Permit: DP21-0060
Permit Details
Status:
Inspections
Type:
Development Package
Address:
4855 S WINGATE BL
Address NEW:
4855 S WINGATE BL
Apply Date:
03/05/2021
Applicant:
Description:
Revision 4 - Tentative Plat/FLD - Bella Tierra, Phase 3. An FLD Subdivision, Lots 1-78 and Common Areas A-1 (open
Permit Reviews
Permit Number - DP21-0060
Permit Status: Inspections
Permit Description: Revision 4 - Tentative Plat/FLD - Bella Tierra, Phase 3. An FLD Subdivision, Lots 1-78 and Common Areas A-1 (open
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 01/25/2022 | DEV PKG - OK TO SUBMIT | 02/07/2022 | COMPLETED |
| 03/05/2021 | DEV PKG - OK TO SUBMIT | 03/11/2021 | COMPLETED |
| 03/11/2021 | TENTATIVE PLAT REVIEW | 05/12/2021 | COMPLETED |
| 05/05/2022 | DEV PKG - OK TO SUBMIT | 05/24/2022 | COMPLETED |
| 05/21/2021 | TENTATIVE PLAT REVIEW | 07/07/2021 | COMPLETED |
| 05/24/2022 | REVISION - - 1ST | 07/14/2022 | COMPLETED |
| 07/09/2021 | TENTATIVE PLAT REVIEW | 08/05/2021 | COMPLETED |
| 08/03/2022 | DEV PKG - OK TO SUBMIT | 08/19/2022 | COMPLETED |
| 08/19/2022 | REVISION - - 2ND | 10/10/2022 | ACTIVE |
| 11/03/2023 | DEVELOPMENT PACKAGE REVIEW v.2 | 11/08/2023 | APPROVED |
| 09/11/2023 | DEVELOPMENT PACKAGE REVIEW v.1 | 10/18/2023 | REQUIRES RESUBMIT |
| 11/12/2024 | DEVELOPMENT PACKAGE NEW REVISION v.2 | 12/23/2024 | APPROVED |
| 10/27/2022 | DEVELOPMENT PACKAGE REVIEW v.1 | 12/06/2022 | APPROVED |
| 10/30/2024 | DEVELOPMENT PACKAGE NEW REVISION v.1 | 11/06/2024 | REQUIRES RESUBMIT |
Outstanding Activity Conditions
Permit Number - DP21-0060
Permit Status: Inspections
Permit Description: Revision 4 - Tentative Plat/FLD - Bella Tierra, Phase 3. An FLD Subdivision, Lots 1-78 and Common Areas A-1 (open
Total Outstanding Activity Conditions - 2
| Date | Name |
|---|---|
| 11/22/2023 | THIS DOES NOT APPLY |
| 11/22/2023 | THIS DOES NOT APPLY |
Outstanding Inspections
Permit Status: Inspections
Permit Number: DP21-0060
Permite Description: Revision 4 - Tentative Plat/FLD - Bella Tierra, Phase 3. An FLD Subdivision, Lots 1-78 and Common Areas A-1 (open
Total Outstanding Inspections - 8
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 12/21/2021 | SITE - Stormwater Setup and Controls | N/A | Complete (Recurring) | {Activity date: 12/21/2021; Status: Continued; Inspector: MHERNANDEZ; Comment: Entered by RSALDAT1 - CN /STORMWATER,… NOT INSTALLED YET} |
| 10/26/2022 | PDSD Site/Engineering Division - NPPO | N/A | Not Ready | |
| 10/27/2022 | COT - ENGR - Signage Final | N/A | Not Ready | |
| 10/26/2022 | SITE - Stormwater Follow-up | N/A | Not Ready | |
| 04/03/2025 | Grading Progress ENGR | N/A | Partial Pass | See checklist item. |
| 04/02/2025 | COT - FCON - Fire - Final | N/A | Not Applicable | |
| 04/04/2025 | ENGR Grading Final | N/A | Not Ready | |
| 10/09/2025 | PDSD Site/Engineering Division - Landscaping | N/A | Not Ready | Repair leaky Backflow preventer at southside of red Bluff cul-de-sac. Majority of Occotillo are dead in subdivision. Along S Verdin Valley, Red Bluff Cul-de-sac and in B-1 Basin Occotillos need to be replaced. Creosote and Brittle brush need to go into Basin Retention basin at Irvington Road. Repair disturbed area at corner of Wingate and Irvington between retention basin and pathway. |
Completed Inspections
Permit Status: Inspections
Permit Number: DP21-0060
Permit Description: Revision 4 - Tentative Plat/FLD - Bella Tierra, Phase 3. An FLD Subdivision, Lots 1-78 and Common Areas A-1 (open
Total Completed Inspections - 5
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 11/02/2021 | PDSD Engineering Division Pre-Construction SITE | Passed | {Activity date: 11/02/2021; Status: Approved; Inspector: DROBERTS; Comment: Entered by NGARCIA3 - APPROVED, I MET WITH THE REPRESENTATIVES FROM THE DEVELOPER, CONTRACTOR, ENGINEER AND LOOKED OVER THE FUTURE. THE DEVELOPER AND CONTRACTOR WILL DELAY WORK TO ALLOW THEM TO CALL IN AN INVESTIGATOR TO LOOK AT A LOCATION WERE THEY HAVE FOUND ACROSS WITHIN THE SITE. ONCE THIS HAS BEEN CHECKED THEY WILL LET ME KNOW THAT THEY ARE CONTINUING WITH THE WORK, CURRENTLY THEY HAVE CLEARED THE SITE OF ALL VEGETATION. I WILL BE CHECKING THE NPPO TO VERIFY THAT THERE WAS NO PLANTS CALLED TO BE PRESERVED IN PLACE, OR TRANSPLANTED ON SITE. } |
|
| 10/23/2025 | ENGR Engineering Final | Passed | ||
| 10/23/2025 | Final inspection to ensure all landscape and water harvesting SITE | Passed | ||
| 10/23/2025 | SITE - Stormwater Final Inspection | Passed | ||
| 10/23/2025 | SITE - Zoning Final | Passed |