Permit: DP21-0213
Permit Details
Apply Date:
08/17/2021
Applicant:
Lisa Bowers
Description:
*Revision #3 (plumbing) started 6/21/2024* Site/Grading/Swppp - The Bridges Sub-Area B-3, Lots 6,8, and 9.
Permit Reviews
Permit Number - DP21-0213
Permit Status: Issued
Permit Description: *Revision #3 (plumbing) started 6/21/2024* Site/Grading/Swppp - The Bridges Sub-Area B-3, Lots 6,8, and 9.
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
03/04/2022 | DEV PKG - RESUBMITTAL | 03/16/2022 | COMPLETED |
05/09/2022 | DEV PKG - OK TO SUBMIT | 06/13/2022 | COMPLETED |
06/13/2022 | REVISION - - 1ST | 07/12/2022 | COMPLETED |
08/19/2021 | DEV PKG - OK TO SUBMIT | 08/27/2021 | COMPLETED |
08/27/2021 | DEV PKG | 10/04/2021 | COMPLETED |
10/04/2022 | DEV PKG - OK TO SUBMIT | 10/11/2022 | ACTIVE |
12/30/2021 | DEV PKG - RESUBMITTAL | 03/03/2022 | COMPLETED |
10/28/2022 | DEVELOPMENT PACKAGE REVIEW v.1 | 11/02/2022 | REQUIRES RESUBMIT |
06/21/2024 | DEVELOPMENT PACKAGE NEW v.1 | 06/27/2024 | APPROVED |
11/29/2022 | DEVELOPMENT PACKAGE REVIEW v.2 | 12/15/2022 | APPROVED |
Outstanding Inspections
Permit Status: Issued
Permit Number: DP21-0213
Permite Description: *Revision #3 (plumbing) started 6/21/2024* Site/Grading/Swppp - The Bridges Sub-Area B-3, Lots 6,8, and 9.
Total Outstanding Inspections - 4
Last Inspection Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
05/16/2023 | TRSP - ROW - Final/Close-Out | N/A | Not Applicable | n/a per Dave Roberts |
03/02/2023 | ENGR Grading Final | N/A | Not Ready | COMPLETE ALL THE WORK THAT IS SHOWN ON THE APPROVED PLANS. PROVIDE REVISED DRAWINGS AS NEEDED FOR ALL CHANGES THAT HAVE BEEN MADE TO THIS SITES APPROVED SET OF DRAWINGS. THIS WILL INCLUDE BUT IS NOT LIMITED TO ALL LANDSCAPE ITEMS THAT EITHER ARE NOT COMPLETE OR INSTALLED CORRECTLY, OR STILL NEED TO BE INSTALLED, (WATER HARVESTING BASINS TOO SHALLOW, ADDED ROCK RIP RAP ON THE EAST AND NORTH SIDES OF THE SITE, MISSING PLANTERS IN THE SIDEWALK AREAS). COMPLETE ALL OF THE WORK FOR LOTS 8 AND 9 AS NOTED ON THE APPROVED PLANS. ENSURE THAT THIS REVISION WILL ALSO INCLUDE THE REMOVAL OF ANY AND ALL WORK FOR LOT #6 THAT WILL NOT BE COMPLETED PER THESE APPROVED PLANS. ADDITIONAL INSPECTIONS FOR THIS SITE WILL BE REQUIRED BEFORE IT IS POSSIBLE FOR APPLYING FOR A TCO FOR EITHER LOT #8 AND #9. |
02/16/2023 | SITE - Stormwater Follow-up | N/A | Complete (Recurring) | No concerns as of today |
03/02/2023 | PDSD Site/Engineering Division - Landscaping | N/A | Not Ready | COMPLETE ALL THE WORK THAT IS SHOWN ON THE APPROVED PLANS. PROVIDE REVISED DRAWINGS AS NEEDED FOR ALL CHANGES THAT HAVE BEEN MADE TO THIS SITES APPROVED SET OF DRAWINGS. THIS WILL INCLUDE BUT IS NOT LIMITED TO ALL LANDSCAPE ITEMS THAT EITHER ARE NOT COMPLETE OR INSTALLED CORRECTLY, OR STILL NEED TO BE INSTALLED, (WATER HARVESTING BASINS TOO SHALLOW, ADDED ROCK RIP RAP ON THE EAST AND NORTH SIDES OF THE SITE, MISSING PLANTERS IN THE SIDEWALK AREAS). COMPLETE ALL OF THE WORK FOR LOTS 8 AND 9 AS NOTED ON THE APPROVED PLANS. ENSURE THAT THIS REVISION WILL ALSO INCLUDE THE REMOVAL OF ANY AND ALL WORK FOR LOT #6 THAT WILL NOT BE COMPLETED PER THESE APPROVED PLANS. ADDITIONAL INSPECTIONS FOR THIS SITE WILL BE REQUIRED BEFORE IT IS POSSIBLE FOR APPLYING FOR A TCO FOR EITHER LOT #8 AND #9. |
Completed Inspections
Permit Status: Issued
Permit Number: DP21-0213
Permit Description: *Revision #3 (plumbing) started 6/21/2024* Site/Grading/Swppp - The Bridges Sub-Area B-3, Lots 6,8, and 9.
Total Completed Inspections - 17
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
03/02/2023 | SITE - SWPPP Violation Notice | Passed | N/A | |
03/02/2023 | SITE - SWPPP Correction Notice | Passed | N/A | |
03/02/2023 | SITE - Stormwater Setup and Controls | Passed | N/A | |
03/02/2023 | PDSD Engineering Division Pre-Construction SITE | Passed | N/A | |
03/02/2023 | COT - ENGR - Signage Final | Passed | N/A | |
03/02/2023 | PDSD Site/Engineering Division - NPPO | Passed | NA/ | |
03/02/2023 | ENGR - Drainage Structures | Passed | N/A | |
03/02/2023 | COT - SITE - Zoning Intermediate | Passed | N/A | |
03/02/2023 | COT - FCON - Fire - Final | Passed | ||
03/02/2023 | SITE - Zoning Final | Passed | N/A | |
03/09/2023 | COT - ENGR - Stormwater | Passed | ||
03/09/2023 | Final inspection to ensure all landscape and water harvesting SITE | Passed | ||
03/09/2023 | ENGR Grading Final | Passed | ||
03/15/2023 | SITE - Stormwater Follow-up | Passed | ||
03/15/2023 | PDSD Site/Engineering Division - Landscaping | Passed | ||
03/15/2023 | SITE - Stormwater Final Inspection | Passed | ||
04/12/2023 | ENGR Engineering Final | Passed |