Permit Details

Status:
Complete
Type:
Development Package
Address:
3434 S KINO PW
Address NEW:
3434 S KINO PW
Apply Date:
04/13/2021
Applicant:
Description:
Site/Grading - Circle K at The Bridges, Sub-Area B-3. Fuel canopy, roadway, median.

Permit Reviews

Permit Number - DP21-0094
Permit Status: Complete
Permit Description: Site/Grading - Circle K at The Bridges, Sub-Area B-3. Fuel canopy, roadway, median.
Start Date Submittal Complete Date Status  
04/13/2021 DEV PKG - OK TO SUBMIT 04/15/2021 COMPLETED Review Details
04/15/2021 DEV PKG 06/04/2021 COMPLETED Review Details
08/04/2021 DEV PKG - RESUBMITTAL 09/09/2021 COMPLETED Review Details
11/23/2021 DEV PKG - RESUBMITTAL 01/03/2022 COMPLETED Review Details

Outstanding Inspections

Permit Status: Complete
Permit Number: DP21-0094
Permite Description: Site/Grading - Circle K at The Bridges, Sub-Area B-3. Fuel canopy, roadway, median.
Total Outstanding Inspections - 2
Last Inspection Date Description Inspector Results Comments
01/10/2023 SITE - Stormwater Follow-up N/A Complete (Recurring) {Activity date: 09/27/2022; Status: Continued; Inspector: DROBERTS; Comment: Entered by VVERA1 - IS CONTINUED, NO CONCERNS AT THIS TIME} ; {Activity date: 08/26/2022; Status: Continued; Inspector: BBENEDDON; Comment: Entered by NGARCIA3 - Continued. Minor track out noted.}
09/27/2022 ENGR Grading Final N/A Scheduled {Activity date: 09/27/2022; Status: Continued; Inspector: DROBERTS; Comment: Entered by VVERA1 - IS CONTINUED, LOOKED AT APPROXIMATELY 20 FEET OF 12 INCH DRAINAGE PIPE WEST OF THE FUEL ISLAND SOUTH TOWARDS THE BUILDING} ; {Activity date: 08/26/2022; Status: Partial Approval; Inspector: BBENEDDON; Comment: Entered by NGARCIA3 - Partially approved. 18 inch HDPE as shown. Paul with Circle K at 480-430-1759. Post SWPPP information with address. Schedule Stormwater inspections biweekly. Schedule 09185, Grading intermediate inspections as needed for all work shown on civil drawings. Schedule 09152 Stormwater controls inspection. Provide contact information on scheduling inspections.
}

Completed Inspections

Permit Status: Complete
Permit Number: DP21-0094
Permit Description: Site/Grading - Circle K at The Bridges, Sub-Area B-3. Fuel canopy, roadway, median.
Total Completed Inspections - 2
Date Description Inspector Results Comments
08/26/2022 PDSD Engineering Division Pre-Construction SITE Passed {Activity date: 08/26/2022; Status: Approved; Inspector: BBENEDDON; Comment: Entered by NGARCIA3 - Approved. Paul with Circle K at 480-430-1759. Post SWPPP information with address. Schedule Stormwater inspections biweekly. Schedule 09185, Grading intermediate inspections as needed for all work shown on civil drawings. Schedule 09152 Stormwater controls inspection. Provide contact information on scheduling inspections. Days excavating on site.
} ; {Activity date: 08/10/2022; Status: Continued; Inspector: MHERNANDEZ; Comment: Entered by NGARCIA3 - CN./ INFORMED THE CONTRACTOR THAT THERE IS THREE NUMBER 4 BARS AT THE CORNER AND TWO NUMBER 4 BARS AT ENDSOR FRONT.
ALSO TO CALL IN FOR INSPECTION EVERY TWO.

}
03/09/2023 ENGR Engineering Final Passed N/A

Scheduled Inspections

Scheduled Inspections - DP21-0094
Status: Complete
Description: Site/Grading - Circle K at The Bridges, Sub-Area B-3. Fuel canopy, roadway, median.
Scheduled Date Description Entered By Entered Date
01/10/2023 ENGR Grading Final Scheduled
For information about today’s scheduled inspections please refer to the PDSD Daily Inspections Dashboards (Desktop) PDSD Daily Inspections Dashboards (Mobile) .