Permit: DP22-0290
Permit Details
Apply Date:
10/17/2022
Applicant:
Description:
Revision 3 - Site/Grading - 7th Avenue Lofts site improvements. Replace and improve existing parking.
Permit Reviews
Permit Number - DP22-0290
Permit Status: Complete
Permit Description: Revision 3 - Site/Grading - 7th Avenue Lofts site improvements. Replace and improve existing parking.
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 10/17/2022 | DEV PKG - OK TO SUBMIT | 10/20/2022 | ACTIVE |
| 04/25/2025 | DEVELOPMENT PACKAGE NEW REVISION v.4 | 05/15/2025 | APPROVED |
| 09/16/2024 | DEVELOPMENT PACKAGE NEW REVISION v.1 | 11/25/2024 | APPROVED |
| 03/20/2025 | DEVELOPMENT PACKAGE NEW REVISION v.2 | 03/20/2025 | REQUIRES RESUBMIT |
| 03/20/2025 | DEVELOPMENT PACKAGE NEW REVISION v.3 | 04/09/2025 | REQUIRES RESUBMIT |
| 02/15/2023 | DEVELOPMENT PACKAGE REVIEW v.4 | 03/09/2023 | REQUIRES RESUBMIT |
| 06/13/2024 | DEVELOPMENT PACKAGE REVIEW v.1 | 07/31/2024 | APPROVED |
| 10/28/2022 | DEVELOPMENT PACKAGE REVIEW v.1 | 12/14/2022 | REQUIRES RESUBMIT |
| 12/27/2022 | DEVELOPMENT PACKAGE REVIEW v.2 | 12/30/2022 | REQUIRES RESUBMIT |
| 03/28/2023 | DEVELOPMENT PACKAGE REVIEW v.5 | 06/12/2023 | APPROVED |
| 11/29/2024 | DEVELOPMENT PACKAGE NEW REVISION v.1 | 01/13/2025 | REQUIRES RESUBMIT |
| 01/05/2023 | DEVELOPMENT PACKAGE REVIEW v.3 | 01/26/2023 | REQUIRES RESUBMIT |
| 10/28/2022 | DEVELOPMENT PACKAGE REVIEW v.1 | 12/22/2022 | REQUIRES RESUBMIT |
Outstanding Inspections
Permit Status: Complete
Permit Number: DP22-0290
Permite Description: Revision 3 - Site/Grading - 7th Avenue Lofts site improvements. Replace and improve existing parking.
Total Outstanding Inspections - 9
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 11/14/2023 | SITE | N/A | Partial Pass | |
| 10/12/2023 | PDSD Site/Engineering Division - NPPO | N/A | Partial Pass | Project has 10 native plants to be saved in place and 10 require transplant |
| 05/01/2024 | ENGR - Drainage Structures | N/A | Not Ready | Plan specifies a double enclosure. Rough Grading only at this time. |
| 10/12/2023 | PDSD Engineering Division Pre-Construction SITE | N/A | Partial Pass | Remodel of existing building. Caldwell constructors. Entrance to site is locked. Contain all materials within site schedule inspections from development package permit on a regular basis and prior to final. |
| 11/29/2024 | Consultation SITE | N/A | Not Ready | Per Ernie Stephens. Contractor cancelled joint walk through for TCO |
| 10/11/2024 | N/A | Partial Pass | Looked at the footer for a wall located at the southwest corner of the building, it is ready to be poured. Also a small crew has poured some sidewalk at the southeast corner of the site. | |
| 07/11/2024 | COT - ENGR - Stormwater | N/A | Complete (Recurring) | Also looked at trash enclosure footing and it passed |
| 02/16/2024 | SITE - Stormwater Follow-up | N/A | Partial Pass | |
| 02/16/2024 | Final inspection to ensure all landscape and water harvesting SITE | N/A | Partial Pass |
Completed Inspections
Permit Status: Complete
Permit Number: DP22-0290
Permit Description: Revision 3 - Site/Grading - 7th Avenue Lofts site improvements. Replace and improve existing parking.
Total Completed Inspections - 13
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 05/01/2024 | PDSD Engineering Division Pre-Construction SITE | Passed | ||
| 12/19/2024 | Passed | |||
| 12/19/2024 | For trash and recycling enclosures | Passed | ||
| 12/19/2024 | COT - ENGR - Stormwater | Passed | ||
| 12/19/2024 | Passed | |||
| 12/19/2024 | Passed | |||
| 12/24/2024 | SITE - Stormwater Follow-up | Passed | ||
| 12/24/2024 | SITE - Zoning Final | Passed | ||
| 12/24/2024 | ENGR Paving | Passed | ||
| 12/24/2024 | SITE - Stormwater Final Inspection | Passed | ||
| 12/24/2024 | NPPO Final | Passed | ||
| 01/13/2025 | Final inspection to ensure all landscape and water harvesting SITE | Passed | Site Landscape inspection 1/13/25. - The trees along the east property line appear to be dying or are in shock. Owner/owner representative to review the tree health in late spring/summer of 2025 to make sure the trees are still alive and thriving. If not, please replace the trees with the same species and size per the approved plans prior to landscape warrantee period expiration. - Prior to warranty expiration, owner/owners representative to inspect all tree stakes. If the single trunk trees appear healthy and have an upright trunk, then remove the stakes. Also, at the time of this inspection by the owner/owners representative, remove all stakes from multi-trunk tree species. |
|
| 01/13/2025 | ENGR Engineering Final | Passed |