Permit: T02CM00284
Permit Details
Apply Date:
01/17/2002
Applicant:
RAINHART ARCHITECTS
Description:
NEW:PHARMACY (WALGREENS) TEMP CO OK PER SLONG
Contractors:
- WILGER ENTERPRISES INC ,
Permit Reviews
Permit Number - T02CM00284
Permit Status: C of o
Permit Description: NEW:PHARMACY (WALGREENS) TEMP CO OK PER SLONG
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
01/17/2002 | 3RD PARTY REVIEW-COMMERCIAL | 05/01/2002 | COMPLETED |
04/19/2002 | SITE | 05/01/2002 | COMPLETED |
10/07/2002 | REVISION | 10/07/2002 | COMPLETED |
Outstanding Activity Conditions
Permit Number - T02CM00284
Permit Status: C of o
Permit Description: NEW:PHARMACY (WALGREENS) TEMP CO OK PER SLONG
Total Outstanding Activity Conditions - 1
Date | Name |
---|---|
01/17/2002 | PLANS EXPIRE IN 180 DAYS FROM DATE OF SUBMITTAL. PERMITS EXPIRE IN 180 DAYS FROM DATE OF ISSUE OR LAST INSPECTION. |
Completed Inspections
Permit Status: C of o
Permit Number: T02CM00284
Permit Description: NEW:PHARMACY (WALGREENS) TEMP CO OK PER SLONG
Total Completed Inspections - 34
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
05/07/2002 | ELECTRIC - UFER | DSANTACR | Approved | IVRS - Inspection 0000* |
05/13/2002 | PLUMBING - ROUGH, SOIL | TRINIVJR | Approved | IVRS - Inspection 0000*1.) SOIL WATER TEST IS OK 2.) NOTE: BLDG. DRAIN IS STUBBED OUT AT TWO WAY C.O. ONLY 3.) OK TO BACKFILL TRENCH. |
06/26/2002 | ELECTRIC - INTERMEDIATE | DSANTACR | Approved | IVRS - Inspection 0000*OK WALLS. |
07/08/2002 | ROOF NAILING | AQUIROZ | Approved | IVRS - Inspection 0000* |
07/08/2002 | EXT METAL CLIPS/EXT SHEATHING | AQUIROZ | Approved | IVRS - Inspection 0000* |
07/12/2002 | MECHANICAL - INTERMEDIATE | JMILITEL | Approved | IVRS - Inspection 0000*OK TO SHEET ROCK CEILING PROVIDE LETTER FROM ENGINEER ABOUT INTENT OF FIRE SMOKE DAMPERS & DELETED UNIT HEATER OK TO PROCEED W/GRID. OK TO INSULATE DUCT. |
07/12/2002 | PLUMBING - INTERMEDIATE | TRINIVJR | Approved | IVRS - Inspection 0000*1.) SOIL WATER TEST IS OK 2.) OVERHEAD WATER DISTRIBUTION IS OK 3.) OK FOR DRYWALL. |
07/12/2002 | STUCCO MESH | AQUIROZ | Approved | IVRS - Inspection 0000* |
07/12/2002 | FRAMING | AQUIROZ | Approved | IVRS - Inspection 0000* |
07/16/2002 | PLUMBING - GAS PRESSURE TEST | TRINIVJR | Approved | IVRS - Inspection 0000* 1.) GAS PRESSURE TEST IS OK 2.) OVERHEAD GAS DISTRIBUTION IS OK. |
07/24/2002 | PLUMBING - SEWER HCS CONNECT | TRINIVJR | Approved | IVRS - Inspection 0000*1.) SOIL WATER TEST IS OK 2.) SITE SEWER IS OK FROM MH #2 EAST TO C.O. AND SOUTH TO P.O.C. OF BLDG. DRAIN TO BLDG. SEWER. 3.) OK TO BACKFILL TRENCH 4.) NOTE: WILL REQUIRE A REVISED & APPROVED DRAWING ON SITE SEWER PRIOR TO FINAL INSPECTION. |
07/29/2002 | MECHANICAL - ABOVE CEILING | JMILITEL | Approved | IVRS - Inspection 0000*OK FOR CEILING TILES. |
07/29/2002 | PLUMBING - ABOVE CEILING | TRINIVJR | Approved | IVRS - Inspection 0000*1.) ABOVE CEILING IS OK 2.) OK FOR GRID. |
07/29/2002 | ELECTRIC - UNDERGROUND | DSANTACR | Approved | IVRS - Inspection 0000* |
08/01/2002 | BUILDING ABOVE CEILING | AQUIROZ | Approved | IVRS - Inspection 0000* |
09/24/2002 | ELECTRIC - ABOVE CEILING | DSANTACR | Approved | IVRS - Inspection 0000* |
10/01/2002 | REINFORCED MASONRY PRE-GROUT | AQUIROZ | Approved | IVRS - Inspection 0000* |
10/01/2002 | BUILDING PRE-SLAB | AQUIROZ | Approved | IVRS - Inspection 0000* |
10/01/2002 | STEM WALL/RETAINING WALL | AQUIROZ | Approved | IVRS - Inspection 0000* |
10/08/2002 | MECHANICAL - FINAL | JMILITEL | Approved | IVRS - Inspection 0000*ALL CORRECTION HAVE BEEN MADE OK FOR C OF O. ALL PLUMBING CORRECTIONS HAVE BEEN MADE. OK FOR C OF O AS PER TRINI LEFT GAS CARD. |
10/08/2002 | FIRE - FINAL | LTHOMAS | Approved | OK FOR C OF O SPRINKLER FINAL OK |
10/08/2002 | PLUMBING - FINAL | TRINIVJR | Approved | IVRS - Inspection 0000*PLBG. FINAL IS OK 2.) OK FOR C OF O. |
10/08/2002 | ELECTRIC - FINAL | DSANTACR | Approved | IVRS - Inspection 0000*OK C OF O. |
10/08/2002 | ELECTRIC - CABLE DROP | DSANTACR | Approved | |
10/09/2002 | BUILDING - FINAL | AQUIROZ | Approved | IVRS - Inspection 0000* |
10/09/2002 | SHEET ROCK NAILING | AQUIROZ | Approved | IVRS - Inspection 0000* |
10/09/2002 | U VALUE FOR WINDOW | AQUIROZ | Approved | IVRS - Inspection 0000* |
10/09/2002 | EXCAVATION/LAYOUT REBAR & ZON | AQUIROZ | Approved | IVRS - Inspection 0000* |
10/17/2002 | RIGHT OF WAY - FINAL | PWHIDDON | Approved | TEMP ONLY PENDING COMPLETION OF P I A |
10/22/2002 | SIGN - FINAL | DJOHNSTO | Approved | IVRS - Inspection 0000* |
12/09/2002 | NPPO - FINAL | PGILBERT | Approved | |
12/09/2002 | LANDSCAPE - FINAL | PGILBERT | Approved | |
12/09/2002 | ENGINEERING - FINAL | JBRUCKME | Approved | TEMPORARY C OF O APPROVED. PERMANENT C OF O NOT TO BE GRANTED UNTIL THE FINAL GRADING INSPECTION #09190 FOR T02BU00869 HAS BEEN COMPLETED AND ACCEPTED. |
03/19/2003 | PERMIT FINALED | AQUIROZ | Approved |