Permit Details

Status:
Complete
Type:
Development Package
Address:
3434 S KINO PW
Apply Date:
04/13/2021
Applicant:
Description:
Site/Grading - Circle K at The Bridges, Sub-Area B-3. Fuel canopy, roadway, median.

Permit Reviews

Permit Number - DP21-0094
Permit Status: Complete
Permit Description: Site/Grading - Circle K at The Bridges, Sub-Area B-3. Fuel canopy, roadway, median.
Start Date Submittal Complete Date Status  
04/13/2021 DEV PKG - OK TO SUBMIT 04/15/2021 COMPLETED Review Details
04/15/2021 DEV PKG 06/04/2021 COMPLETED Review Details
08/04/2021 DEV PKG - RESUBMITTAL 09/09/2021 COMPLETED Review Details
11/23/2021 DEV PKG - RESUBMITTAL 01/03/2022 COMPLETED Review Details

Outstanding Inspections

Permit Status: Complete
Permit Number: DP21-0094
Permite Description: Site/Grading - Circle K at The Bridges, Sub-Area B-3. Fuel canopy, roadway, median.
Total Outstanding Inspections - 2
Last Inspection Date Description Inspector Results Comments
01/10/2023 SITE - Stormwater Follow-up N/A Complete (Recurring) {Activity date: 09/27/2022; Status: Continued; Inspector: DROBERTS; Comment: Entered by VVERA1 - IS CONTINUED, NO CONCERNS AT THIS TIME} ; {Activity date: 08/26/2022; Status: Continued; Inspector: BBENEDDON; Comment: Entered by NGARCIA3 - Continued. Minor track out noted.}
09/27/2022 ENGR Grading Final N/A Scheduled {Activity date: 09/27/2022; Status: Continued; Inspector: DROBERTS; Comment: Entered by VVERA1 - IS CONTINUED, LOOKED AT APPROXIMATELY 20 FEET OF 12 INCH DRAINAGE PIPE WEST OF THE FUEL ISLAND SOUTH TOWARDS THE BUILDING} ; {Activity date: 08/26/2022; Status: Partial Approval; Inspector: BBENEDDON; Comment: Entered by NGARCIA3 - Partially approved. 18 inch HDPE as shown. Paul with Circle K at 480-430-1759. Post SWPPP information with address. Schedule Stormwater inspections biweekly. Schedule 09185, Grading intermediate inspections as needed for all work shown on civil drawings. Schedule 09152 Stormwater controls inspection. Provide contact information on scheduling inspections.
}

Completed Inspections

Permit Status: Complete
Permit Number: DP21-0094
Permit Description: Site/Grading - Circle K at The Bridges, Sub-Area B-3. Fuel canopy, roadway, median.
Total Completed Inspections - 2
Date Description Inspector Results Comments
08/26/2022 PDSD Engineering Division Pre-Construction SITE Passed {Activity date: 08/26/2022; Status: Approved; Inspector: BBENEDDON; Comment: Entered by NGARCIA3 - Approved. Paul with Circle K at 480-430-1759. Post SWPPP information with address. Schedule Stormwater inspections biweekly. Schedule 09185, Grading intermediate inspections as needed for all work shown on civil drawings. Schedule 09152 Stormwater controls inspection. Provide contact information on scheduling inspections. Days excavating on site.
} ; {Activity date: 08/10/2022; Status: Continued; Inspector: MHERNANDEZ; Comment: Entered by NGARCIA3 - CN./ INFORMED THE CONTRACTOR THAT THERE IS THREE NUMBER 4 BARS AT THE CORNER AND TWO NUMBER 4 BARS AT ENDSOR FRONT.
ALSO TO CALL IN FOR INSPECTION EVERY TWO.

}
03/09/2023 ENGR Engineering Final Passed N/A

Scheduled Inspections

Scheduled Inspections - DP21-0094
Status: Complete
Description: Site/Grading - Circle K at The Bridges, Sub-Area B-3. Fuel canopy, roadway, median.
Scheduled Date Description Entered By Entered Date
01/10/2023 ENGR Grading Final Scheduled
For information about today’s scheduled inspections please refer to the PDSD Daily Inspections Dashboards (Desktop) PDSD Daily Inspections Dashboards (Mobile) .

Documents

File Name Document Type  
APPROVED DEVELOPMENT PACKAGE.PDF DEVELOPMENT PACKAGE VIEW
CONTRACTORS LETTER OF INTENT.PDF DOCUMENTS VIEW
FUGITIVE DUST ACTIVITY PERMIT, 3540 S. KINO PARKWAY.PDF DOCUMENTS VIEW
PERMIT.PDF DOCUMENTS VIEW
PIMA COUNTY REG FLOOD CONTROL, FACILITY IMPACT PERMIT.PDF DOCUMENTS VIEW
PROJECT ADDRESS DISCREPANCY, DP21-0094.PDF DOCUMENTS VIEW
TAA APPROVAL LETTER, 12.20.21.PDF DOCUMENTS VIEW
FAA APPROVAL FOR BUILDING.PDF DOCUMENTS VIEW
FAA APPROVAL FOR CRANE.PDF DOCUMENTS VIEW
FAA APPROVAL FOR CANOPY.PDF DOCUMENTS VIEW
ONLINE SUBMITTAL PAGE, RECVD 11.19.21.PDF DOCUMENTS VIEW
COMMENT RESPONSE LETTER, 11.23.21.PDF DOCUMENTS VIEW
PIMA COUNTY DRAINAGE EASEMENT, RECORDED ON 09.01.21.PDF DOCUMENTS VIEW
STORMWATER MANAGEMENT.PDF DOCUMENTS VIEW
WATERHARVESTING OK_STEPHEN BLOOD, ENGINEER, EMAIL.PDF DOCUMENTS VIEW
TAA REVIEW COMMENTS, 08.23.21.PDF DOCUMENTS VIEW
FINAL DRAINAGE REPORT, 03.22.22.PDF DOCUMENTS VIEW
ADOT ATTACHED PLAN SHEET, REVIEW COMMENTS, 08.06.21.PDF DOCUMENTS VIEW
COMMENT RESPONSE LETTER, 08.04.21.PDF DOCUMENTS VIEW
PIMA COUNTY DRAINAGE EASEMENT_UNSIGNED.PDF DOCUMENTS VIEW
ONLINE SUBMITTAL PAGE, RECVD 08.03.21.PDF DOCUMENTS VIEW
TEP REDLINE MAP, 04.29.21.PDF DOCUMENTS VIEW
TEP FACILITIES MAP, 04.29.21.PDF DOCUMENTS VIEW
TDOT PLANS, 04.19.21.PDF DOCUMENTS VIEW
APPLICATION, DEV PKG.PDF DOCUMENTS VIEW
ONLINE SUBMITTAL APPLICATION, RECVD 04.09.21.PDF DOCUMENTS VIEW
FIRE FLOW ANALYSIS RESULTS, TUCSON WATER.PDF DOCUMENTS VIEW
DRC_BRIDGES_APPROVAL, DESIGN REVIEW COMM.PDF DOCUMENTS VIEW
GEOTECHNICAL REPORT.PDF DOCUMENTS VIEW