Permit: DP20-0237
Permit Details
Apply Date:
11/16/2020
Applicant:
Description:
Site/Grading/Swpp - Industrial Building at Bilby.
Permit Reviews
Permit Number - DP20-0237
Permit Status: Issued
Permit Description: Site/Grading/Swpp - Industrial Building at Bilby.
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 01/12/2022 | REVISION - - 1ST | 02/14/2022 | COMPLETED |
| 05/03/2021 | DEV PKG - RESUBMITTAL | 05/21/2021 | COMPLETED |
| 06/03/2022 | DEV PKG - OK TO SUBMIT | 06/21/2022 | COMPLETED |
| 06/21/2022 | REVISION - - 2ND | 06/29/2022 | COMPLETED |
| 08/13/2021 | DEV PKG - OK TO SUBMIT | 09/01/2021 | COMPLETED |
| 09/01/2021 | REVISION - - 1ST | 10/13/2021 | COMPLETED |
| 11/16/2020 | DEV PKG - OK TO SUBMIT | 11/19/2020 | COMPLETED |
| 11/19/2020 | DEV PKG | 01/27/2021 | COMPLETED |
Outstanding Inspections
Permit Status: Issued
Permit Number: DP20-0237
Permite Description: Site/Grading/Swpp - Industrial Building at Bilby.
Total Outstanding Inspections - 8
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 09/03/2021 | SITE - Stormwater Setup and Controls | N/A | Complete (Recurring) | {Activity date: 09/03/2021; Status: Continued; Inspector: DROBERTS; Comment: Entered by VVERA1 - 9152 (STORMWATER INSTALL OF CONTROLS) NO CONCERNS AT THIS TIME } |
| 08/15/2022 | SITE - Stormwater Follow-up | N/A | Complete (Recurring) | {Activity date: 08/15/2022; Status: Continued; Inspector: MHERNANDEZ; Comment: Entered by VVERA1 - CN/ NO CHANGES} ; {Activity date: 07/08/2022; Status: Continued; Inspector: DROBERTS; Comment: Entered by RSALDAT1 - CONTINUED, NO CONCERNS AT THIS TIME.} ; {Activity date: 12/21/2021; Status: Continued; Inspector: MHERNANDEZ; Comment: Entered by RSALDAT1 - CN GOOD FOR TODAY} ; {Activity date: 11/01/2021; Status: Continued; Inspector: DROBERTS; Comment: Entered by VVERA1 - IS CONTINUED, NO CONCERNS AT THIS TIME.} |
| 10/27/2022 | PDSD Site/Engineering Division - Landscaping | N/A | Not Ready | |
| 10/26/2022 | PDSD Site/Engineering Division - NPPO | N/A | Not Ready | |
| 10/26/2022 | SITE - Stormwater Final Inspection | N/A | Not Ready | |
| 10/26/2022 | PDSD Engineering Division Pre-Construction SITE | N/A | Not Ready | |
| 10/27/2022 | COT - ENGR - Signage Final | N/A | Not Ready | |
| 11/22/2022 | ENGR Grading Final | N/A | Complete (Recurring) | Continuing to install HD pipe |
Completed Inspections
Permit Status: Issued
Permit Number: DP20-0237
Permit Description: Site/Grading/Swpp - Industrial Building at Bilby.
Total Completed Inspections - 2
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 05/29/2024 | ENGR Engineering Final | Passed | No issues can be seen to impede the passing of this inspection. Solar window and door has been here since 2022 and operates out to both warehouses. |
|
| 05/29/2024 | ENGR Grading Final | Passed | No issues can be seen, grade all looks like it was done correctly and all drainage is positive. Solar window and door has been here since 2022 and operates out to both warehouses. |