Permit: DP22-0206
Permit Details
Status:
Complete
Type:
Development Package
Address:
1610 W SAINT MARYS RD
Address NEW:
1610 W SAINT MARYS RD
Apply Date:
07/25/2022
Applicant:
Michael Epstein
Description:
Site/Grading : Starbucks - Silverbell and St. Mary's. New coffee shop with drive-thru.
Permit Reviews
Permit Number - DP22-0206
Permit Status: Complete
Permit Description: Site/Grading : Starbucks - Silverbell and St. Mary's. New coffee shop with drive-thru.
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 07/25/2022 | DEV PKG - OK TO SUBMIT | 08/10/2022 | COMPLETED |
| 08/10/2022 | DEV PKG | 09/02/2022 | COMPLETED |
| 12/12/2022 | DEVELOPMENT PACKAGE REVIEW v.1 | 01/11/2023 | APPROVED |
Outstanding Inspections
Permit Status: Complete
Permit Number: DP22-0206
Permite Description: Site/Grading : Starbucks - Silverbell and St. Mary's. New coffee shop with drive-thru.
Total Outstanding Inspections - 9
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 04/20/2023 | PDSD Engineering Division Pre-Construction SITE | N/A | Partial Pass | MET WITH EPSTEIN CONSTRUCTION FOR THE INITIAL PRE-CON, THIS WILL BE RESCHEDULED FOR TOMORROW WITH BRIAN BENEDON |
| 09/22/2023 | SITE - Zoning Violation | N/A | Not Applicable | |
| 09/22/2023 | SITE - SWPPP Violation Notice | N/A | Not Applicable | |
| 09/28/2023 | SITE - SWPPP Correction Notice | N/A | Not Applicable | |
| 10/03/2023 | SITE - Stormwater Setup and Controls | N/A | Partial Pass | |
| 10/13/2023 | ENGR - Drainage Structures | N/A | Partial Pass | provided side Ballard’s required per detail 801. Minimum 4 inch schedule 40 steel. Minimum 7 feet in length with 3 feet embedded. |
| 08/04/2023 | COT - ENGR - Stormwater | N/A | Partial Pass | |
| 01/08/2024 | NPPO Pre-Construction | N/A | Partial Pass | remove construction fencing, remove construction debris, light post installation southeast corner. sign poles in parking lot need signs. |
| 01/08/2024 | ENGR Engineering Final | N/A | Partial Pass | remove construction fencing, light pole install SEC, poles in parking need signs, remove construction debris. |
Completed Inspections
Permit Status: Complete
Permit Number: DP22-0206
Permit Description: Site/Grading : Starbucks - Silverbell and St. Mary's. New coffee shop with drive-thru.
Total Completed Inspections - 20