Permit Details

Status:
C of o
Type:
MULTI FAMILY NEW
Address NEW:
6790 E CALLE LA PAZ 04
Apply Date:
07/11/2003
Applicant:
METRO PERMIT EXPRESS, INC
Description:
NEW:APARTMENTS TYPE I
Architects:
  • ACORN, KIM BRIAN
Contractors:
  • PREFERRED APARTMENT BUILDERS INC

Permit Reviews

Permit Number - T03CM03420
Permit Status: C of o
Permit Description: NEW:APARTMENTS TYPE I
Start Date Submittal Complete Date Status  
04/08/2004 3RD PARTY REVIEW-COMMERCIAL 04/26/2004 COMPLETED Review Details
04/23/2004 POST 3RD PARTY REVIEW 06/11/2004 COMPLETED Review Details
06/11/2004 RESUBMITTAL 06/18/2004 COMPLETED Review Details
07/11/2003 PLANS OK TO SUBMIT - 3RD PARTY 07/15/2003 COMPLETED Review Details
07/17/2003 3RD PARTY REVIEW-COMMERCIAL 08/13/2003 COMPLETED Review Details
07/20/2004 3RD PARTY REVIEW-REVISION/OTHER 07/30/2004 COMPLETED Review Details
08/20/2004 3RD PARTY REVIEW-REVISION/OTHER 08/23/2004 COMPLETED Review Details
08/30/2004 3RD PARTY REVIEW-REVISION/OTHER 08/31/2004 COMPLETED Review Details
11/09/2004 3RD PARTY REVIEW-REVISION/OTHER 11/15/2004 COMPLETED Review Details
12/07/2004 POST 3RD PARTY REVIEW 12/09/2004 COMPLETED Review Details
12/08/2004 3RD PARTY REVIEW-REVISION/OTHER 12/09/2004 COMPLETED Review Details
12/15/2004 3RD PARTY REVIEW-REVISION/OTHER 12/15/2004 COMPLETED Review Details
12/15/2004 3RD PARTY REVIEW-REVISION/OTHER 12/15/2004 COMPLETED Review Details
12/17/2003 3RD PARTY REVIEW-COMMERCIAL 12/29/2003 COMPLETED Review Details
12/27/2004 3RD PARTY REVIEW-REVISION/OTHER 01/05/2005 COMPLETED Review Details

