection :*
1) WASTE AND VENT PIPING RESTROOM 114, 115, AND JANITOR ROOM 113 WATER TEST THRU ROOF OK
2) H20 PIPING FROM 2' OUTSIDE BLDG EXTERIOR THRU BLDG 55 + PSI AIR TEST OK
08/18/2005 ELECTRIC - TEMP POWER FOR TEST RSUBA Approved IVRS - Inspection :*
1) OK TO CLEAR
08/19/2005 TEP CLEARANCE - AM RMAJUTA Approved OK TEMP POWER ON BOND PER SUBA
09/02/2005 PLUMBING - SEWER HCS CONNECT RMYERS Approved IVRS - Inspection :*
1) CONNECTION BETWEEN SITE SEWER AND BLDG DRAIN OK
2) OK TO COVER
09/08/2005 ELECTRIC - UFER DSANTACR Approved IVRS - Inspection :*
09/08/2005 ELECTRIC - INTERMEDIATE DSANTACR Approved IVRS - Inspection :*
09/08/2005 ELECTRIC - ABOVE CEILING DSANTACR Approved IVRS - Inspection :*
09/16/2005 FIRE - FINAL LTHOMAS Approved
09/16/2005 FIRE SPKLR - FINAL LTHOMAS Approved
10/02/2005 MECHANICAL - FINAL CWILLIAM Approved IVRS - Inspection :*
10/04/2005 RIGHT OF WAY - FINAL MOTERO Approved PER EMAIL
10/04/2005 SHEET ROCK NAILING AQUIROZ Approved IVRS - Inspection :*
10/04/2005 U VALUE FOR WINDOW AQUIROZ Approved IVRS - Inspection :*
10/04/2005 BUILDING ABOVE CEILING AQUIROZ Approved IVRS - Inspection :*
10/04/2005 FRAMING AQUIROZ Approved IVRS - Inspection :*
10/04/2005 BUILDING PRE-SLAB AQUIROZ Approved IVRS - Inspection :*
10/04/2005 STEM WALL/RETAINING WALL AQUIROZ Approved IVRS - Inspection :*
10/04/2005 EXCAVATION/LAYOUT REBAR & ZON AQUIROZ Approved IVRS - Inspection :*
10/12/2005 OUTDOOR LIGHTING FINAL RSUBA Approved IVRS - Inspection :*
10/12/2005 ELECTRIC - FINAL RSUBA Approved IVRS - Inspection :*
10/18/2005 SIGN - FINAL JYBARRA Approved IVRS - Inspection :*
10/19/2005 PLUMBING - YARD WTR LINE/TEST RMYERS Approved IVRS - Inspection :*
10/19/2005 SITE - SEWER RMYERS Approved IVRS - Inspection :*
10/19/2005 PLUMBING - GAS PRESS TEST FNL RMYERS Approved IVRS - Inspection :*
10/19/2005 PLUMBING - GAS PRESSURE TEST RMYERS Approved IVRS - Inspection :*
10/19/2005 PLUMBING - ROOF DRAINS RMYERS Approved IVRS - Inspection :*
10/19/2005 PLUMBING - ABOVE CEILING RMYERS Approved IVRS - Inspection :*
10/19/2006 PLUMBING - FINAL RMYERS Approved
12/01/2006 BUILDING - FINAL AQUIROZ Approved IVRS - Inspection :*
12/06/2006 ELECTRIC - UNDERGROUND RSUBA Approved
12/06/2006 ELECTRIC - CABLE DROP RSUBA Approved
12/06/2006 ELECTRIC - CONSTRUCTION POWER RSUBA Approved
12/06/2006 ELECTRIC - OUTDOOR LIGHTING RSUBA Approved
12/18/2006 MECHANICAL - ABOVE CEILING CWILLIAM Approved
12/18/2006 MECHANICAL - INTERMEDIATE CWILLIAM Approved
12/18/2006 ENGINEERING - FINAL JFEMLING Approved Fianl grading inspection approved
01/03/2007 PERMIT FINALED LJACKSON Approved

Documents

File Name Document Type  
None CERT OF OCC VIEW
STRUCCALCS.TIF DOCUMENTS VIEW
T04CM00341.PDF DOCUMENTS VIEW
None DOCUMENTS VIEW