Permit: T03CM05505
Permit Details
Apply Date:
11/21/2003
Applicant:
RAPP DAVID
Description:
SFR:NEW
Contractors:
- ANCHOR PLUMBING INC ,
- ESCO MASONRY ,
- HECTOR S CONCRETE ,
- RAPP ROOFING COMPANY ,
- WENTZ AND PATRICK CONSTRUCTION
Permit Reviews
Permit Number - T03CM05505
Permit Status: Final
Permit Description: SFR:NEW
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 02/02/2004 | RESUBMITTAL | 04/23/2004 | COMPLETED |
| 05/24/2004 | REVISION | 05/24/2004 | COMPLETED |
| 11/21/2003 | PLANS OK TO SUBMIT - RES | 12/19/2003 | COMPLETED |
| 11/22/2004 | REVISION - WALK THRU | 11/22/2004 | COMPLETED |
| 12/19/2003 | RESIDENTIAL BLDG/WWM | 01/08/2004 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T03CM05505
Permit Status: Final
Permit Description: SFR:NEW
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 11/21/2003 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: Final
Permit Number: T03CM05505
Permit Description: SFR:NEW
Total Completed Inspections - 24
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 05/04/2004 | ELECTRIC - UFER | FGREER | Approved | IVRS - Inspection :* |
| 05/04/2004 | EXCAVATION/LAYOUT REBAR & ZON | FGREER | Approved | IVRS - Inspection :* |
| 05/10/2004 | STEM WALL/RETAINING WALL | RSUBA | Approved | IVRS - Inspection : See detailed listing on site.| 999* |
| 05/19/2004 | PLUMBING - ROUGH, SOIL | JSTANLEY | Approved | IVRS - Inspection :*/ ALSO SEWER TIE-IN OK. |
| 05/26/2004 | BUILDING PRE-SLAB | RSUBA | Approved | IVRS - Inspection :* |
| 06/16/2004 | REINFORCED MASONRY PRE-GROUT | HLEYVA | Approved | IVRS - Inspection :* |
| 06/29/2004 | ROOF NAILING | HLEYVA | Approved | IVRS - Inspection :* |
| 07/07/2004 | PLUMBING - GAS PRESSURE TEST | JSTANLEY | Approved | IVRS - Inspection :* |
| 07/12/2004 | ELECTRIC - INTERMEDIATE | RHOLLAND | Approved | IVRS - Inspection :*/ 1) OK ROUGH |
| 07/13/2004 | PLUMBING - INTERMEDIATE | JSTANLEY | Approved | IVRS - Inspection :* |
| 07/14/2004 | MECHANICAL - INTERMEDIATE | JMILITEL | Approved | IVRS - Inspection :*/ 1) OK FOR SHEETROCK |
| 07/16/2004 | FRAMING | AMATHIES | Approved | IVRS - Inspection :* |
| 07/21/2004 | SHEET ROCK NAILING | AMATHIES | Approved | IVRS - Inspection :* |
| 07/21/2004 | U VALUE FOR WINDOW | AMATHIES | Approved | IVRS - Inspection :* |
| 08/17/2004 | ELECTRIC - CABLE DROP | RMAJUTA | Approved | |
| 08/17/2004 | ELECTRIC - TEMPORARY SERVICE | RMAJUTA | Approved | IVRS - Inspection :* 1) NEED TO PUT # 2 ON METER ADDRESS. 2) FINISH BATHO ROOM LIGHTS 3) PROVIDE LADDER TO ROOF FOR FINAL |
| 08/18/2004 | TEP CLEARANCE - AM | JKOZUCH | Approved | |
| 11/17/2004 | PLUMBING - YARD WTR LINE/TEST | RRICH | Approved | IVRS - Inspection :* |
| 11/24/2004 | MECHANICAL - FINAL | JMILITEL | Approved | IVRS - Inspection :*/LEFT GAS CARD |
| 11/24/2004 | PLUMBING - SEWER HCS CONNECT | RRICH | Approved | IVRS - Inspection :*/APPROVED BY JIM STANLY ON PREVIOUS INSPECTION 5/19/04 |
| 11/24/2004 | PLUMBING - FINAL | RRICH | Approved | IVRS - Inspection :* |
| 12/07/2004 | ELECTRIC - FINAL | RMAJUTA | Approved | IVRS - Inspection :* |
| 12/07/2004 | BUILDING - FINAL | HLEYVA | Approved | IVRS - Inspection :* |
| 06/15/2005 | PERMIT FINALED | LJACKSON | Approved |