Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you cannot find what you are looking for please submit a records request.

Permit: DP20-0237

Parcel: 14027042C


Addresses:

2622 E BILBY RD

Inspection Status: Not Ready

Inspection History: ENGR Grading Final

Date Description Inspector Results Comments
10/27/2022 ENGR Grading Final Not Ready
10/27/2022 ENGR Grading Final Not Ready
08/22/2022 ENGR Grading Final MHERNANDEZ Continued Entered by VVERA1 - CN NON COMPLIANCE THE LAYOUT FOR THE FLOOR IS ON 18” LAYOUT.
08/15/2022 ENGR Grading Final MHERNANDEZ Continued Entered by VVERA1 - CN /GROUT AT FOUR FOR TRASH BIN
07/20/2022 ENGR Grading Final MHERNANDEZ Continued Entered by VVERA1 - CN / rebar inspection for spillway.
07/15/2022 ENGR Grading Final DROBERTS Partial Approval Entered by RSALDAT1 - PARTIALLY APPROVED FOR THE DRAINAGE STRUCTURE LOCATED IN THE EASTERN HALF OF THE SOUTHERN PARKING LOT.
05/04/2022 ENGR Grading Final MHERNANDEZ Continued Entered by VVERA1 - CN GOOD TO POUR.THE FLOOR FOR LOADING DOCK FLOOR.
03/17/2022 ENGR Grading Final MHERNANDEZ Continued Entered by NGARCIA3 - CN/CONTRACTOR NOT ON SITE NEED TO RESCHEDULE
12/21/2021 ENGR Grading Final MHERNANDEZ Continued Entered by RSALDAT1 - CN / FAIL REBAR NON-COMPLIANCE WITH THE CITY OF TUCSON..RESCHEDULE FOR INSPECTION
11/01/2021 ENGR Grading Final DROBERTS Not ready for Inspection Entered by VVERA1 - IS NOT READY, THE REBAR IS TO BE CALLED IN UNDER THE COMBO PERMIT FOR THIS SITE.
09/03/2021 ENGR Grading Final DROBERTS Continued Entered by VVERA1 - 9181 (GRADING - REBAR) IS CONTINUED AT THIS TIME
10/12/2022 ENGR Grading Final MHERNANDEZ Continued Entered by VVERA1 - CN / INSTALLING DRAINAGE CHAMBERS.
09/30/2022 ENGR Grading Final DROBERTS Partial Approval Entered by RSALDAT1 - PARTIAL AT THIS TIME, WORK HAS BEEN CHECKED AND CAN CONTINUE WIT THE 2 RUNS OF THE DETENTION/RETENTION BASIN ON THE WEST SIDE OF THE PROJECT ADJACENT TO THE BUILDING
09/19/2022 ENGR Grading Final MHERNANDEZ Continued Entered by VVERA1 - CN /BACKFILLING THE STORM DRAIN CHAMBERS.
09/14/2022 ENGR Grading Final MHERNANDEZ Continued Entered by VVERA1 - CN INSTALLING DRAINAGE CHAMBERS.
09/08/2022 ENGR Grading Final DROBERTS Partial Approval Entered by NGARCIA3 - IS PARTIAL,CREWS WORKING ON INSTALLING THE UNDERGROUND RETENTION/DETENTION BASIN. I HAVE LOOKED AT THE SIX TUBES ACROSS FOR APPROXIMATELY 40 PLUS FEET AND HAVE APPROVED PORTIONS THIS AREA TO BE BACKFILLED AS NEEDED. THEY WILL BE CALLING IN FOR ADDITIONAL INSPECTIONS WHILE THIS WORK CONTINUES FURTHER NORTH.
09/01/2022 ENGR Grading Final MHERNANDEZ Continued Entered by NGARCIA3 - CN/ CUTTING THE GRADING FOR THE CHAMBERS SYSTEM.
08/15/2022 ENGR Grading Final MHERNANDEZ Continued Entered by VVERA1 - CN / FOR TRASH BIN FLOOR.
07/26/2022 ENGR Grading Final MHERNANDEZ Continued Entered by NGARCIA3 - CN / REBAR FOR TRASH BIN NEED TWO REBAR AT THE END AND ONE IN THE CENTER.CONTRACTOR WILL SEND PHOTOS.
07/21/2022 ENGR Grading Final MHERNANDEZ Continued Entered by NGARCIA3 - CN / NO CHANGES FOR YESTERDAY GOOD.
07/19/2022 ENGR Grading Final MHERNANDEZ Continued Entered by NGARCIA3 - CN /NO READY FOR INSPECTION RESCHEDULE FOR TOMORROW MORNING.
07/08/2022 ENGR Grading Final DROBERTS Partial Approval Entered by RSALDAT1 - ) IS PARTIAL NO ONE ON SITE AT THIS TIME, CONTACTED PATRICK WITH RIO WEST WHO GAS ADVISED ME THAT THEY HAVE STARTED GRADING THE SOUTH END OF THE LOT. THEY WILL BE WORKING ON THE INSTALLATION OF THE UNDERGROUND DRAINAGE SYSTEM IN THE WEEKS TO COME SO HE WILL BE SCHEDULING INSPECTIONS DAILY TILL ALL OF THE WORK IS COMPLETE.
03/17/2022 ENGR Grading Final MHERNANDEZ Continued Entered by NGARCIA3 - CN
09/03/2021 ENGR Grading Final DROBERTS Not ready for Inspection Entered by VVERA1 - 9185 (GRADING - INTERMEDIATE) CREWS ARE WORKING ON INSTALLING CSP DRAINAGE PIPE ALONG THE WEST SIDE OF THE BUILDING SOUTH OF THE LOADING DOCKS. PREVIOUSLY THEY HAVE INSTALLED 3 DROP INLET STRUCTURES AND CONNECTING PIPE SOUTH OF THE LOADING DOCK AND HAVE BACKFILLED THE PIPES. CURRENTLY THEY HAVE INSTALLED 2 ADDITIONAL STRUCTURES AND WILL INSTALL A THIRD BY THE END OF THE DAY TODAY, ALONG WITH THE CONNECTING PIPES. THE GROUTING OF THE PIPES AND THE STRUCTURES WILL BE STARTED NEXT WEEK AND WILL BE INSPECTED BY MARTIN HERNANDEZ.
01/06/2023 ENGR Grading Final Partial Pass Complete the remaining work on this job site which will include general cleanup installation of the trash enclosure doors
05/29/2024 ENGR Grading Final Passed No issues can be seen, grade all looks like it was done correctly and all drainage is positive.
Solar window and door has been here since 2022 and operates out to both warehouses.
11/09/2022 ENGR Grading Final Complete (Recurring) Continuing to install drainage chambers
11/22/2022 ENGR Grading Final Complete (Recurring) Continuing to install HD pipe
11/23/2022 ENGR Grading Final Complete (Recurring) Continue to install drain chambers
12/06/2022 ENGR Grading Final Complete (Recurring) Backfilling the new chamber drainage pipe
12/07/2022 ENGR Grading Final Complete (Recurring) placing subgrade material for the new RoadThat’s being built
12/09/2022 ENGR Grading Final Complete (Recurring) CREWS WORKING ON PAVING THE NORTH PORTION OF THE SITE ON THE WESTERN HALF FOR THE EXISTING ROADWAY. THEY ARE ANTICIPATING HAVING THIS WORK COMPLETED BY MID WEEK NEXT WEEK.