Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.

Permit: DP21-0213

Parcel: 132131280


Addresses:

3434 S KINO PW


Inspection Status: Not Ready

Inspection History: ENGR Grading Final

Permit Number - DP21-0213

Inspection Description - ENGR Grading Final

Inspection Status - Not Ready

Date Description Inspector Results Comments
10/27/2022 ENGR Grading Final Not Ready
10/27/2022 ENGR Grading Final Not Ready
10/27/2022 ENGR Grading Final Not Ready
10/11/2022 ENGR Grading Final MHERNANDEZ Continued Entered by NGARCIA3 - CN /INSTALLING ADOT COLLAR FOR 18" RCP 3460 S KINO PW
10/11/2022 ENGR Grading Final MHERNANDEZ Continued Entered by NGARCIA3 - CN /INSTALLING ADOT COLLAR FOR 18" RCP 3456 S KINO PW
10/11/2022 ENGR Grading Final MHERNANDEZ Continued Entered by NGARCIA3 - CN /INSTALLING ADOT COLLAR FOR 18" RCP 3450 S KINO PW
10/11/2022 ENGR Grading Final MHERNANDEZ Continued Entered by NGARCIA3 - CN /INSTALLING ADOT COLLAR FOR 18" RCP 3434 S KINO PW
09/30/2022 ENGR Grading Final DROBERTS Partial Approval Entered by RSALDAT1 - PARTIAL, OK TO POUR THE FLOOR SLAB OF THE EASTERN TRASH ENCLOSURE
09/30/2022 ENGR Grading Final DROBERTS Partial Approval Entered by RSALDAT1 - PARTIAL, OK TO POUR THE FLOOR SLAB OF THE EASTERN TRASH ENCLOSURE
09/30/2022 ENGR Grading Final DROBERTS Partial Approval Entered by RSALDAT1 - PARTIAL, OK TO POUR THE FLOOR SLAB OF THE EASTERN TRASH ENCLO
09/30/2022 ENGR Grading Final DROBERTS Partial Approval Entered by RSALDAT1 - PARTIAL, OK TO POUR THE FLOOR SLAB OF THE EASTERN TRASH ENCLOSURE
09/23/2022 ENGR Grading Final DROBERTS Partial Approval Entered by NGARCIA3 - IS PARTIAL PROVIDE ADDITIONAL CHAIRS FOR THE REBAR AND PHOTOS AFTER THEY ARE PLACED 3460 S KINO PW
09/23/2022 ENGR Grading Final DROBERTS Partial Approval Entered by NGARCIA3 - IS PARTIAL PROVIDE ADDITIONAL CHAIRS FOR THE REBAR AND PHOTOS AFTER THEY ARE PLACED 3456 S KINO PW
09/23/2022 ENGR Grading Final DROBERTS Partial Approval Entered by NGARCIA3 - IS PARTIAL LOOKED AT THE SIDEWALKS FOR FUTURE POURS AND TREE WELL BLOCKOUTS 3450 S KINO PW
09/23/2022 ENGR Grading Final DROBERTS Partial Approval Entered by NGARCIA3 - IS PARTIAL LOOKED AT THE SIDEWALKS FOR FUTURE POURS AND TREE WELL BLOCKOUTS 3434 S KINO PW
08/15/2022 ENGR Grading Final MHERNANDEZ Continued Entered by VVERA1 - CN/ GOOD TO GROUT FOR THE TRASH BIN .TWO OF THEM
07/26/2022 ENGR Grading Final MHERNANDEZ Continued Entered by NGARCIA3 - CN /REBAR INSPECTION FOR TRASH BIN FOOTER 3460 S KINO PW
07/26/2022 ENGR Grading Final MHERNANDEZ Continued Entered by NGARCIA3 - CN /REBAR INSPECTION FOR TRASH BIN FOOTER 3450 S KINO PW
07/26/2022 ENGR Grading Final MHERNANDEZ Continued Entered by NGARCIA3 - CN /INSPECTION FOR TRASH BIN FOOTER 3456 S KINO PW
07/26/2022 ENGR Grading Final MHERNANDEZ Continued Entered by NGARCIA3 - CN /REBAR INSPECTION FOR TRASH BIN FOOTER 3434 S KINO PW
02/16/2023 ENGR Grading Final Partial Pass There is some grading that need to be done on lot six
03/02/2023 ENGR Grading Final Not Ready COMPLETE ALL THE WORK THAT IS SHOWN ON THE APPROVED PLANS. PROVIDE REVISED DRAWINGS AS NEEDED FOR ALL CHANGES THAT HAVE BEEN MADE TO THIS SITES APPROVED SET OF DRAWINGS. THIS WILL INCLUDE BUT IS NOT LIMITED TO ALL LANDSCAPE ITEMS THAT EITHER ARE NOT COMPLETE OR INSTALLED CORRECTLY, OR STILL NEED TO BE INSTALLED, (WATER HARVESTING BASINS TOO SHALLOW, ADDED ROCK RIP RAP ON THE EAST AND NORTH SIDES OF THE SITE, MISSING PLANTERS IN THE SIDEWALK AREAS). COMPLETE ALL OF THE WORK FOR LOTS 8 AND 9 AS NOTED ON THE APPROVED PLANS. ENSURE THAT THIS REVISION WILL ALSO INCLUDE THE REMOVAL OF ANY AND ALL WORK FOR LOT #6 THAT WILL NOT BE COMPLETED PER THESE APPROVED PLANS.

