Permit: T01CM03501
Permit Details
Apply Date:
07/17/2001
Applicant:
N/A
Description:
SERVICE STATION:NEW
Architects:
- BOTTOMLEY, THOMAS ROBERT
Contractors:
- HAWORTH CORPORATION , THE
Permit Reviews
Permit Number - T01CM03501
Permit Status: C of o
Permit Description: SERVICE STATION:NEW
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
07/17/2001 | 3RD PARTY REVIEW-COMMERCIAL | 10/03/2001 | COMPLETED |
10/01/2001 | SITE | 10/03/2001 | COMPLETED |
11/21/2001 | REVISION | 11/27/2001 | COMPLETED |
Completed Inspections
Permit Status: C of o
Permit Number: T01CM03501
Permit Description: SERVICE STATION:NEW
Total Completed Inspections - 31
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
10/17/2001 | PLUMBING - ROUGH, SOIL | RMYERS | Approved | IVRS - Inspection 0000*1.) ABS UNDERGROUND OK .2) WATER TEST OK 3.) OK TO BACKFILL NOTE* INVERT REQUIRES ONE PERENT PITCH ON BLDG DRAIN. |
10/24/2001 | ELECTRIC - UFER | JORTA | Approved | AT MAIN STORE. |
10/24/2001 | ELECTRIC - UFER | JORTA | Approved | IVRS - Inspection 0000* |
11/05/2001 | ROOF NAILING | LHANLY | Approved | IVRS - Inspection 0000* |
11/05/2001 | EXT METAL CLIPS/EXT SHEATHING | LHANLY | Approved | IVRS - Inspection 0000* |
11/14/2001 | SHEET ROCK NAILING | DWITT | Approved | |
11/16/2001 | STUCCO MESH | LHANLY | Approved | IVRS - Inspection 0000* |
11/20/2001 | STEM WALL/RETAINING WALL | LHANLY | Approved | IVRS - Inspection 0000* |
11/20/2001 | EXCAVATION/LAYOUT REBAR & ZON | LHANLY | Approved | IVRS - Inspection 0000* |
11/28/2001 | PLUMBING - SEWER HCS CONNECT | RMYERS | Approved | IVRS - Inspection 0000*1. 4" ABS SEWER FROM BACKWATER VALVE TO TIE-IN AT EXISTING OK WATER TEST OK 2.) OK TO COVER. |
11/30/2001 | MECHANICAL - INTERMEDIATE | CWILLIAM | Approved | |
11/30/2001 | FRAMING | LHANLY | Approved | IVRS - Inspection 0000* |
12/03/2001 | PLUMBING - YARD WTR LINE/TEST | RMYERS | Approved | IVRS - Inspection 0000*1.) ALL CORRECTIONS MADE OK ON YARDWATER 2.) REMEMBER NO CONNECTIONS MAY BE MADE BETWEEN METER AND RPBP. 3.) OK TO COVER ALL AREAS OF YARDWATER PIPING. |
12/07/2001 | PLUMBING - ABOVE CEILING | RMYERS | Approved | IVRS - Inspection 0000*1. 11/09/01 NOTE #2 CHECK VALVES OK 2.) OK FOR CEILING TILE. |
12/07/2001 | BUILDING ABOVE CEILING | LHANLY | Approved | IVRS - Inspection 0000* |
12/10/2001 | MECHANICAL - ABOVE CEILING | CWILLIAM | Approved | IVRS - Inspection 0000* |
12/10/2001 | ELECTRIC - ABOVE CEILING | JORTA | Approved | IVRS - Inspection 0000* |
12/13/2001 | MECHANICAL - TEMP PWR FOR TEST | CWILLIAM | Approved | |
12/13/2001 | PLUMBING - TEMP POWER FOR TEST | RMYERS | Approved | IVRS - Inspection 0000*OK FOR TEMP POWER. |
12/20/2001 | BUILDING PRE-SLAB | LHANLY | Approved | IVRS - Inspection 0000* |
12/27/2001 | SIGN - FINAL | JYBARRA | Approved | IVRS - Inspection 0000* |
12/27/2001 | PLUMBING - FINAL | RMYERS | Approved | |
12/27/2001 | PLUMBING - INTERMEDIATE | RMYERS | Approved | 1.) CAR WASH INTERMEDIATE OK (ALL EXPOSED) 2.) CAR WASH FINAL OK PENDING ANY OTHER INSPECTIONS.3 .) PLUMBING FINAL FOR SERVICE STATION OK 4.) ALL RPBP CERTIFIED OK ON FILE OF TUCSON WATER. 5.) OK FOR C OF O. PENDING ANY OTHER INSPECTIONS. |
12/27/2001 | ELECTRIC - FINAL | DSANTACR | Approved | IVRS - Inspection 0000*OK FOR C OF O. |
12/27/2001 | ELECTRIC - INTERMEDIATE | DSANTACR | Approved | IVRS - Inspection 0000* |
12/27/2001 | ELECTRIC - UNDERGROUND | DSANTACR | Approved | IVRS - Inspection 0000* |
12/28/2001 | MECHANICAL - FINAL | CWILLIAM | Approved | APPROVED |
12/28/2001 | BUILDING - FINAL | LHANLY | Approved | IVRS - Inspection 0000* |
01/02/2002 | PERMIT FINALED | ENGINEER | Approved | |
01/02/2002 | RIGHT OF WAY - FINAL | ENGINEER | Approved | |
01/02/2002 | ENGINEERING - FINAL | ENGINEER | Approved |