Permit Details

Status:
Final
Type:
DUPLEX NEW
Address NEW:
429 E LINCOLN ST #01
Apply Date:
02/25/2002
Applicant:
SONORA EXPEDITIONS
Description:
NEW:DUPLEX
Contractors:
  • C D ENTERPRISES

Permit Reviews

Permit Number - T02CM01053
Permit Status: Final
Permit Description: NEW:DUPLEX
Start Date Submittal Complete Date Status  
02/25/2002 RESIDENTIAL BLDG/ZONING/FLOOD/WWM 04/15/2002 COMPLETED Review Details
02/25/2002 SITE 05/14/2002 COMPLETED Review Details
04/23/2002 RESUBMITTAL 05/14/2002 COMPLETED Review Details

Outstanding Activity Conditions

Permit Number - T02CM01053
Permit Status: Final
Permit Description: NEW:DUPLEX
Total Outstanding Activity Conditions - 1
Date Name
02/25/2002 PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION.

Completed Inspections

Permit Status: Final
Permit Number: T02CM01053
Permit Description: NEW:DUPLEX
Total Completed Inspections - 23
Date Description Inspector Results Comments
07/10/2002 PLUMBING - ROUGH, SOIL RMYERS Approved IVRS - Inspection 0000*ABS DWV UNDERGROUND OK WATER TEST OK 2.) OK TO BACKFILL.
07/16/2002 ELECTRIC - UFER DSANTACR Approved IVRS - Inspection 0000*NOTES 1.) OK #2 BARE 20'IN FOOTING. 2.) PLEASE HAVE CITY APPROVED PLANS ON SITE.
07/16/2002 BUILDING PRE-SLAB LHANLY Approved IVRS - Inspection 0000*
07/16/2002 EXCAVATION/LAYOUT REBAR & ZON LHANLY Approved IVRS - Inspection 0000*PLEASE CUT COLUMN FOOTER @ NW CORNER SO THAT YOU HAVE 3" CLEAR DISTANCE FROM RE-BAR TO EARTH.
08/28/2002 PLUMBING - GAS PRESSURE TEST RMYERS Approved IVRS - Inspection 0000*1.) NO GAS PIPNG INSTALLED AT THIS TIME. 2.) IT IS NOT THE RESPONSIBILITY OF THIS DEPT. TO PROVIDE THE PLUMBER WITH A PUNCH LIST HAVE A JOURNEYMAN PLUMBER CHECK ALL WORK, ESPECIALLY: 1.) 804.1 STANDPIPE RECEPTORS 2.) 1002.2 TRAP ARMS 3.) A TRAP ARM MAY NOT CHANGE SIZE A TRAP ARM AND TRAP TO BE THE SAME SIZE. 4.) SEE TABLE 3-1 HORIZONTAL SUPPORT FOR ABS. 5.) WASTE AND OVER FLOW CONNECTIONS COVERED BEFORE INSPECTION. 6.) THIS MAY NOT BE A COMPLETE LIST OF CODE VIOLATIONS HAVE COMPETANT PERSON CHECK ALL WORK.
09/11/2002 FRAMING LHANLY Approved IVRS - Inspection 0000*
09/11/2002 ROOF NAILING LHANLY Approved IVRS - Inspection 0000*
09/12/2002 MECHANICAL - INTERMEDIATE CWILLIAM Approved IVRS - Inspection 0000*
09/17/2002 ELECTRIC - FINAL JORTA Approved IVRS - Inspection 0000*
09/20/2002 PLUMBING - INTERMEDIATE RMYERS Approved 1.) ALL CORRECTIONS MADE OK 2.) OK TO COVER WALLS AND CEILINGS 3.) CLOSET FLANGES OK 4.)TUBS OK.
09/25/2002 ELECTRIC - INTERMEDIATE JORTA Approved IVRS - Inspection 0000*
09/25/2002 EXT METAL CLIPS/EXT SHEATHING LHANLY Approved IVRS - Inspection 0000*
10/01/2002 SHEET ROCK NAILING LHANLY Approved IVRS - Inspection 0000*OK TO TAPE. I STILL NEED TO SEE FIRE STOP SYSTEM.
11/21/2002 U VALUE FOR WINDOW RSUBA Approved IVRS - Inspection 0000*
11/21/2002 STUCCO MESH RSUBA Approved IVRS - Inspection 0000*
12/09/2002 ELECTRIC - TEMPORARY SERVICE RMAJUTA Approved IVRS - Inspection 0000*
12/09/2002 ELECTRIC - CABLE DROP RMAJUTA Approved IVRS - Inspection 0000*OK TO CLEAR TEC 1 & 2.
01/09/2003 PLUMBING - SEWER HCS CONNECT RMYERS Approved IVRS - Inspection 0000*1.) 3" ABS SEWER, FROM 2 WAY TO TIE IN AT HCS OK WATER TEST OK TRANSITION FITTING OK OK TO COVER.
2.) YARD WATER NOT INSTALLED PER PLAN. PLAN CALLS FOR ONE INCH SERVICE.
01/23/2003 PLUMBING - YARD WTR LINE/TEST RMYERS Approved IVRS - Inspection 0000*
02/17/2004 MECHANICAL - FINAL CWILLIAM Approved IVRS - Inspection 0000*
02/17/2004 PLUMBING - FINAL TRINIVJR Approved IVRS - Inspection 0000*/ 1) PLBG FINAL IS OK. 2) OK FOR C OF O.
02/18/2004 BUILDING - FINAL AMATHIES Approved IVRS - Inspection 0000*
02/19/2004 PERMIT FINALED AMATHIES Approved

Documents

File Name Document Type  
None DOCUMENTS VIEW