Inspection Status: Not Ready
Inspection History: ENGR - Drainage Structures
| Date |
Description |
Inspector |
Results |
Comments |
| 05/18/2023 |
ENGR - Drainage Structures |
|
Not Ready |
temporary fencing and track out protection in place. Rough grading. Building construction underway. No one on site at this time. Trash enclosure does not appear to be ready at this time. |
| 06/29/2023 |
ENGR - Drainage Structures |
|
Complete (Recurring) |
grading inspection. Building construction has started. Site has been rough graded. |
| 07/06/2023 |
ENGR - Drainage Structures |
|
Not Ready |
|
| 09/29/2023 |
ENGR - Drainage Structures |
|
Partial Pass |
Trash enclosure footings |
| 10/04/2023 |
ENGR - Drainage Structures |
|
Partial Pass |
Pre-grout |
| 10/06/2023 |
ENGR - Drainage Structures |
|
Partial Pass |
|
| 10/10/2023 |
ENGR - Drainage Structures |
|
Not Ready |
|
| 10/13/2023 |
ENGR - Drainage Structures |
|
Partial Pass |
provided side Ballard’s required per detail 801. Minimum 4 inch schedule 40 steel. Minimum 7 feet in length with 3 feet embedded. |
| 10/25/2023 |
ENGR - Drainage Structures |
|
Partial Pass |
|
| 11/21/2023 |
ENGR - Drainage Structures |
|
Passed |
|