Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Inspection History Details
Inspection Status: Not Ready
Inspection History: ENGR Engineering Final
Permit Number - DP21-0213
Inspection Description - ENGR Engineering Final
Inspection Status - Not Ready
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
10/27/2022 | ENGR Engineering Final | Not Ready | ||
03/02/2023 | ENGR Engineering Final | Not Ready | COMPLETE ALL THE WORK THAT IS SHOWN ON THE APPROVED PLANS. PROVIDE REVISED DRAWINGS AS NEEDED FOR ALL CHANGES THAT HAVE BEEN MADE TO THIS SITES APPROVED SET OF DRAWINGS. THIS WILL INCLUDE BUT IS NOT LIMITED TO ALL LANDSCAPE ITEMS THAT EITHER ARE NOT COMPLETE OR INSTALLED CORRECTLY, OR STILL NEED TO BE INSTALLED, (WATER HARVESTING BASINS TOO SHALLOW, ADDED ROCK RIP RAP ON THE EAST AND NORTH SIDES OF THE SITE, MISSING PLANTERS IN THE SIDEWALK AREAS). COMPLETE ALL OF THE WORK FOR LOTS 8 AND 9 AS NOTED ON THE APPROVED PLANS. ENSURE THAT THIS REVISION WILL ALSO INCLUDE THE REMOVAL OF ANY AND ALL WORK FOR LOT #6 THAT WILL NOT BE COMPLETED PER THESE APPROVED PLANS. ADDITIONAL INSPECTIONS FOR THIS SITE WILL BE REQUIRED BEFORE IT IS POSSIBLE FOR APPLYING FOR A TCO FOR EITHER LOT #8 AND #9. |
|
03/09/2023 | ENGR Engineering Final | Partial Pass | Landscaping is not completed there’s trees and shrubbery and DG and the fencing on the northside has not been installed | |
03/09/2023 | ENGR Engineering Final | Passed | ||
03/15/2023 | ENGR Engineering Final | Partial Pass | The railing on the north side of the building first watch still need to be installed | |
04/12/2023 | ENGR Engineering Final | Passed |