Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you cannot find what you are looking for please submit a records request.

PRO is currently experiencing an outage. Some documents and records may not be available on PRO momentarily. We apologize for the inconvenience and are working to restore full access.

Permit Details

Status:
Final
Type:
COMMERCIAL OTHER
Address NEW:
7511 S HOUGHTON RD
Apply Date:
09/27/2004
Applicant:
E E C
Description:
GRADING:10846CY CUT & 1017CY FILL

Permit Reviews

Permit Number - T04BU02370
Permit Status: Final
Permit Description: GRADING:10846CY CUT & 1017CY FILL
Start Date Submittal Complete Date Status  
04/14/2005 RESUBMITTAL - GRADING ALL 05/16/2005 COMPLETED Review Details
06/15/2005 RESUBMITTAL - GRADING 07/19/2005 COMPLETED Review Details
07/26/2005 RESUBMITTAL - GRADING ALL 08/15/2005 COMPLETED Review Details
08/19/2005 RESUBMITTAL - GRADING 08/25/2005 COMPLETED Review Details
08/25/2005 RESUBMITTAL - GRADING 09/14/2005 COMPLETED Review Details
09/27/2004 PLANS OK TO SUBMIT - GRADING 09/27/2004 COMPLETED Review Details
09/27/2004 GRADING 10/19/2004 COMPLETED Review Details

Outstanding Activity Conditions

Permit Number - T04BU02370
Permit Status: Final
Permit Description: GRADING:10846CY CUT & 1017CY FILL
Total Outstanding Activity Conditions - 1
Date Name
09/27/2004 PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION.

Completed Inspections

Permit Status: Final
Permit Number: T04BU02370
Permit Description: GRADING:10846CY CUT & 1017CY FILL
Total Completed Inspections - 7
Date Description Inspector Results Comments
09/15/2005 NPPO PRE PERMIT INSPECTION ACONNOR Approved
11/10/2005 STORMWATER INSTALL OF CONTROLS NKALAHAR Approved - SITE GRUBBED AND GRADING HAS STARTED
- 2 S.C.E. IN PLACE (SHOULD BE LONGER)
- CONTROLS IN PLACE ALONG N AND W SIDE OF PROJECT
UNABLE TO ACERTAIN IF SWPPP IS POSTED WITHIN THE PROJECT. IT IS NOT APPARENT FROM OUTSIDE THE CONSTRUCTION FENCING. NO CREW ON SITE
10/19/2006 GRADING - INTERMEDIATE NKALAHAR Approved MET ONSITE WITH RON'S CONCRETE AND LOU BOCK ABOUT ON SITE RAMPS AND TRUNCATED DOMES
12/28/2006 STORMWATER FOLLOW-UP INSP NKALAHAR Approved CORRECTION NOTICE 7 DAYS

UNCONTAINED CONSTRUCTION DEBRIS
SITE MOSTLY STABLE
04/11/2007 GRADING - FINAL NKALAHAR Approved LOOKED AT ALL PREVIOUS PUNCHLIST ITEMS
ALL HAVE BEEN ADDRESSED
04/11/2007 ENGINEERING PRE-CONSTRUCTION NKALAHAR Approved
05/23/2007 LANDSCAPE INSPECTION ACONNOR Approved