Permit: T03CM02450
Permit Details
Status:
C of o
Type:
COMMERCIAL ALTERATION
Address:
4534 E CAMP LOWELL DR
Address NEW:
4534 E CAMP LOWELL DR
Apply Date:
05/20/2003
Applicant:
ROBINETTE ARCHITECTS
Description:
TI:OFFICE
Architects:
- ROBINETTE, RONALD WILLIAM
Contractors:
- RIO WEST DEVELOPMENT AND CONSTRU
Permit Reviews
Permit Number - T03CM02450
Permit Status: C of o
Permit Description: TI:OFFICE
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 05/20/2003 | PLANS OK TO SUBMIT - 3RD PARTY | 06/02/2003 | COMPLETED |
| 06/04/2003 | 3RD PARTY REVIEW-COMMERCIAL TI | 06/17/2003 | COMPLETED |
| 06/23/2003 | 3RD PARTY REVIEW-COMMERCIAL TI | 07/28/2003 | COMPLETED |
| 11/24/2003 | 3RD PARTY REVIEW-REVISION/OTHER | 11/25/2003 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T03CM02450
Permit Status: C of o
Permit Description: TI:OFFICE
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 05/20/2003 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T03CM02450
Permit Description: TI:OFFICE
Total Completed Inspections - 23
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 10/02/2003 | PLUMBING - ABOVE CEILING | JSTANLEY | Approved | IVRS - Inspection 0000*/ CODE VIOLATION ON CONDENSATE LINE. CONDENSATE TO SINK NOT TO CODE. |
| 10/02/2003 | PLUMBING - INTERMEDIATE | JSTANLEY | Approved | IVRS - Inspection 0000* |
| 10/02/2003 | FRAMING | RSUBA | Approved | IVRS - Inspection 0000* |
| 10/10/2003 | RIGHT OF WAY - FINAL | PWHIDDON | Approved | |
| 10/20/2003 | ELECTRIC - INTERMEDIATE | RHOLLAND | Approved | IVRS - Inspection 0000* OK HARD CEILINGS |
| 10/22/2003 | SHEET ROCK NAILING | RSUBA | Approved | IVRS - Inspection 0000* |
| 11/06/2003 | MECHANICAL - INTERMEDIATE | JMILITEL | Approved | IVRS - Inspection 0000* |
| 11/07/2003 | MECHANICAL - ABOVE CEILING | JMILITEL | Approved | IVRS - Inspection 0000*/ 1) INSPECTED CONDENSATE DRAIN LINES, ALL DUCT ABOVE T-BAR. CHECKED DUCT SMOKE DETECTORS. WILL CHECK OPERATION OF DETECTORS ON FINAL. OK FOR CEILING TILES |
| 11/12/2003 | SIGN - FINAL | JYBARRA | Approved | |
| 11/18/2003 | ELECTRIC - ABOVE CEILING | RHOLLAND | Approved | IVRS - Inspection 0000*/ 1) OK LOBBY |
| 11/21/2003 | MECHANICAL - TEMP PWR FOR TEST | JMILITEL | Approved | IVRS - Inspection 0000* |
| 11/21/2003 | BUILDING - TEMP POWER FOR TEST | RSUBA | Approved | IVRS - Inspection 0000* |
| 11/24/2003 | PLUMBING - TEMP POWER FOR TEST | JSTANLEY | Approved | IVRS - Inspection 0000*/ SUBJECT TO OTHER INSP. PLEASE HAVE REVISED PLAN BY NEXT INSP. |
| 11/24/2003 | ELECTRIC - TEMP POWER FOR TEST | RHOLLAND | Approved | IVRS - Inspection 0000*/ 1) OK TEMP POWER FOR TESTING. NO OCCUPANCY ALLOWED IF SPACE IS OCCUPIED WITHOUT C OF O/TEMP C OF O POWER MAY BE DISCONNECTED |
| 11/26/2003 | ENGINEERING - FINAL | DROBERTS | Approved | TEMPORARY C OF O APPROVED AT THIS TIME, FINAL NOT TO BE GIVEN UNTIL ALL REMAINING WORK ON THIS SITE IS COMPLETE AND THE FINAL GRADING PERMIT IS CLEARED. THE WORKING REMAINING ON THIS SITE CONSIST TO THE FOLLOWING BUT IS NOT LIMITED TO: 1) CURBS AND SIDEWALKS 2) GRADING ADJACENT TO THE SIDEWALKS 3) HANDRAILS AS NEEDED |
| 11/26/2003 | FIRE - FINAL | JEGAN | Approved | IVRS - Inspection 0000* |
| 12/01/2003 | MECHANICAL - FINAL | CWILLIAM | Approved | IVRS - Inspection 0000*/ OK TEMP C OF O. |
| 12/01/2003 | PLUMBING - FINAL | JSTANLEY | Approved | IVRS - Inspection 0000*/ FINAL OK S.T.O.I. |
| 12/01/2003 | PLUMBING - ROUGH, SOIL | JSTANLEY | Approved | IVRS - Inspection 0000* |
| 12/03/2003 | ELECTRIC - CONSTRUCTION POWER | RHOLLAND | Approved | IVRS - Inspection 0000* |
| 12/05/2003 | ELECTRIC - FINAL | RHOLLAND | Approved | IVRS - Inspection 0000*/ 1) OK FINAL |
| 12/05/2003 | BUILDING - FINAL | RSUBA | Approved | IVRS - Inspection 0000* |
| 10/07/2004 | PERMIT FINALED | TACHONG | Approved |