Completed Inspections

Permit Status: C of o
Permit Number: T03CM03420
Permit Description: NEW:APARTMENTS TYPE I
Total Completed Inspections - 41
Date Description Inspector Results Comments
10/14/2004 PLUMBING - ROUGH, SOIL RRICH Approved IVRS - Inspection :*
11/19/2004 PLUMBING - YARD WTR LINE/TEST JSTANLEY Approved IVRS - Inspection :*/STUB OUT UNDER SLAB OK
11/19/2004 ELECTRIC - UFER RSUBA Approved IVRS - Inspection :*
11/19/2004 BUILDING PRE-SLAB RSUBA Approved IVRS - Inspection :*
12/03/2004 EXCAVATION/LAYOUT REBAR & ZON HLEYVA Approved IVRS - Inspection :*
12/13/2004 ROOF NAILING HLEYVA Approved IVRS - Inspection :*
1) SECOND FLOOR DECKING ONLY
01/19/2005 PLUMBING - SEWER HCS CONNECT RRICH Approved IVRS - Inspection :*6"HCS CONNECTION OK
02/24/2005 EXT METAL CLIPS/EXT SHEATHING BSTEVENS Approved IVRS - Inspection :*
06/07/2005 PLUMBING - INTERMEDIATE TRINIVJR Approved IVRS - Inspection :* 1) SOIL WATER TEST IS OK. 2) OVERHEAD WATER DISTRIBUTION IS OK. 2) OVERHEAD WATER DISTRIBUTION IS OK. 3) R.W.C WATER TEST IS OK.
06/07/2005 FRAMING BSTEVENS Approved IVRS - Inspection :*
06/08/2005 PLUMBING - ROOF DRAINS TRINIVJR Approved IVRS - Inspection :*
06/08/2005 PLUMBING - ABOVE CEILING TRINIVJR Approved IVRS - Inspection :*
08/12/2005 U VALUE FOR WINDOW HLEYVA Approved
08/12/2005 STUCCO MESH HLEYVA Approved
09/01/2005 MECHANICAL - ABOVE CEILING JMILITEL Approved IVRS - Inspection :*
1) OK FOR SHEETROCK
09/01/2005 MECHANICAL - INTERMEDIATE JMILITEL Approved IVRS - Inspection :*
09/03/2005 ELECTRIC - ABOVE CEILING RHOLLAND Approved IVRS - Inspection :*
1) OK ROUGH ELECTRIC
09/03/2005 ELECTRIC - INTERMEDIATE RHOLLAND Approved IVRS - Inspection :*
09/06/2005 BUILDING ABOVE CEILING LHANLY Approved IVRS - Inspection :*
09/15/2005 SHEET ROCK NAILING LHANLY Approved IVRS - Inspection :*
09/22/2005 ELECTRIC - CABLE DROP RSUBA Approved IVRS - Inspection :*
1) OK TO CLEAR 4101-4108, 4201-4208 AND HOUSE PANEL
10/26/2005 MECHANICAL - FINAL JMILITEL Approved IVRS - Inspection :*
1) OK FOR FINAL
11/01/2005 TEP CLEARANCE - AM RMAJUTA Approved OK TEMP POWER BLDG 4 PER SUBA
11/10/2005 FIRE - FINAL LTHOMAS Approved
11/10/2005 FIRE SPKLR - FINAL LTHOMAS Approved
11/10/2005 FIRE SPKLR - OH PIPING & HYDRO LTHOMAS Approved
11/10/2005 FIRE SPKLR - UG PIPING FLUSH LTHOMAS Approved
11/10/2005 FIRE SPKLR - UG, PIPING, HYDRO LTHOMAS Approved
11/12/2005 PLUMBING - FINAL TRINIVJR Approved IVRS - Inspection :*PLBG FINAL IS OK
OK FOR C OF O
11/14/2005 SIGN - FINAL RDEAR Approved IVRS - Inspection :*
11/15/2005 OUTDOOR LIGHTING FINAL RHOLLAND Approved IVRS - Inspection :*OK OUTDOOR LIGHTING
11/21/2005 RIGHT OF WAY - FINAL PWHIDDON Approved PER EMAIL
11/22/2005 ENGINEERING - FINAL JBRUCKME Approved TEMPORARY C OF O APPROVED.
1. PERMANENT C OF O NOT TO BE GIVEN UNTIL THE FINAL GRADING INSPECTION #09190 FOR T03BU03223 IS COMPLETED AND APPROVED.
2. PROVIDE A REVISED AND C.O.T. APPROVED GRADING PLAN TO SHOW ALL REVISIONS AND MODIFICATIONS.
3. CONSTRUCT THE TYPE II SIDEWALK SCUPPER AT THE SOUTHEAST CORNER OF THE PROJECT TO COT/PC STANDARD DETAIL 205.
4. BARRICADE ALL AREAS WHERE ON-GOING CONSTRUCTION ACTIVITY IS OCCURRING.
5. CLEAN-UP AND REMOVE ALL CONSTRUCTION MATERIAL, DEBRIS, AND TEMPORARY CONSTRUCTION FENCING.
11/22/2005 NPPO - FINAL ACONNOR Approved Ok for Temp C of O
11/22/2005 LANDSCAPE - FINAL ACONNOR Approved Ok for Temp C of O
11/22/2005 ELECTRIC - FINAL RHOLLAND Approved IVRS - Inspection :*
11/22/2005 ELECTRIC - TEMP POWER FOR TEST RHOLLAND Approved IVRS - Inspection :*
11/22/2005 ELECTRIC - UNDERGROUND RHOLLAND Approved IVRS - Inspection :*
11/28/2005 BUILDING - FINAL JCAGLE Approved OK FOR TEMP C OF O PER INSP COPY
11/28/2005 BUILDING - FINAL JCAGLE Approved IVRS - Inspection :*
04/12/2006 PERMIT FINALED GBONILLA Approved

Documents

File Name Document Type  
C OF O_04-12-2006.TIF CERT OF OCC VIEW
None DOCUMENTS VIEW