ADDITIONAL INSPECTIONS FOR THIS SITE WILL BE REQUIRED BEFORE IT IS POSSIBLE FOR APPLYING FOR A TCO FOR EITHER LOT #8 AND #9.
03/02/2023 ENGR Grading Final Not Ready COMPLETE ALL THE WORK THAT IS SHOWN ON THE APPROVED PLANS. PROVIDE REVISED DRAWINGS AS NEEDED FOR ALL CHANGES THAT HAVE BEEN MADE TO THIS SITES APPROVED SET OF DRAWINGS. THIS WILL INCLUDE BUT IS NOT LIMITED TO ALL LANDSCAPE ITEMS THAT EITHER ARE NOT COMPLETE OR INSTALLED CORRECTLY, OR STILL NEED TO BE INSTALLED, (WATER HARVESTING BASINS TOO SHALLOW, ADDED ROCK RIP RAP ON THE EAST AND NORTH SIDES OF THE SITE, MISSING PLANTERS IN THE SIDEWALK AREAS). COMPLETE ALL OF THE WORK FOR LOTS 8 AND 9 AS NOTED ON THE APPROVED PLANS. ENSURE THAT THIS REVISION WILL ALSO INCLUDE THE REMOVAL OF ANY AND ALL WORK FOR LOT #6 THAT WILL NOT BE COMPLETED PER THESE APPROVED PLANS.

ADDITIONAL INSPECTIONS FOR THIS SITE WILL BE REQUIRED BEFORE IT IS POSSIBLE FOR APPLYING FOR A TCO FOR EITHER LOT #8 AND #9.
03/02/2023 ENGR Grading Final Not Ready COMPLETE ALL THE WORK THAT IS SHOWN ON THE APPROVED PLANS. PROVIDE REVISED DRAWINGS AS NEEDED FOR ALL CHANGES THAT HAVE BEEN MADE TO THIS SITES APPROVED SET OF DRAWINGS. THIS WILL INCLUDE BUT IS NOT LIMITED TO ALL LANDSCAPE ITEMS THAT EITHER ARE NOT COMPLETE OR INSTALLED CORRECTLY, OR STILL NEED TO BE INSTALLED, (WATER HARVESTING BASINS TOO SHALLOW, ADDED ROCK RIP RAP ON THE EAST AND NORTH SIDES OF THE SITE, MISSING PLANTERS IN THE SIDEWALK AREAS). COMPLETE ALL OF THE WORK FOR LOTS 8 AND 9 AS NOTED ON THE APPROVED PLANS. ENSURE THAT THIS REVISION WILL ALSO INCLUDE THE REMOVAL OF ANY AND ALL WORK FOR LOT #6 THAT WILL NOT BE COMPLETED PER THESE APPROVED PLANS.

ADDITIONAL INSPECTIONS FOR THIS SITE WILL BE REQUIRED BEFORE IT IS POSSIBLE FOR APPLYING FOR A TCO FOR EITHER LOT #8 AND #9.
03/02/2023 ENGR Grading Final Not Ready COMPLETE ALL THE WORK THAT IS SHOWN ON THE APPROVED PLANS. PROVIDE REVISED DRAWINGS AS NEEDED FOR ALL CHANGES THAT HAVE BEEN MADE TO THIS SITES APPROVED SET OF DRAWINGS. THIS WILL INCLUDE BUT IS NOT LIMITED TO ALL LANDSCAPE ITEMS THAT EITHER ARE NOT COMPLETE OR INSTALLED CORRECTLY, OR STILL NEED TO BE INSTALLED, (WATER HARVESTING BASINS TOO SHALLOW, ADDED ROCK RIP RAP ON THE EAST AND NORTH SIDES OF THE SITE, MISSING PLANTERS IN THE SIDEWALK AREAS). COMPLETE ALL OF THE WORK FOR LOTS 8 AND 9 AS NOTED ON THE APPROVED PLANS. ENSURE THAT THIS REVISION WILL ALSO INCLUDE THE REMOVAL OF ANY AND ALL WORK FOR LOT #6 THAT WILL NOT BE COMPLETED PER THESE APPROVED PLANS.

ADDITIONAL INSPECTIONS FOR THIS SITE WILL BE REQUIRED BEFORE IT IS POSSIBLE FOR APPLYING FOR A TCO FOR EITHER LOT #8 AND #9.
03/09/2023 ENGR Grading Final Passed
03/09/2023 ENGR Grading Final Passed
03/09/2023 ENGR Grading Final Passed
03/09/2023 ENGR Grading Final Passed
12/15/2022 ENGR Grading Final Complete (Recurring) Excavating for the footers and the walls of the building have not started grading for the parking lot yet inform the contractor Call on for inspections every two weeks