Permit: T03CM02747
Permit Details
Status:
C of o
Type:
COMMERCIAL NEW
Address:
1315 E BENSON HY BLDG #2
Address NEW:
1315 E BENSON HY BLDG #2
Apply Date:
06/04/2003
Applicant:
METRO PERMIT EXPRESS, INC
Description:
NEW:WHOLESALE & FABRICATION BLDG
Contractors:
- FAST FAB ERECTORS INC ,
- GALLEGO PLUMBING
- M R M C CONTRACTING L L C
- SWINIUCH ELECTRIC ,
Permit Reviews
Permit Number - T03CM02747
Permit Status: C of o
Permit Description: NEW:WHOLESALE & FABRICATION BLDG
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 05/10/2004 | SITE | 05/11/2004 | COMPLETED |
| 06/04/2003 | PLANS OK TO SUBMIT - 3RD PARTY | 07/16/2003 | COMPLETED |
| 07/17/2003 | 3RD PARTY REVIEW-COMMERCIAL | 07/28/2003 | COMPLETED |
| 09/16/2003 | 3RD PARTY REVIEW-COMMERCIAL | 09/22/2003 | COMPLETED |
| 09/26/2003 | 3RD PARTY REVIEW-COMMERCIAL | 10/07/2003 | COMPLETED |
Completed Inspections
Permit Status: C of o
Permit Number: T03CM02747
Permit Description: NEW:WHOLESALE & FABRICATION BLDG
Total Completed Inspections - 36
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 10/15/2003 | PLUMBING - ROUGH, SOIL | TRINIVJR | Approved | IVRS - Inspection 0000*1) SOIL WATER TEST IS OK. 2) NOTE: BLDG DRAIN IS STUBBED OUT OF BLDG AT TWO WAY C.O. ONLY. 3) OK TO BACKFILL TRENCH. |
| 10/30/2003 | ELECTRIC - UFER | DSANTACR | Approved | IVRS - Inspection 0000* |
| 10/30/2003 | BUILDING PRE-SLAB | AMATHIES | Approved | IVRS - Inspection 0000* |
| 10/30/2003 | EXCAVATION/LAYOUT REBAR & ZON | AMATHIES | Approved | IVRS - Inspection 0000* |
| 12/24/2003 | U VALUE FOR WINDOW | AMATHIES | Approved | IVRS - Inspection 0000* |
| 12/24/2003 | ROOF NAILING | AMATHIES | Approved | IVRS - Inspection 0000* |
| 12/24/2003 | EXT METAL CLIPS/EXT SHEATHING | AMATHIES | Approved | IVRS - Inspection 0000* |
| 12/29/2003 | PLUMBING - ABOVE CEILING | TRINIVJR | Approved | 1) SOIL WATER TEST IS OK. 2) OVERHEAD WTR DISTRIBUTION IS OK. 3) OK FOR DRYWALL. |
| 12/29/2003 | PLUMBING - INTERMEDIATE | TRINIVJR | Approved | |
| 12/29/2003 | ELECTRIC - INTERMEDIATE | DSANTACR | Approved | IVRS - Inspection 0000* |
| 12/29/2003 | FRAMING | AMATHIES | Approved | IVRS - Inspection 0000* |
| 01/06/2004 | SHEET ROCK NAILING | AMATHIES | Approved | IVRS - Inspection 0000* |
| 01/26/2004 | MECHANICAL - INTERMEDIATE | CWILLIAM | Approved | IVRS - Inspection 0000* |
| 01/26/2004 | ELECTRIC - ABOVE CEILING | DSANTACR | Approved | IVRS - Inspection 0000* |
| 02/02/2004 | MECHANICAL - ABOVE CEILING | CWILLIAM | Approved | IVRS - Inspection 0000* |
| 02/17/2004 | PLUMBING - SEWER HCS CONNECT | TRINIVJR | Approved | IVRS - Inspection 0000* |
| 02/17/2004 | ELECTRIC - CABLE DROP | DSANTACR | Approved | IVRS - Inspection 0000*/ OK CABLE DROP TO ALLOW BACKFILL OF TRENCH. |
| 02/17/2004 | ELECTRIC - UNDERGROUND | DSANTACR | Approved | IVRS - Inspection 0000* |
| 02/19/2004 | PLUMBING - YARD WTR LINE/TEST | TRINIVJR | Approved | IVRS - Inspection 0000*/ ALL CORRECTIONS HAVE BEEN MADE. |
| 02/27/2004 | ELECTRIC - FINAL | DSANTACR | Approved | IVRS - Inspection 0000*/ 1) OK TO CLEAR TEMP POWER FOR TEST. SUBJECT TO BOND POSTING METER #2. PLEASE CLEAR UPON BOND POSTING. ELECTRICAL INSTALL COMPLETE |
| 03/10/2004 | PLUMBING - TEMP POWER FOR TEST | RRICH | Approved | IVRS - Inspection 0000* |
| 03/10/2004 | ELECTRIC - TEMP POWER FOR TEST | DSANTACR | Approved | IVRS - Inspection 0000*/ OK TO CLEAR TEMP POWER FOR TEST SUBJECT TO BOND POSTING AND APPROVAL OF OTHER INSP. SENT TO TEP ON 03/11/04PM |
| 03/11/2004 | MECHANICAL - TEMP PWR FOR TEST | CWILLIAM | Approved | IVRS - Inspection 0000* |
| 03/11/2004 | BUILDING - TEMP POWER FOR TEST | AMATHIES | Approved | |
| 03/16/2004 | PLUMBING - FINAL | TRINIVJR | Approved | IVRS - Inspection 0000*/ PLBG FINAL IS OK. OK FOR C OF O. |
| 03/19/2004 | SIGN - FINAL | JYBARRA | Approved | IVRS - Inspection 0000* |
| 03/19/2004 | FIRE - FINAL | LTHOMAS | Approved | 1) OK C OF O |
| 03/22/2004 | RIGHT OF WAY - FINAL | LLOPEZ | Approved | |
| 03/22/2004 | MECHANICAL - FINAL | CWILLIAM | Approved | IVRS - Inspection 0000* |
| 05/13/2004 | NPPO - FINAL | ACONNOR | Approved | |
| 05/13/2004 | LANDSCAPE - FINAL | ACONNOR | Approved | |
| 05/13/2004 | ENGINEERING - FINAL | JBRUCKME | Approved | |
| 05/18/2004 | OUTDOOR LIGHTING FINAL | RHOLLAND | Approved | IVRS - Inspection :*/ OK 8 - 60 WATT FIXTURES. |
| 05/19/2004 | BUILDING - FINAL | AMATHIES | Approved | IVRS - Inspection :* |
| 05/19/2004 | BUILDING ABOVE CEILING | AMATHIES | Approved | IVRS - Inspection :* |
| 06/04/2004 | PERMIT FINALED | AMATHIES | Approved |